Why does the 1,300 billion project in Dien Bien have to be extended for another year?

NHÓM PV |

The 1,300 billion VND transport project in Dien Bien will have to be extended by another year because it cannot be completed by the end of 2024 as planned.

Only reached over 60% of the volume

The traffic project connecting key economic areas in the dynamic economic zone along National Highway 279 and National Highway 12 in Dien Bien province (Dynamic Road Project) was approved by the People's Committee of Dien Bien province on May 31, 2021. The project has a total investment of VND 1,300 billion, invested by the Traffic Project Management Board.

The total length of the project route is 35.35 km. Of which, the route within Dien Bien Phu city is 5.78 km long, including 7 sections; the route outside the urban area is 29.57 km long, including 1 main route and 5 branch routes.

Cong nhan thi cong tren tuyen nhanh 3 tu xa Thanh Yen – Quoc lo 12 co chieu dai 2,66Km (tuyen duong ngoai pham vi do thi).
Workers are working on branch line 3 from Thanh Yen commune - National Highway 12, 2.66km long (outside urban area).

The project aims to complete the transport infrastructure, ensuring synchronous connection between the basin area of ​​Dien Bien district and Dien Bien Phu city. At the same time, create regional linkages to promote the exploitation of potential and advantages in developing agricultural and forestry production, trade services, and tourism. Implementation period is from 2021-2024.

However, recently, Mr. Le Thanh Do - Chairman of Dien Bien Provincial People's Committee had to sign a decision to adjust the project implementation time to the end of 2025 because up to now - less than 1 month left until the end of the implementation time but the total volume of construction packages implemented has only reached 62.4%.

Thi cong cau tai tuyen nhanh 2 - tuyen duong ngoai pham vi do thi (thuoc xa Thanh Chan, huyen Dien Bien).
Bridge construction at branch line 2 - road outside urban area (in Thanh Chan commune, Dien Bien district).

On December 6, according to the reporter of Lao Dong Newspaper, at the construction sites of packages 04, 05, 06 located in the Provincial Administrative - Political Center and packages 01, 02, 03, 07, 08, 09, 10, 12 within the scope of Dien Bien Phu City and Dien Bien District, contractors are still actively working.

For package 11 (Lighting, water supply), the contractor has received the NT1 section site and part of the NT2 section site to start construction.

Cac nha thau huy dong may moc, nhan luc de thi cong nen duong.
Contractors mobilized machinery and manpower to construct the roadbed.

The investor must pay in advance to have the premises.

Speaking to Lao Dong Newspaper, Mr. Nguyen Minh Tuan - Acting Director of the Traffic Project Management Board of Dien Bien Province said that the project is still facing many difficulties due to problems with site clearance. In particular, in Dien Bien Phu City, the progress of preparing and approving compensation and support plans for site clearance is still very slow.

“After having the site, the issue of progress is the number one priority. In case any contractor fails to meet the progress, we will base on the contract terms and legal regulations to consider adding subcontractors or transferring the volume,..." - Mr. Tuan emphasized.

Chu dau tu phai vay tien, tam ung cho dan de lay mat bang thuc hien du an.
Investors must borrow money and advance money to people to get land to carry out the project.

According to Mr. Nguyen Minh Tuan, due to difficulties in preparing and approving site clearance plans, investors must mobilize and persuade households to agree to advance money according to the public plan estimate to have a site for project construction.

“Faced with such reality, we have also requested the People's Committee of Dien Bien Phu City to continue to pay more attention to speeding up the site clearance progress, ensuring that by December 15, 2024 at the latest (the time has been postponed by 60 days according to Dien Bien Phu City's commitment), the entire site will be cleared for the project,” Mr. Tuan added.

NHÓM PV
TIN LIÊN QUAN

Traffic project stuck because natural forest has not been cleared

|

Quang Tri - The natural forest area that the road passes through has not been cleared, causing the road project to be stuck and behind schedule.

Ho Chi Minh City departments and branches work together to remove difficulties so that the Zoo can operate well

|

HCMC - Regarding the story of land tax debt, the Director of the Zoo felt warm when receiving attention from leaders, departments and people of HCMC.

Current state of My Dinh Stadium after the concert "Anh trai say hi"

|

My Dinh Stadium is being urgently cleaned up and scaffolding dismantled to prepare for upcoming events, including the 2024 ASEAN Cup.

Why ChatGPT is Having Global Issues

|

ChatGPT has experienced a global outage that has left users unable to access and use it.

There are still shortcomings in issuing retail invoices for gasoline and oil

|

The issuance of electronic invoices for each sale at gas stations has been actively implemented by many businesses, but there are still shortcomings.

Audience spent tens of millions of dong to watch Anh Trai's concert in Hung Yen

|

As December 14 approaches, the audience is ready to burn out at the Call Me by Fire concert held in Hung Yen.

Maintain the "green, clean, beautiful" movement at the workplace for employees

|

Over the years, union members of the Hanoi Construction Trade Union have always been active in environmental protection work, maintaining a "green, clean, and beautiful" workplace.

7,000 billion VND airport bypass in Lao Cai eroded after storm and flood

|

Lao Cai - Many landslides and subsidence points on the Sa Pa Airport bypass road make it difficult for people to travel.

Traffic project stuck because natural forest has not been cleared

HƯNG THƠ |

Quang Tri - The natural forest area that the road passes through has not been cleared, causing the road project to be stuck and behind schedule.

Tái khởi động dự án 1.300 tỉ đồng sau phản ánh của Lao Động

NHÓM PV |

Điện Biên - Sau khi Báo Lao Động có bài phản ánh "Khổ vì dự án giao thông 1.300 tỉ chậm tiến độ", các nhà thầu đã huy động tối đa máy móc, nhân lực để thi công.

Khổ vì dự án giao thông 1.300 tỉ chậm tiến độ

NHÓM PV |

Dự án giao thông 1.300 tỉ tại Điện Biên được kỳ vọng sẽ là “cú hích” để phát triển. Tuy nhiên, do dự án chậm tiến độ đã ảnh hưởng tới cuộc sống nhiều người.