Construction of North-South Expressway faces difficulties due to floods

Nhóm PV |

Prolonged rain and floods have caused many difficulties in the construction of the North-South Expressway in the Eastern phase of 2021-2025 through the North Central provinces of Ha Tinh, Quang Binh, and Quang Tri.

Stop asphalt paving, roadbed construction due to rain

According to Lao Dong Newspaper reporters, in the days after the storm, at the North-South expressway construction site, Ham Nghi - Vung Ang section through Tan Lam Huong commune (Thach Ha, Ha Tinh), many trucks, road rollers, and asphalt paving vehicles were idling. Floods and rains have caused temporary suspension of asphalt paving and foundation pouring, a common situation for contractors constructing expressways through Ha Tinh province over the past time.

Mr. Dang Dinh Duyen - Construction site commander of Xuan Truong Private Construction Company - the construction unit of package No. 11 of the Ham Nghi - Vung Ang section - said that heavy rain and floods in Ha Tinh have affected the company's construction progress.

At the Bai Vot - Ham Nghi expressway construction site, Mr. Tran Dinh Ngan - Construction Site Commander of Corporation 319 - Ministry of National Defense - said that the recent rain and floods have made the company's construction work difficult, forcing the temporary suspension of asphalt paving and bridge construction. "The rainy weather can only be used to construct the gravel roadbed, other work must wait until the rain stops and the weather is dry before it can be done" - Mr. Ngan shared.

In Quang Binh, according to Mr. Chu Van Long - Deputy Head of Project Management Division 4, Ho Chi Minh Road Project Management Board (investor of Van Ninh - Cam Lo Expressway Component Project), the weather has recently been unfavorable, so after September 26, the unit has just started to continue implementing the concrete contents, the earthwork cannot be done because the ground is wet.

In Quang Tri province, the Van Ninh - Cam Lo expressway is currently under construction with a length of 32.53km, starting in Vinh Linh district and ending in Cam Lo district at the intersection with National Highway 9. Mr. Mai Quy Khanh - Deputy Head of Project Management Division 4 of the Ho Chi Minh Road Project Management Board - said that the biggest concern now is the weather, because Quang Tri has entered the rainy and stormy season. It is forecasted that from now until the end of the year, many low pressure and storms are likely to affect Quang Tri, so the earthworks and leveling projects at newly handed-over locations will be very difficult.

Focus on volume compensation when the weather is good

According to Mr. Hoang Chien Thang - Executive Director of Thang Long Project Management Board, the investor of the North - South expressway project, Bai Vot - Ham Nghi section (Ha Tinh), the prolonged rainy and flooded weather has caused difficulties for expressway construction contractors, forcing them to stop construction when the weather is bad for the part of transporting materials for roadbed embankment and concrete pavement. To limit the impact of slow progress due to the weather, contractors are flexible in constructing suitable items that can be constructed during rainy and flooded weather.

Mr. Nguyen Khac Trung - Director of the North-South Expressway Project Management Board, Ham Nghi - Vung Ang section (Ha Tinh) - also informed that prolonged rain and floods have affected the contractor's construction of the roadbed earthworks, making construction impossible.

During rainy and windy times, contractors take advantage of the opportunity to construct suitable items, such as crushed stone for road foundations, iron parts for bridges and culverts, etc. "When the weather is favorable, we must concentrate maximum machinery and human resources to speed up the construction progress to compensate for the volume of the rainy and flood season," said Mr. Trung.

In Quang Binh, according to Mr. Chu Van Long - Deputy Head of Project Management Division 4, Ho Chi Minh Road Project Management Board - said that to minimize the impact of the weather at the end of the year, the board has directed the contractor to focus on construction in adverse weather conditions such as concrete structures. Currently, there are more than 1,400 officers, workers, operators, and about 700 locomotives and equipment of all kinds on the construction site.

According to Mr. Mai Quy Khanh - Deputy Head of Project Management Division 4, Ho Chi Minh Road Project Management Board, to complete the project before June 30, 2025 as directed by the Government, the board has urged contractors to work overtime, increase shifts, and mobilize human resources to speed up the progress as much as possible when the weather is favorable.

Nhóm PV
TIN LIÊN QUAN

Đường sắt cao tốc Bắc - Nam dự kiến hoàn thành năm 2035

Xuyên Đông |

Trong báo cáo mới đây của Bộ Giao thông Vận tải, Việt Nam phấn đấu hoàn thành đầu tư toàn tuyến đường sắt cao tốc Bắc - Nam trong năm 2035.

Chỉ đạo mới về đầu tư đoạn cao tốc Bắc - Nam phía Tây

Xuyên Đông |

Chính phủ vừa có chỉ đạo mới về dự án cao tốc Bắc - Nam phía Tây đoạn Gia Nghĩa - Chơn Thành.

Kiên quyết giải phóng mặt bằng thực hiện cao tốc Bắc - Nam

CÔNG SÁNG |

UBND huyện Lệ Thủy (tỉnh Quảng Bình) sẽ tiến hành cưỡng chế nếu các hộ dân không thực hiện đúng quy định, phương án giải phóng mặt bằng.

Giá vàng cao kỷ lục, chọn kênh đầu tư nào để tránh mạo hiểm?

Hoàng Xuyến - Việt Anh |

Theo các chuyên gia, trong bối cảnh giá vàng tăng cao, người dân nên cẩn trọng khi đầu tư vào vàng. Dự kiến, chứng khoán là một thị trường đầu tư tiềm năng.

Hàng trăm người chui rào đập thủy điện, đổ xô bắt cá khủng

HÀ ANH CHIẾN |

Đồng Nai - Hàng trăm người dân đổ xô xuống đập tràn của hồ Thủy điện Trị An để bắt cá khủng, kiếm tiền triệu.

Chưa rõ nguyên nhân hơn 40 người ở chung cư nghi ngộ độc

QUANG ĐẠI |

Nghệ An – Cơ quan chức năng đang tiếp tục xác minh nguyên nhân vụ hơn 40 người ở chung cư Golden City 3 (Nghi Phú, TP Vinh) có biểu hiện ngộ độc.

Thanh niên tử vong khi livestream cảnh báo sạt lở QL2

Lam Thanh |

Hà Giang - Vụ sạt lở trên QL2 đoạn qua xã Việt Vinh (huyện Bắc Quang) đã vùi lấp nhiều người và phương tiện.

Lực lượng chức năng căng mình phân luồng cầu phao Phong Châu

Tô Công |

Phú Thọ - Ngày 30.9, khi cầu phao Phong Châu thông xe, lưu lượng phương tiện đổ về rất đông, các lực lượng chức năng phải căng mình điều tiết giao thông.

North-South high-speed railway expected to be completed in 2035

Xuyên Đông |

In a recent report by the Ministry of Transport, Vietnam strives to complete investment in the entire North-South high-speed railway route by 2035.

New direction on investment in the western section of the North-South Expressway

Xuyên Đông |

The Government has just issued new instructions on the North-South Expressway project, western section Gia Nghia - Chon Thanh.

Resolutely clearing land for North-South expressway

CÔNG SÁNG |

The People's Committee of Le Thuy district (Quang Binh province) will carry out enforcement if households do not comply with regulations and site clearance plans.