Railway overpass project in Dong Hoi stagnates

CÔNG SÁNG |

Quang Binh - The road and overpass project of the central railway of Dong Hoi City is in a state of stagnation due to problems in site clearance.

Land clearance problems

The Dong Hoi City Central Railway Overpass and Road Project (Quang Binh Province) is invested by the Department of Transport (GTVT) of Quang Binh Province, the Provincial Traffic Construction Investment Project Management Board is the investor's representative.

The project consists of two packages: the bridge section has a contract value of more than 85 billion VND and the road section is more than 13.4 billion VND. The total length of the entire route and bridge is 1.15 km, connecting the Ha Van Quan - Ton That Tung road axis with the Nguyen Cong Hoan - Phan Dinh Phung route.

This project is of great significance in regulating inner-city traffic, reducing congestion, especially at intersections between roads and railways, creating favorable conditions for people and contributing to promoting the socio-economic development of the area. However, although construction started in October 2022 with an expected completion time of 36 months, the project has so far only built pillars.

Nhieu vi tri sat, thep bi gi ret. Anh: Cong Sang
Many iron bars were rusted. Photo: Cong Sang

According to Lao Dong Newspaper's reporter on February 18, the project has no construction workers, and many grass and trees grow outside. The pillars have been built. Many long iron bars placed in the project show signs of rust.

According to the Project Management Board, the construction site is almost stalled due to not yet completed site clearance.

The Department of Natural Resources and Environment of Dong Hoi City said that within the scope of site clearance for the project, there are 96 affected cases in Nam Ly and Bac Ly wards. Many households have not been able to clear the land because the land acquisition scope of the project coincides with another project.

Resettlement work also faces difficulties due to differences in people's needs and lack of consensus among relevant parties.

In the bridge construction package, although more than half of the construction time has passed, only a few piers have been built.

Efforts to resolve but there are still no changes

To remove obstacles for the project, the People's Committee of Dong Hoi City recently held a meeting with the participation of the Department of Transport and related units to find solutions to speed up the site clearance progress. However, up to now, the construction site is still lacking workers, with no signs of construction returning.

Co cay moc um tum. Anh: Cong Sang
Grass and trees grow wildly. Photo: Cong Sang

In the face of the above situation, removing obstacles in site clearance is a prerequisite for the project to continue to be implemented on schedule, helping to reduce traffic pressure for Dong Hoi City.

Recently, the People's Committee of Quang Binh province has issued a document directing departments, branches, sectors, localities, and investors of projects to report and review projects, works, and works that are behind schedule, have long-term backlogs, and are ineffective, causing great loss and waste.

Khong co hoat dong thi cong duoc dien ra. Anh: Cong Sang
There are no construction activities inside the project. Photo: Cong Sang

In 2024, at the request of the Department of Planning and Investment, the People's Committee of Quang Binh province agreed to withdraw 13 projects, which are investment projects that have not leased land, have not deposited funds, and are behind schedule. All 13 projects above have a total land use area of more than 39 hectares, a total investment of more than 261 billion VND, all of which are beyond the completion deadline and have not been implemented, leading to revocation.

CÔNG SÁNG
TIN LIÊN QUAN

Detailed information about the Ha Dinh social housing project

|

Hanoi - Ha Dinh social housing project is expected to receive documents in the fourth quarter of 2025.

The VND2,160 billion project in Pleiku is behind schedule due to land clearance problems

|

Currently, there are 327 households with land and assets in the planning and clearance area that have not agreed to relocate because they think the compensation price is still low.

Progress of a series of hundred-billion-dong projects in Ha Giang

|

A series of key projects and works with a total investment of hundreds of billions of VND in Ha Giang province are being accelerated, expected to be completed in 2025.

Intersection in Hanoi before proposal to build underpass worth over VND1,400 billion

|

Hanoi - The Hoang Quoc Viet extended underpass - Ring Road 3 is proposed to be built 600m long, with an investment capital of more than VND1,400 billion to help reduce congestion and increase connectivity.

Mr. Trump denies going to Russia to attend the Victory Day celebration

|

US President Donald Trump denied the information that he will travel to Russia on the occasion of the Victory Day celebration on May 9.

Consecutive earthquakes shake mountainous areas of Quang Nam

|

Quang Nam experienced 3 consecutive earthquakes in just a few days, causing mountainous areas to shake.

Expected to open more than 10,000 apartments for sale in Ho Chi Minh City

|

HCMC - By 2025, more than 10,000 apartments are expected to be opened for sale, of which class B accounts for 54% of the total number of apartments.

The peaceful beauty of the 5 sacred ancient pagodas in Ha Nam

|

Ha Nam is a province famous for its sacred ancient pagodas and peaceful beauty that attract many pilgrims.

Detailed information about the Ha Dinh social housing project

Như Hạ |

Hanoi - Ha Dinh social housing project is expected to receive documents in the fourth quarter of 2025.

The VND2,160 billion project in Pleiku is behind schedule due to land clearance problems

Phan Tuấn |

Currently, there are 327 households with land and assets in the planning and clearance area that have not agreed to relocate because they think the compensation price is still low.

Progress of a series of hundred-billion-dong projects in Ha Giang

Việt Bắc |

A series of key projects and works with a total investment of hundreds of billions of VND in Ha Giang province are being accelerated, expected to be completed in 2025.