How is the project to renovate the busiest road in Dien Bien now

QUANG ĐẠT |

After more than a year of being suspended to wait for adjustment procedures, the busiest street in Dien Bien Phu City, Dien Bien Province is gradually revealing a new look.

More than a year ago, the project to renovate and upgrade Nguyen Chi Thanh Street (15m wide) in Dien Bien Phu City had to be temporarily suspended due to problems arising during the construction process. Now, the city's busiest and most bustling street is showing a new face.

On January 4, according to the reporter of Lao Dong Newspaper, of the total length of the road of more than 1,400m, nearly 700m has been completed, the remaining part has also completed most of the items.

Sau hon mot nam, duong Nguyen Chi Thanh (duong 15m) tai TP Dien Bien Phu bi dao xoi tan hoang... roi de day khien cuoc song nguoi dan bi dao lon gio day con pho dong duc va sam uat nhat TP Dien Bien Phu da co nhieu thay doi.
A section of Nguyen Chi Thanh Street has been completed. Photo: Quang Dat
Tuyen pho sam uat nhat Dien Bien gio day dang khoac len minh mot dien mao moi.
The busiest street in Dien Bien is now wearing a new look.

Ms. Va Thi Hoa - owner of a business on Nguyen Chi Thanh Street said that the initial construction process caused a lot of dust and inconvenience to residents. However, when returning to the implementation, the items were completed quickly after only about 2 weeks. Currently, it no longer affects the business of the restaurant.

"For over a year, people have suffered a lot because they have to live on an unfinished street, especially businesses. However, now that the road is completed, the street has become spacious and modern, I believe that business will be more favorable" - Ms. Hoa said.

Toan bo via he va long duong duoc dau tu dong bo.
All sidewalks and roads are invested synchronously.

Truc duong Nguyen Chi Thanh, TP Dien Bien Phu (Anh: Google Maps).

Nguyen Chi Thanh Street, Dien Bien Phu City. Photo: Google Maps

On the afternoon of January 4, speaking with Lao Dong Newspaper reporters, Mr. Tran Duc Lam - Deputy Director of Dien Bien Phu City Project Management Board (representing the investor) said that the project has completed all procedures after adjustment. "We have requested contractors to complete all items before January 15," said Mr. Lam.

Theo ghi nhan cua PV, hien nay van con khoang hon 700m dang duoc nha thau tiep tuc thi cong, hoan thien cac hang muc nhu mat duong, mot so doan via he, he thong cong thoat nuoc.
Many machines are gathered to prepare to complete the final items on the remaining roads.

Previously in October 2023, Lao Dong Newspaper published an article reflecting "Enterprises dig up roads and leave them there, people's lives are turned upside down".

Accordingly, from around mid-September 2023, the company came to dig sidewalks, drainage systems, cut trees and gather materials along Nguyen Chi Thanh Street. After that, both workers and machines moved away, causing great impact on people's travel and business.

Truoc do vao thang 10.2023, Bao Lao Dong da co bai phan anh “Doanh nghiep dao duong roi de day, cuoc song nguoi dan bi dao lon”. Theo do, tu nhieu ngay qua, cuoc song nguoi dan song doc 2 ben duong Nguyen Chi bi dao lon khi doanh nghiep dao xoi tan hoang... roi de day.

Nguyen Chi Thanh Street when the project was first implemented. (Photo taken in October 2023).

The contractor representative said that the reason for not being able to continue implementation was due to problems arising during the construction process. Accordingly, the entire old drainage system had seriously degraded but was not included in the project list.

Immediately after that, Chairman of Dien Bien Provincial People's Committee - Mr. Le Thanh Do directly led the working group to inspect, evaluate and approve the project adjustment. However, due to the urgent preparation for the activities to celebrate the 70th anniversary of Dien Bien Phu Victory, the project had to be temporarily suspended.

Dai dien nha thau cho biet - nguyen nhan do phat sinh trong qua trinh thi cong. Toan bo he thong thoat nuoc cu da xuong cap nghiem trong nhung lai khong nam trong danh muc cua cong trinh. De dieu chinh du an phai cho xin y kien UBND tinh Dien Bien.
The mangrove drainage system has been newly invested after project adjustment.

After that, the investor and contractor will have to wait for the project adjustment procedures to be completed. Therefore, the project will not be implemented until the end of 2024.

Speaking to Lao Dong Newspaper reporter, Mr. Le Hong Quang - Director of Vinh Phuc Investment and Construction Company Limited - one of the contractors of this project - said: "Immediately after completing the project adjustment documents, we mobilized maximum human resources and means to complete the project as soon as possible".

Sau do, chu dau tu va nha thau lai tiep tuc phai cho hoan thien cac thu tuc dieu chinh du an nen den nhung ngay cuoi nam 2024 du an moi tiep tuc duoc trien khai. Du kien cac toan bo cac hang muc se co ban hoan thanh truoc Tet Nguyen dan.
Sidewalk paving and tree planting projects have been basically completed.

According to the investigation of Lao Dong Newspaper reporters, the project to upgrade and repair drainage ditches and sidewalks to complete the technical infrastructure on Nguyen Chi Thanh Street has a total length of more than 1,400m with a total investment of nearly 15 billion VND.

After adjustment, the project has a total cost of 35 billion VND, including all drainage ditches (renewed) and the entire road surface. This project is invested by Dien Bien Phu City People's Committee, the construction unit is a joint venture of Vinh Phuc Company - Thuat Tuong Nguyen.

QUANG ĐẠT
TIN LIÊN QUAN

Cement shortage, trucks lined up in Dien Bien

|

There is less than a month left until Lunar New Year, but for many days now, dozens of trucks at Dien Bien Cement Factory have been lining up to wait for their turn to load goods.

Dien Bien provides professional training for more than 100 union officials

|

More than 100 grassroots trade union officials in Tua Chua district, Dien Bien province have just participated in a professional training course with many important skills.

New Year's Day at the construction site of the 1,300 billion VND project in Dien Bien

|

From New Year's Eve to New Year's Day 2025, the construction site of the 1,300 billion VND project in Dien Bien is always bustling with urgent work atmosphere.

Forest fire in Bai Chay ward, Ha Long city

|

Quang Ninh - The forest in Bai Chay ward, Ha Long city is still burning due to strong winds and dry weather.

Deputy Prime Minister inspects progress of Long Thanh airport project

|

Dong Nai - On the afternoon of January 9, Deputy Prime Minister Tran Hong Ha and a delegation of the Government and ministries worked and inspected the progress of the Long Thanh airport project.

Approving the election results of the Chairman of the People's Committee of Nghe An and Bac Giang provinces

|

On January 9, 2025, Prime Minister Pham Minh Chinh signed and issued Decisions approving the election results for the positions of Chairman of the People's Committee of Nghe An province and Chairman of the People's Committee of Bac Giang province.

Cruise missile strikes, vehicles burn in Ukraine

|

Ukraine accused Russia of using cruise missiles to attack on January 8, killing many people and setting many vehicles on fire.

It took 3 years to build more than 700m of road in Da Lat

|

Lam Dong - After many years of construction, the contractor has only built about 700m of the road to Xuan Huong Lake in Da Lat city.

Cement shortage, trucks lined up in Dien Bien

VĂN THÀNH CHƯƠNG |

There is less than a month left until Lunar New Year, but for many days now, dozens of trucks at Dien Bien Cement Factory have been lining up to wait for their turn to load goods.

Dien Bien provides professional training for more than 100 union officials

MINH THUẬN |

More than 100 grassroots trade union officials in Tua Chua district, Dien Bien province have just participated in a professional training course with many important skills.

New Year's Day at the construction site of the 1,300 billion VND project in Dien Bien

NHÓM PV |

From New Year's Eve to New Year's Day 2025, the construction site of the 1,300 billion VND project in Dien Bien is always bustling with urgent work atmosphere.

Doanh nghiệp đào đường rồi để đấy, cuộc sống người dân bị đảo lộn

VĂN THÀNH CHƯƠNG |

Điện Biên - Từ nhiều ngày qua, cuộc sống người dân bị đảo lộn khi trục đường Nguyễn Chí Thanh tại TP Điện Biên Phủ bị đào xới tan hoang... rồi để đấy.