Ring Road 3 of Ho Chi Minh City through Dong Nai construction reaches over 63%

HÀ ANH CHIẾN |

Dong Nai - Ho Chi Minh City Ring Road 3 from Ben Luc - Long Thanh expressway to Nhon Trach bridge has a total investment of 2,584 billion VND, with construction reaching more than 63%.

On January 5, according to information from the Dong Nai Provincial Construction Investment Project Management Board, component project 3, Ho Chi Minh City Ring Road 3 project section passing through the province is implementing 3 main construction packages with output exceeding 63% of the contract value.

Component project 3 belongs to the Ho Chi Minh City Ring Road 3 project with a length of more than 11 km, with the starting point intersecting with the Ben Luc - Long Thanh expressway, the ending point intersecting with the B culvert belonging to Nhon Trach bridge, with a total investment of 2,584 billion VND.

In which, the project will invest in building 5 km of expressway connecting to component project 1A, Ho Chi Minh City Ring Road 3 Project at the intersection with provincial road 25B. Currently, the 5 km long main expressway section of the project has been technically opened to traffic.

In addition, the project will also invest in building the parallel road along both sides of the expressway, and has now completed 100% of the land filling of road K95, crushed stone grade...

HÀ ANH CHIẾN
RELATED NEWS

Deputy Prime Minister directs to remove 4 obstacles at the Ho Chi Minh City Ring Road 3 project

|

The Deputy Prime Minister requested the Ho Chi Minh City People's Committee and relevant localities to focus on removing difficulties and obstacles in the Ring Road 3 project.

Temporary exploitation of a section of Ho Chi Minh City Ring Road 3 connecting Dong Nai from August 19

|

Dong Nai - Component project 1A of Ho Chi Minh City Ring Road 3 is completing procedures for temporary exploitation.

Tay Ninh commits to completing Ho Chi Minh City Ring Road 3 through the province on schedule

|

Tay Ninh - Up to now, the site clearance work for the Ho Chi Minh City Ring Road 3 project has reached 100% of households, completed the resettlement area and arranged plots for people.

New proposal on the roadmap for implementing a 30% allowance for school staff

|

School staff such as libraries, clerical staff, accountants, and school health workers will enjoy a 30% allowance from January 1, 2023.

Many households do not comply with the direction on the Ring Road 2.5 project

|

Hanoi - Many households have not terminated or stopped leasing or lending houses and land within the Ring Road 2.5 project area as directed by Cau Giay ward.

Secrets to help Russia export gas amidst sanctions

|

Amidst the US sanctions, Russia still maintains LNG exports from the Arctic LNG 2 project thanks to a single icebreaker.

Van Dung shares her sadness when not having Tao Quan

|

Comedian Van Dung said that this year there will be no Tao Quan program broadcast on New Year's Eve like every year.

Deputy Prime Minister directs to remove 4 obstacles at the Ho Chi Minh City Ring Road 3 project

PHẠM ĐÔNG |

The Deputy Prime Minister requested the Ho Chi Minh City People's Committee and relevant localities to focus on removing difficulties and obstacles in the Ring Road 3 project.

Temporary exploitation of a section of Ho Chi Minh City Ring Road 3 connecting Dong Nai from August 19

HÀ ANH CHIẾN |

Dong Nai - Component project 1A of Ho Chi Minh City Ring Road 3 is completing procedures for temporary exploitation.

Tay Ninh commits to completing Ho Chi Minh City Ring Road 3 through the province on schedule

Duy Minh |

Tay Ninh - Up to now, the site clearance work for the Ho Chi Minh City Ring Road 3 project has reached 100% of households, completed the resettlement area and arranged plots for people.