Hai Phong strives to complete Hoa River bridge before Tet

Hoàng Khôi |

Hai Phong - Hai Phong City directs to speed up progress, striving to complete the Hoa River bridge before Lunar New Year 2025.

More than 760 billion VND to connect traffic between 2 localities

The investment project to build a bridge over the Hoa River and the section through Hai Phong of the road from Thai Binh City to Nghin Bridge (Hoa River bridge project) was approved by the Hai Phong City People's Council at the 2nd session of the 16th term (August 2021).

Project to build a bridge over Hoa River with a length of 411.2 m, retaining wall length of 140 m; bridge width of 22.5 m; navigation clearance BxH=30mx6m. At the same time, build a connecting road according to the scale of a level II plain road, cross-section width of 22.5 m with a length of 1,882 m and other works on the route according to current standards.

Den thang 9.2024, huyen Vinh Bao hoan thanh giai phong mat bang du an cau vuot song Hoa. Anh: Kien Nguyen
By September 2024, Vinh Bao district will complete site clearance for the Hoa River overpass project. Photo: Kien Nguyen

The project is being implemented in Vinh Bao district, Hai Phong and Quynh Phu district, Thai Binh province with a total land area of ​​nearly 12 hectares. The total investment of the project is more than 760 billion VND from the budget of Hai Phong city and Thai Binh province. In particular, Thai Binh province's budget will pay for the site clearance of the bridge and the approach road of the Hoa River overpass in the province.

The project is expected to shorten travel time between Thai Binh and Nam Dinh provinces with Hai Phong City and Quang Ninh Province, reducing the load on National Highway 10. The project also contributes to enhancing traffic safety, reducing traffic accidents in the area; creating favorable conditions to attract investment, contributing to promoting socio-economic development between Thai Binh Province and Hai Phong City.

Preparing to close the overpass project before Tet

According to the report of the Hai Phong City Traffic Construction Investment Management Board, by September 2024, localities will complete site clearance of more than 9 hectares of land and hand it over to the construction unit.

The contractors started construction in April 2024 and are currently constructing the pedestal, body, and cap beams of the piers, the bridge deck; box retaining walls; cement-reinforced soil piles for the roadbed; roadbed aggregate layers; and Super T beams. Currently, the contractors have completed 109/109 bored piles, 62/100 Super T beams, 7/11 piers and abutments, with the completed volume by November 25, 2024 reaching about 58% of the contract value.

Pho Chu tich UBND TP Hai Phong Nguyen Duc Tho kiem tra tien do du an. Anh: Tram Bau
Vice Chairman of Hai Phong City People's Committee Nguyen Duc Tho inspects the project's progress. Photo: Tram Bau

In a recent inspection of the Hoa River overpass construction project, the Vice Chairman of Hai Phong City People's Committee requested contractors to speed up the construction progress of the items, striving to close the Hoa River overpass on the 23rd of December and open it to traffic on the occasion of the 70th anniversary of Hai Phong Liberation Day (May 13, 2025).

Along with this project, Hai Phong City promotes the construction of the renovation and upgrading project of the 1.65km section from Hoa River Bridge to Provincial Road 354, Vinh Bao District (under the Hoa River Bridge Construction Investment Project connecting Vinh Bao District, Hai Phong with Thai Thuy District, Thai Binh Province) and the construction of the road from Provincial Road 354, Tien Lang District to National Highway 10, Vinh Bao District. Thai Binh Province focuses on completing the road project from Thai Binh to Nghin Bridge under the form of a BOT contract, 21.28 km long (starting point from the beginning of Hoa River Bridge, An Thanh Commune, Quynh Phu District, the end point connecting to Vo Nguyen Giap Road in Dong My Commune, Thai Binh City) in 2025. Thereby, promoting the effectiveness of the projects, creating a regional traffic connection system for the goal of modernizing the traffic infrastructure of both Hai Phong and Thai Binh localities.

Hoàng Khôi
TIN LIÊN QUAN

Opening of exhibition on the tradition of mandarin examinations in Hai Phong city

|

Hai Phong - On November 30, at the Hang Kenh communal house relic (Le Chan, Hai Phong), the exhibition "Van Mieu - Quoc Tu Giam and Hai Phong's tradition of mandarin examinations" was displayed.

Revealing the investor of the industrial cluster worth over 900 billion VND in Hai Phong

|

Hai Phong - Tien Lang District People's Committee (Hai Phong) announced the receipt of investor documents for the construction of infrastructure for Quyet Tien Industrial Park.

Nearly 100 Hai Phong union officials trained in democratic regulations

|

Hai Phong - On the morning of November 30, the Hai Phong Industry and Trade Union trained nearly 100 grassroots union officials on implementing grassroots democracy regulations at work.

Disciplinary action against Vice Chairman of Ha Giang Provincial People's Committee

|

The Prime Minister has disciplined Mr. Tran Duc Quy - Vice Chairman of Ha Giang Provincial People's Committee, for violations and shortcomings.

"The person who follows the job" when transferring corporations to ministries

|

The transfer of management personnel of corporations and general companies according to the principle of "people follow the work" is in sync with the business transfer plan.

Removing tax and customs barriers helps businesses recover

|

The Ministry of Finance affirmed that it will strongly reform tax and customs policies to remove difficulties and create conditions for businesses to recover and develop sustainably.

2 advantages of Vietnam team against Indonesia in ASEAN Cup

|

Indonesian newspaper CNN pointed out two advantages of the Vietnamese team before the match against the national team of this country at the ASEAN Cup (formerly known as AFF Cup) 2024.

South Korean National Assembly passes bill to investigate President Yoon

|

South Korea's National Assembly passes bill to appoint special prosecutor to investigate President Yoon Suk Yeol.

Opening of exhibition on the tradition of mandarin examinations in Hai Phong city

Mai Dung |

Hai Phong - On November 30, at the Hang Kenh communal house relic (Le Chan, Hai Phong), the exhibition "Van Mieu - Quoc Tu Giam and Hai Phong's tradition of mandarin examinations" was displayed.

Revealing the investor of the industrial cluster worth over 900 billion VND in Hai Phong

Hoàng Khôi |

Hai Phong - Tien Lang District People's Committee (Hai Phong) announced the receipt of investor documents for the construction of infrastructure for Quyet Tien Industrial Park.

Nearly 100 Hai Phong union officials trained in democratic regulations

Mai Dung |

Hai Phong - On the morning of November 30, the Hai Phong Industry and Trade Union trained nearly 100 grassroots union officials on implementing grassroots democracy regulations at work.