Roads in Hanoi have been under construction for 16 years, with 7 extensions, but no deadline yet

HỮU CHÁNH |

Hanoi - After 16 years of construction and 7 contract extensions, the Southern trunk road project still has no date for the entire route to open to traffic.

The Southern axis road project of Ha Tay province (old) is 41.5km long, starting at the intersection of Phuc La - Van Phu road (Kien Hung, Ha Dong), ending at the intersection of National Highway 1A - the section below Gie bridge (Chau Can, Phu Xuyen).

The route is designed to be 40m wide with 6 lanes, running through Ha Dong, Thanh Oai, Ung Hoa and Phu Xuyen districts.

The project is divided into two phases with a total investment of more than 6,000 billion VND. The investment capital is matched by land use fees of 3 projects: Thanh Ha A Urban Area (195.5ha), Thanh Ha B Urban Area (193.22ha), My Hung Urban Area (182ha).

Traffic Construction Corporation 5 is the investor, Cienco 5 Real Estate Development Joint Stock Company is the project enterprise.

a
Phase 1 of the Southern Axis Road project has been completed. Photo: Huu Chanh

In 2008, the project was implemented and was scheduled to be completed in 2014. However, the completion date of the route was not as originally planned.

In fact, the 19.9km phase 1 of the project will not be open to traffic until the end of 2018. The 21.6km phase 2 is currently undergoing site clearance.

According to the Hanoi Department of Transport, the southern axis road project of Ha Tay province (old) under the BT contract form was signed in 2008.

After more than 16 years with many adjustments, the project is still not completed.

a
Southern axis road project through Hong Minh commune (Phu Xuyen, Hanoi). Photo: Huu Chanh

According to contract appendix No. 07 dated June 6, 2024, the Investment Project contract expired on June 30.

Therefore, the Department of Transport proposed that the Hanoi People's Committee assign the Department of Transport to continue signing the contract appendix to extend the project implementation period while the adjusted Feasibility Study Report has not been approved.

This is to ensure the legal continuity of the contract as well as to carry out site clearance and subsequent work items, ensuring regulations on construction investment management.

This agency also requested the Hanoi People's Committee to direct the People's Committees of Phu Xuyen and Ung Hoa districts to focus on resolving site clearance problems and handing over the site to investors and project enterprises in the third quarter of 2024.

Mot so doan tuyen du an dang duoc trien khai thi cong. Anh: Huu Chanh
Some sections of the project are under construction. Photo: Huu Chanh

According to the Hanoi Department of Transport, the project has so far extended the contract implementation period 7 times. However, this is only temporary and cannot resolve all the existing issues and problems.

This agency believes that it is necessary to urgently complete the approval of the adjustment of the Investment Project to ensure full legality as well as to resolve all remaining issues with the Investment Project.

At the same time, it is necessary to continue to temporarily extend the project implementation period and contract implementation period. The extension should only last until the end of June 2025 and the official implementation period will be updated when the Investment Project adjustment is approved.

HỮU CHÁNH
TIN LIÊN QUAN

Hai dự án giao thông được mong chờ ở Hà Nội sắp về đích

HỮU CHÁNH |

Hà Nội - Hai dự án giao thông quan trọng ở Long Biên và Nam Từ Liêm đang tiến gần vạch đích, dự kiến khánh thành dịp 70 năm Giải phóng Thủ đô (10.10).

Đường 1.300 tỉ ở Hà Nội đạt 95% khối lượng rồi "đắp chiếu"

HỮU CHÁNH |

Hà Nội - Đạt 95% khối lượng và nhận đủ mặt bằng thi công song đoạn vành đai 2,1km, vốn 1.300 tỉ đồng vẫn chưa hẹn ngày về đích.

Đường 1.200 tỉ nổi tiếng làm lâu ở Long Biên sắp hoàn thành

HỮU CHÁNH |

Hà Nội - Dự án đường nối Nguyễn Văn Cừ - Ngọc Thụy đang gấp rút hoàn thiện các hạng mục cuối, dự kiến khánh thành dịp 70 năm Giải phóng Thủ đô (10.10).

Xe tải bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết

Duy Tuấn |

Bình Thuận - Xe tải đang lưu thông thì bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết.

Tin 20h: Yên Bái kiểm tra nhà hàng "chặt chém" đoàn từ thiện

Nhóm PV |

Tin 20h ngày 19.9: Bà Nguyễn Phương Hằng được ra tù vào hôm nay; Yên Bái kiểm tra nhà hàng bị tố chặt chém đoàn từ thiện...

Phía Miss Universe nói về thông tin Kỳ Duyên chưa tốt nghiệp

Huyền Chi |

Thông tin Hoa hậu Kỳ Duyên chưa tốt nghiệp Trường Đại học Ngoại Thương gây xôn xao mạng xã hội.

Thể Công Tân Cảng bảo vệ thành công chức vô địch giải bóng chuyền U23 Quốc gia 2024

Nhóm PV |

U23 Thể Công Tân Cảng thắng U23 Ninh Bình 3-1 tại chung kết giải bóng chuyền U23 quốc gia vào tối 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

Two highly anticipated transport projects in Hanoi are nearing completion

HỮU CHÁNH |

Hanoi - Two important traffic projects in Long Bien and Nam Tu Liem are approaching the finish line, expected to be inaugurated on the occasion of the 70th anniversary of the Liberation of the Capital (October 10).

1,300 billion VND road in Hanoi reaches 95% of volume and then "shelved"

HỮU CHÁNH |

Hanoi - 95% of the work has been completed and the construction site has been received, but the 2.1km beltway section, with a capital of 1,300 billion VND, still has no completion date.

The famous 1,200 billion VND road in Long Bien is about to be completed

HỮU CHÁNH |

Hanoi - The Nguyen Van Cu - Ngoc Thuy connecting road project is urgently completing the final items, expected to be inaugurated on the occasion of the 70th anniversary of the Liberation of the Capital (October 10).