The shape of Hanoi's Ring Road 4 after 15 months of construction

HỮU CHÁNH |

Hanoi - Many parallel sections of Ring Road 4 have taken shape after 15 months of construction.

On the afternoon of November 9, at the parallel road of Ring Road 4 through Hoai Duc district (Hanoi), reporters of Lao Dong Newspaper recorded that the project has had many obvious changes after 15 months of construction.

At the construction site, many machines, workers, and engineers are mobilized to construct project items. The construction site almost never has a moment of silence.

Package No. 9 (Component Project 2.1, construction of parallel road to Hanoi Ring Road 4) is constructed by contractor Vinaconex. The total length of the route is about 21km, passing through 2 districts of Hoai Duc and Dan Phuong.

Speaking with Lao Dong, Mr. Nguyen Hoang Hai - Commander of Package No. 9 - said that after 15 months from the start of construction, the section of the route undertaken by the contractor has reached nearly 40% of its output.

At the construction site, about 200 machines and 300 workers are working with a total of 18 construction teams day and night, speeding up the project's progress.

"Up to now, the construction progress is still on schedule. The contractor is striving to complete the sections with available land in 2025," Mr. Hai affirmed.

According to the commander of package 9, there are many interruptions and "sticky rice" points on the route, including 10 points in Hoai Duc district and 2 points in Dan Phuong district. The constructions blocking the ground are mainly residential areas, factories, underground and above-ground technical infrastructure systems.

"The local site clearance progress is slowing down, potentially affecting the contractor's construction progress," Mr. Nguyen Hoang Hai worried.

Regarding the progress of the 57km parallel road project of Ring Road 4 through Hanoi, the Hanoi Traffic Construction Investment Project Management Board said that 4 construction packages have been simultaneously deployed by contractors on the handed over land area with 32 construction points (23 road points, 9 bridge points).

The output to date has reached about 36.86%. Hanoi City is focusing on clearing the remaining sections to hand over to the contractor in 2024. The parallel road of Ring Road 4 through Hanoi is expected to be completed in the fourth quarter of 2025.

Doan tuyen qua xa Tien Yen (Hoai Duc) da ro hinh hai va dang duoc tham nhua mat duong. Anh: Huu Chanh
After 15 months of construction, package 9 of the 21km parallel road through Hoai Duc and Dan Phuong districts has basically completed the roadbed in the sections where the ground has been cleared. Photo: Huu Chanh
Doan tuyen qua xa Tien Yen (Hoai Duc) da ro hinh hai va dang duoc tham nhua mat duong. Anh: Huu Chanh
The section through Tien Yen commune (Hoai Duc) has taken shape and is being paved with asphalt. Photo: Huu Chanh
Ngay 9.11, nha thau dang trien khai tham nhua rong C25 doan qua xa Tien Yen, huyen Hoai Duc. Anh: Huu Chanh
On November 9, the contractor deployed C25 hollow plastic mats through Tien Yen commune, Hoai Duc district. Photo: Huu Chanh
300 dau may, 200 ky su, cong nhan duoc huy dong, lam viec ngay dem tren cong truong du an. Anh: Huu Chanhsong
300 locomotives, 200 engineers and workers were mobilized, working day and night at the project site. Photo: Huu Chanh
May moc, cong nhan duoc huy dong tham nhua mat duong. Anh: Huu Chanh
Workers are constructing the asphalt pavement project. The contractor is also in the process of completing the second asphalt concrete station, and is expected to have two asphalt concrete production lines in operation by December. Photo: Huu Chanh
Cong tac thi cong cap phoi da dam da trien khai 8km duong song hanh (16km duong tuyen).
The crushed stone construction work has been deployed along 8km of parallel road. Photo: Huu Chanh
a
At the construction site, the contractor arranged 3 construction lines for the crushed stone grading item. Photo: Huu Chanh
Ve vat lieu thi cong Base hien nha thau da tap ket 8 bai vat lieu tren cong truong, da chuyen 70% khoi luong vat lieu Base cho hop dong.
8 material yards are gathered at the construction site to serve the construction of crushed stone aggregate items. Photo: Huu Chanh
Sau 15 thang thi cong, den nay goi thau so 9 dai 21km qua huyen Hoai Duc va Dan Phuong da co ban hoan thanh hang muc nen duong o nhung doan da co mat bang. Anh: Huu Chanh
The 57km parallel road of Ring Road 4 through Hanoi is expected to be completed in 2025. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

5 years waiting for 10-lane road, capital of nearly 1,500 billion VND in Hanoi

|

Hanoi - Construction started in 2019 and was expected to be completed after 2 years, but to date, the project to build Tay Thang Long road, more than 3km long and costing nearly 1,500 billion VND, is still unfinished.

More good news about the road project connecting Tay Ho with Son Tay town

|

Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.

Iran wins best film, Vietnam has 1 award at HANIFF 2024

|

The closing ceremony and awards ceremony of the Hanoi International Film Festival (HANIFF) announced the winning works and individuals.

Awarding the press prize on national solidarity

|

The 2023-2024 "For the cause of great national unity" Press Award was held on the evening of November 11.

8pm News: Subsidies increase, people with police status enjoy the benefits

|

News at 8pm on November 11: Pensions and allowances for meritorious people increase, the elderly feel secure in their old age; Hanoi plans to reclaim land from more than 300 households to open a 60m wide road...

Selling at a difference of 300 - 500 million VND/lot after Hoai Duc land auction

|

Hanoi - Immediately after the auction in Hoai Duc district ended, many land brokers quickly sold each plot of land for a difference of 300-500 million VND.

Fierce street fighting in strategic eastern Ukraine city

|

Russia says street fighting has begun in strategic eastern Ukraine city.

Mr. Pham Thanh Ngai was elected Chairman of Ca Mau Provincial People's Committee

|

Ca Mau - Before being elected Chairman of the Provincial People's Committee, Mr. Pham Thanh Ngai was the Standing Deputy Secretary of the Provincial Party Committee.

5 years waiting for 10-lane road, capital of nearly 1,500 billion VND in Hanoi

HỮU CHÁNH |

Hanoi - Construction started in 2019 and was expected to be completed after 2 years, but to date, the project to build Tay Thang Long road, more than 3km long and costing nearly 1,500 billion VND, is still unfinished.

Cầu qua sông thành hình rồi bỏ hoang nhiều năm ở Hà Nội

HỮU CHÁNH |

Hà Nội - Cầu L3 đường Vành đai 2,5 (đoạn Đầm Hồng - Quốc lộ 1) hoàn thành nhiều hạng mục chính rồi bỏ hoang, phơi nắng mưa nhiều năm qua.

More good news about the road project connecting Tay Ho with Son Tay town

HỮU CHÁNH |

Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.