Overcoming storms, the 500kV Lao Cai - Vinh Yen project is in the final stage

Nhóm PV |

Despite facing storms and harsh terrain, the 500kV Lao Cai - Vinh Yen transmission line project continues to ensure progress thanks to the efforts of the government, people and construction workers. The goal of completing the power outage before August 19 is being focused on.

In recent days, the family of Mr. Nguyen Quang Ngoi - Lam Thuong commune, Lao Cai province - has become a shelter for officers and workers working on the Lao Cai - Vinh Yen 500kV transmission line project every time a storm comes.

Mr. Ngoi gave the entire lower room to the staff and workers for eating, sleeping, and living. Because he simply thought that helping the power line project to quickly speed up, reach the finish line, and energize before August 19 as requested by the Prime Minister is also the wish of the people here.

Pointing to the top of the hill where the VT140 pole is under construction, Mr. Le Van Du - the project's executive engineer - said: "This is one of the most difficult locations in the project. The nearly 2km road from the foot of the hill to the top seems not far, but after heavy rain, it is muddy and slippery. Many times the truck cannot get on, so the brothers walk, carrying every meter of cable and iron bar. The storm is so hard but no one allows me to give up when the whole project is waiting.

Mr. Van Minh Tam (construction unit) also shared: The work here is extremely difficult because of the complex terrain, dense hills, and large slopes. Opening the road to the construction site also takes a lot of time and effort. Long, heavy steel pipes cannot be transported in whole, forcing them to be divided into many sections for easy transportation.

Speaking to Lao Dong Newspaper, Mr. Do Quang Khai - Deputy Director of Power Project Management Board 1, Director of the Project Management Board - said: Due to the urgent construction, Power Project Management Board 1 has directed the contractor to make the most of the time before the storm to transport materials and start construction. At some locations affected by storms, the board has directed contractors to move all construction equipment and materials to safe shelters.

Currently, 100% of officers and employees of the Project Management Board have been mobilized and on duty at the construction site according to the "4 on-site" motto. Natural disaster prevention and control plans have been activated and deployed simultaneously at locations on the construction site" - the Director of the Project Management Board expressed.

Nhóm PV
TIN LIÊN QUAN

Ensuring safety at the Lao Cai - Vinh Yen 500kV transmission line construction site during the rainy and stormy season

|

The 500kV Lao Cai - Vinh Yen transmission line project is facing many difficulties due to the harsh terrain and the Northwest beginning of the rainy and stormy season.

Overcoming the difficult terrain of the Lao Cai - Vinh Yen 500kV transmission line project

|

100 officers and soldiers of Military Region 2 were present at the project's difficult locations to work with construction units to speed up the progress.

Racing against storms to laid foundations for the 500kV Lao Cai - Vinh Yen power line

|

Despite the sunny weather, unusual rain, landslides and flash floods in Lao Cai and Yen Bai provinces, thousands of workers are still day and night, working hard at the Lao Cai - Vinh Yen 500kV transmission line project site.

Arsenal has prepared well to introduce Viktor Gyokeres

|

After reaching a personal agreement with Viktor Gyokeres, Arsenal are preparing to announce their most anticipated contract in many years.

Countrymen apply AI, village chiefs broadcast livestreams to promote traditional products

|

Thanks to the application of technology and sales on digital platforms, the revenue of traditional product manufacturing households in Phuong Duc commune, Hanoi has increased significantly.

Indonesia U23 coach will not attend a press conference after his team entered the Southeast Asian U23 final

|

The head coach of the U23 Indonesia team was unexpectedly absent from the press conference after winning a ticket to the final of the U23 Southeast Asian tournament.

Ninh Binh proposes to location Ninh Binh International Airport in Liem Tuyen ward

|

Ninh Binh - In the proposal and recommendation report to the Ministry of Construction, the Provincial People's Committee plans to locate Ninh Binh International Airport in Liem Tuyen ward.

Ensuring safety at the Lao Cai - Vinh Yen 500kV transmission line construction site during the rainy and stormy season

Nhóm PV |

The 500kV Lao Cai - Vinh Yen transmission line project is facing many difficulties due to the harsh terrain and the Northwest beginning of the rainy and stormy season.

Overcoming the difficult terrain of the Lao Cai - Vinh Yen 500kV transmission line project

Nhóm PV |

100 officers and soldiers of Military Region 2 were present at the project's difficult locations to work with construction units to speed up the progress.

Racing against storms to laid foundations for the 500kV Lao Cai - Vinh Yen power line

Nhóm PV |

Despite the sunny weather, unusual rain, landslides and flash floods in Lao Cai and Yen Bai provinces, thousands of workers are still day and night, working hard at the Lao Cai - Vinh Yen 500kV transmission line project site.