Time of handover of the project for use

Xuyên Đông |

On the Ministry of Construction's Information Portal, reader D.D. T wondered about the time of handover of the project for use.

Readers reflect that on December 30, 2024, the Government issued Decree No. 175/2024/ND-CP replacing Decree No. 15/2021/ND-CP.

In Article 4 of Decree No. 175/2024/ND-CP on construction investment procedures, the handover of works for use is carried out in the final construction phase. Meanwhile, Article 4 of Decree No. 15/2021/ND-CP stipulates that the handover of works for use is carried out in the project implementation phase, before submitting for appraisal and settlement.

Currently, there are different understandings of the handover time for putting the project into use.

The first understanding is that the time of handover of the project for use according to Decree No. 175/2024/ND-CP is still carried out before submitting for verification and settlement similar to Decree No. 15/2021/ND-CP. At that time, the construction contractor transfers to the obligation to warranty the project. After having a decision approving the settlement, the asset value will continue to be handed over to the unit receiving the project.

The second understanding is that after finalizing the project, the project will be handed over for use and at the same time the assets will be handed over to the receiving unit, and the construction contractor will switch to the project warranty obligation.

Readers request functional agencies to answer which understanding is consistent with Article 4 of Decree No. 175/2024/ND-CP on construction investment procedures.

Answering this content, after research, the Economic - Construction Investment Management Department said that Clause 3, Article 50 of the 2014 Construction Law on construction investment procedures stipulates: "Based on the specific conditions of each project, the investor decides on the sequential or combination, interspersed implementation of works in the project implementation phase and the completion of construction to put the project into operation".

At the same time, point a, clause 1, Article 4 of Decree No. 175/2024/ND-CP dated December 30, 2024 of the Government stipulates: "The construction completion phase includes the following tasks: finalization of construction contracts, finalization of investment capital for completed projects, confirmation of completion of works; handover of works for use...".

In addition, Decree No. 15/2021/ND-CP dated March 3, 2021 has expired according to the provisions of point a, clause 2, Article 124 of Decree No. 175/2024/ND-CP dated December 30, 2024.

The Economic - Construction Investment Management Department requests citizens to study the above regulations to better understand the regulations on the time of handover of works for use.

Xuyên Đông
RELATED NEWS

Dismantling a series of constructions violating traffic corridors in Phu Tho

|

Phu Tho - A series of illegally erected structures, shacks, tarpaulins, and kiosks on the land of the traffic safety corridor in Cam Khe commune have been dismantled.

Risk of delay in progress at the Ke Go lake upgrade and repair project

|

Ha Tinh - Although it has focused on construction to compensate for volume, the project to upgrade and repair Ke Go Lake is still at risk of delaying progress.

8 PM News: Dak Lak recovers hundreds of hectares of land to implement key projects

|

8 PM News on May 30th: Dak Lak recovers hundreds of hectares of land to implement key projects; Using air conditioners incorrectly, many people have neck and shoulder pain in the middle of summer;...

Representative mark of the Trade Union organization

|

One of the biggest imprints of the Trade Union in the past term is the increasingly practical care and protection of the rights and interests of union members and workers.

Expecting strong innovation from the 14th Vietnam Trade Union Congress

|

Lao Dong Newspaper reporter had an interview with Mr. Bui Thanh Nhan - Member of the Presidium of the Vietnam General Confederation of Labor, Chairman of the Ho Chi Minh City Labor Federation - about the challenges for the workers' movement and trade union activities of Ho Chi Minh City and the expectations for the 14th Vietnam Trade Union Congress.

Lai Chau delegation looks forward to the 14th Vietnam Trade Union Congress

|

Lai Chau - Union members and workers are enthusiastically competing, entrusting their faith in the 14th Vietnam Trade Union Congress.

Trade unions participate in building new production forces, creating sustainable jobs for workers

|

This is the sharing of Mr. Tran Duc Thich - Chairman of the Trade Union of Vietnam Post Corporation before the 14th Congress of the Vietnam Trade Union.

The doctor who "defuse the fuse" of psychology, protects healthcare workers

|

An Giang - Studying and following Uncle Ho, BS.CKII Tran Van Loi has created many ways to both increase the efficiency of serving patients and protect healthcare workers.

Dismantling a series of constructions violating traffic corridors in Phu Tho

Tô Công |

Phu Tho - A series of illegally erected structures, shacks, tarpaulins, and kiosks on the land of the traffic safety corridor in Cam Khe commune have been dismantled.

Risk of delay in progress at the Ke Go lake upgrade and repair project

TRẦN TUẤN |

Ha Tinh - Although it has focused on construction to compensate for volume, the project to upgrade and repair Ke Go Lake is still at risk of delaying progress.

8 PM News: Dak Lak recovers hundreds of hectares of land to implement key projects

HUYỀN TRANG - ĐINH THIỆN |

8 PM News on May 30th: Dak Lak recovers hundreds of hectares of land to implement key projects; Using air conditioners incorrectly, many people have neck and shoulder pain in the middle of summer;...