Entangled in technical infrastructure, key projects in Nghe An face difficulties

QUANG ĐẠI |

The project to renovate and expand National Highway 46 Vinh - Nam Dan section is facing many problems with site clearance and technical infrastructure, causing construction progress to be slower than required. Leaders of Nghe An province requested units to focus on definitively handling the site before April 15, 2026.

As a key transport project of Nghe An province, the project has a total investment of about 500 billion VND from the central budget fund invested by Project Management Board 85. The project is expected to be completed in 2025 but the progress is delayed due to site clearance problems.

According to Project Management Board 85, to date, about 1.21km of the project is entangled with power lines, water lines, houses and works of 63 households; the remaining 5.4km cannot be constructed due to technical infrastructure works such as medium and low voltage power lines, domestic water pipelines of Nghe An Water Supply Joint Stock Company, civil power lines, telecommunications cables of VNPT... Localities have organized the handover of land to construction contractors, but there are still household works that have been approved but have not received compensation.

Nghe An Water Supply Joint Stock Company has deployed welding and installing pipelines for nearly 7,000m, but the progress is slower than committed. During the construction of excavation, many more pipe sections are located within the roadbed area that need to be further relocated, affecting the project progress.

Inspecting the project, Vice Chairman of Nghe An Provincial People's Committee Hoang Phu Hien emphasized that the current construction progress has not met the requirements. The main reasons are obstacles in compensation payment capital and delays and lack of decisiveness in relocating technical infrastructure works.

To ensure progress, the Vice Chairman of the Provincial People's Committee requested relevant units to focus on definitively resolving land issues, from adjusting compensation capital sources to relocating technical infrastructure of electricity, water supply and telecommunications units, to be completed before April 15, 2026.

The investor is assigned to preside over and coordinate comprehensively to handle site problems; urgently complete procedures to adjust the total investment and allocate sufficient remaining funds to pay people as soon as capital returns to the treasury.

For the People's Committees of Kim Lien, Dai Hue, Van An communes, the Vice Chairman of the Provincial People's Committee requested to be more drastic in directing the relocation of medium and low voltage power lines; urgently mobilize households to hand over land as soon as they receive money. For households that have received money but obstruct construction or have not dismantled architectural structures, request inspection, verification and thorough handling.

The Vice Chairman of the Provincial People's Committee requested Nghe An Water Supply Joint Stock Company to proactively increase construction teams, accelerate the speed to complete before April 15, 2026, without waiting for the contractor to finish excavating the foundation before relocating. Telecommunications units urgently coordinate to relocate the cable system on the entire route, not to delay the overall progress.

In Nghe An, many important transport infrastructure projects have been delayed due to site clearance, this is the biggest bottleneck but there is no fundamental solution.

QUANG ĐẠI
RELATED NEWS

Cam Khe commune will enforce land recovery from 10 households in key projects

|

Phu Tho - On the morning of March 30, Cam Khe Commune People's Committee held a press conference to inform about the coercive land acquisition to implement the Urban Housing Area and cultural and sports complex project.

Lack of embankment land, tens of trillions VND resettlement project serving expressway delayed

|

Lang Son - Pac Luong resettlement area is currently behind schedule due to lack of embankment land.

Auditing BOT projects before contract termination

|

The State Audit Office of Vietnam conducts audits of BOT projects before payment and contract termination, not allowing loss of assets and state budget.

Early recognition of stroke during prime time, proper treatment increases chances of survival

|

Vinh Long - The health sector warns of stroke requiring emergency care during prime time, each minute of delay loses 2 million brain cells, reducing recovery opportunities.

Hot direction for the pork case at a kindergarten showing signs of abnormality

|

Thai Nguyen - Many parents with children studying at Hoa Binh Kindergarten are worried when they discover that pork shows abnormal signs, suspected of being infected with the epidemic.

Vietnam General Confederation of Labor listens to a report on trade union activities in Ho Chi Minh City

|

Ho Chi Minh City - The working delegation of the Vietnam General Confederation of Labor led by Chairman Nguyen Anh Tuan worked with the City Labor Federation on the morning of April 2.

Parents are confused by the news of diseased pork, schools in Ninh Binh speak out

|

Ninh Binh - Information about diseased pork makes many parents worried about semi-boarding meals. Schools speak out, affirming safe food sources.

Cam Khe commune will enforce land recovery from 10 households in key projects

Tô Công |

Phu Tho - On the morning of March 30, Cam Khe Commune People's Committee held a press conference to inform about the coercive land acquisition to implement the Urban Housing Area and cultural and sports complex project.

Lack of embankment land, tens of trillions VND resettlement project serving expressway delayed

Khánh Linh |

Lang Son - Pac Luong resettlement area is currently behind schedule due to lack of embankment land.

Auditing BOT projects before contract termination

PHẠM ĐÔNG |

The State Audit Office of Vietnam conducts audits of BOT projects before payment and contract termination, not allowing loss of assets and state budget.