Cao Bang - The Hoa An bypass project is being accelerated.

The Nuoc Hai town bypass project (Hoa An district, Cao Bang province) has a total investment of nearly 197 billion VND, started in March 2024, to date, contractors have completed more than 35% of the total volume.

The project is invested by the People's Committee of Hoa An district (now Hoa An commune), with a total length of 3.7km, designed according to the standards of a grade III mountainous area combined with a grade I urban area.

Khoang 1km da duoc giai da, mat duong co ban thanh hinh. Anh: Tan Van
About 1km has been paved with stone, the road surface is basically shaped. Photo: Tan Van

Of which, the 2.3km section has a 9m wide road surface; the remaining 1.5km section has a road surface and sidewalks up to 26m wide, in line with the orientation of urban traffic infrastructure development in the central area.

According to actual records on July 26, about 1km of the road surface has been paved with stone, and the roadbed has basically taken shape. Contractors are mobilizing maximum human resources and machinery to construct items such as filling the ground, rolling the road surface, leveling to create a flat surface, installing a drainage system and auxiliary items.

Cac vi tri dang duoc san gat, tao nen duong. Anh: Tan Van
The locations are being leveled and the roadbed is being created. Photo: Tan Van

The contractor's representative said that the construction process encountered some difficulties due to many sections of the route being blocked by high-voltage power lines, along with a shortage of filling materials - especially in areas with a depth of 3 - 4m, having to transport soil from another place.

In addition, the prolonged heavy rain in the past two months has also significantly affected the construction progress.

Ms. Nong Thi Ha, a resident of Hoa An commune, shared: "I hope the road will be completed soon to make it more convenient for people to travel. The current Ho Chi Minh route is often very crowded with vehicles, making it difficult to travel.

He thong thoat nuoc tren tuyen dang duoc dung. Anh: Tan Van
The drainage system on the route is under construction. Photo: Tan Van

The leader of the People's Committee of Hoa An commune said that the locality is carrying out procedures to hand over the project to the Cao Bang Provincial Traffic Construction Project Management Board for continued effective management and supervision.

According to the plan, the project will be completed in 2026. However, in July 2025, the contractor committed to basically completing the construction this year if the construction conditions were favorable.

When completed, the project will contribute to reducing traffic pressure through the center of Nuoc Hai town, ensuring safety for people and vehicles.

At the same time, the new route also creates conditions to expand urban space, promote local and neighboring socio-economic development.

Tân Văn
TIN LIÊN QUAN

Two hundred-billion-dong bypass routes must be completed in 2025

|

Cao Bang - According to the plan, the two bypass routes in Quang Uyen and Xuan Hoa town must be completed in 2025.

The 329 billion VND bypass in Tuyen Quang is about to reach the finish line

|

Tuyen Quang - The Son Duong town bypass road is 4km long, with a total investment of 329 billion VND, and has been basically completed.

On the hundred-billion-dong bypass road project in the border area

|

Cao Bang - The Quang Uyen town bypass road (Quang Hoa district) will have to be completed in 2025.

Ho Chi Minh City organizes the death anniversary of heroic martyrs and patriotic people in Con Dao

|

Ho Chi Minh City - The War Invalids and Martyrs Day on July 27 is also a national death anniversary for more than 20,000 heroic martyrs and patriots who sacrificed their lives in Con Dao.

Phuong My Chi shined with Son Tung's million-view hit in Sing! Asia?

|

Lac troi is a million-view song by Son Tung M-TP that Phuong My Chi chose to compete in the Sing! final! Asia.

Debate about famous beauty queens who do not have university degrees or coach students in beauty pageants

|

The organizing committee of Miss Student Vietnam 2025 invited famous beauty queens who did not have a university degree as coaches, causing some controversy.

Da Nang Department of Industry and Trade speaks out about the gas station suddenly refusing to accept a transfer

|

Da Nang - Many people are upset that PV Oil gas station (in Hoa Khanh ward) has not received a transfer for about a month now.

Thailand - Cambodia conflict enters 4th day

|

On July 27, the Thailand - Cambodia conflict entered the fourth consecutive day with guns and heavy fire at the border.

Two hundred-billion-dong bypass routes must be completed in 2025

Tân Văn |

Cao Bang - According to the plan, the two bypass routes in Quang Uyen and Xuan Hoa town must be completed in 2025.

The 329 billion VND bypass in Tuyen Quang is about to reach the finish line

Lam Thanh |

Tuyen Quang - The Son Duong town bypass road is 4km long, with a total investment of 329 billion VND, and has been basically completed.

On the hundred-billion-dong bypass road project in the border area

Tân Văn |

Cao Bang - The Quang Uyen town bypass road (Quang Hoa district) will have to be completed in 2025.