The People's Committee of Bac Ninh province has just issued a plan to implement the Investment Project to build a road connecting Gia Binh airport with the capital Hanoi (section through the province).
According to the People's Committee of Bac Ninh province, the investment project to build a road connecting Gia Binh airport with Hanoi capital (through the province) is a project on the list of important national projects and works, key to the Transport sector.
The project also has two meanings: improving transport capacity, promoting socio-economic development, ensuring national defense and security and creating a premise for other key infrastructure projects.
The development and promulgation of the Plan is extremely necessary to strictly implement the instructions of the Central Government and the Government and specify the Resolution of the Executive Committee of the Bac Ninh Provincial Party Committee. The plan will clearly define tasks, assign specific responsibilities and progress to each work item, ensuring timely, synchronous, public, transparent and effective project implementation.
Regarding the overall plan for implementing BT projects:
1. approve the project (since approve selected investors in special cases): Complete before September 24, 2025.
2. Compensation, site clearance, resettlement, and relocation of technical infrastructure:
- Clearance of agricultural land, handover to the Investor: Complete before December 21, 2025.
- Clearance of non-agricultural land (residential land, constructions on land, ...), handover to the Investor: Complete before February 21, 2026.
- Construction of resettlement areas for site clearance: Complete before July 21, 2026.
- Construction, renovation and expansion of cemetery areas served by transferring graves and mounds: Complete before January 2, 2026 (strive to complete before the winter solstice).
- Relocating and returning technical infrastructure works for site clearance: Complete before February 21, 2026
Construction implementation: Complete before December 31, 2026.
It is known that the investment project to build a road connecting Gia Binh airport to Hanoi capital (section passing through Bac Ninh province) has a total length of 27.7km passing through 8 communes and wards, including: Trung Kenh commune, Luong Tai commune, Gia Binh commune, Lam Thao commune, Tram Lo ward, Mao Dien ward, Thuan Thanh ward, Tri Qua ward (Bac Ninh province).
The route is invested according to the standards of a grade I plain road, with a design speed of 120km/h, and a parallel road with a speed of 60-80km/h. The construction scale according to the plan is 10 lanes and there are roads on both sides. The total investment is over VND 47,607 billion.
The starting point of the project is at km0 at the eastern intersection of the road connecting to Gia Binh airport, in Trung Kenh commune (Bac Ninh). The end point is about km27+700 at the beginning of the Duong River bridge, Tri Qua ward (Bac Ninh), bordering Phu Dong commune, Hanoi.
On the route, 6 cross-over bridges are arranged at locations intersecting with provincial roads, national highways or planned roads.