More than 150 construction teams on the entire Tuyen Quang - Ha Giang expressway

Nguyễn Tùng |

On holidays, on the Tuyen Quang - Ha Giang expressway construction site, the sound of machines is still bustling, and construction items are racing for progress.

The Tuyen Quang - Ha Giang expressway project is expected to be completed by the end of the third quarter of 2026. This is the sprint time for bidding packages to complete construction volume, compensating for the time affected by weather and material fluctuations.

Recorded on April 30 and May 1, on the entire route of more than 100km, the construction site was still bustling with engine sounds, and construction work took place continuously day and night.

At package 20, from Km23+00 to Km26+638 and Yen Son intersection, constructed by Cuong Thinh Construction Investment Group, it has now reached more than 72% of the contract value. It is expected that by May 10, two layers of asphalt concrete will be completed.

Mr. Nguyen Van Tinh - Commander of the construction site said that during the April 30 - May 1 holiday this year, the construction site still arranged about 90 workers and more than 30 machines and equipment to work regularly at the construction site.

Các gói thầu xây lắp được đẩy nhanh tiến độ, thi công cả ngày lẫn đêm. Ảnh: Nguyễn Tùng.
Construction packages are being accelerated, constructed day and night. Photo: Nguyen Tung

Workers and employees are guaranteed both material and spiritual benefits. On holidays, we organize parties and training according to regulations, so that everyone can rest assured to stick to the construction site," Mr. Tinh said.

At package No. 19, constructed by Truong Son Construction Corporation with a length of more than 12.8km, it currently reaches 90% of the contract value. 4 construction teams and hundreds of equipment, cadres, engineers, and workers stick to the construction site throughout the holidays.

At the Ham Yen bridge construction site at Km49+663, which is a key item under construction package No. 24 constructed by Deo Ca Group, the bridge surface asphalt is currently being prepared. This is the river overpass with the most complex length and structure of the project.

According to the investor's report, for the section passing through Ha Giang (old) province, a total length of 27 km is being implemented with 5 construction packages. Currently, contractors have organized the simultaneous deployment of nearly 40 construction fronts.

Cao tốc Tuyên Quang - Hà Giang đi qua phần lớn địa hình đồi núi, địa chất phức tạp. Ảnh: Nguyễn Tùng.
Tuyen Quang - Ha Giang expressway passes through most of the hilly terrain, complex geology. Photo: Nguyen Tung

Construction progress reached 91.4% of the construction contract value. Site clearance (GPMB), technical infrastructure relocation and resettlement area construction have been completed, and construction materials meet construction requirements.

For the section passing through Tuyen Quang province with a total length of 77 km, 13 construction packages are being implemented. The construction site maintains more than 111 construction fronts, progress reaching 62% of the contract value.

Also according to the investor's assessment, the overall progress of the project is still slow compared to the plan due to previous difficulties in site clearance, unfavorable weather and material price fluctuations.

Nhiều vị trí địa hình phức tạp đã ảnh hưởng tới tiến độ thi công. Ảnh: Nguyễn Tùng.
Many complex terrain locations have affected the construction progress. Photo: Nguyen Tung

On April 29, inspecting the progress of the Tuyen Quang - Ha Giang expressway project, Mr. Hau A Lenh - Secretary of the Tuyen Quang Provincial Party Committee requested relevant units to continue to improve their sense of responsibility, not avoid, not push, focus on completely removing each bottleneck, especially site clearance work.

The Secretary of the Tuyen Quang Provincial Party Committee requested that issues related to legal procedures, design adjustments, and volume arising should be summarized and reported to competent authorities for consideration and timely resolution, avoiding prolonged backlog affecting the overall progress.

Tuyen Quang - Ha Giang expressway (phase 1), belonging to group A project, the total length of the route is over 104km, with a total investment of 13,800 billion VND.

After completion, this expressway will help increase traffic connectivity between Tuyen Quang province and neighboring areas. At the same time, it will promote socio-economic development in the Northern mountainous region.

Nguyễn Tùng
RELATED NEWS

Land fund planning for construction of rest stops on Tuyen Quang - Ha Giang expressway

|

Investing in rest stops helps develop the service economy, opening up new development space, and improving the operational efficiency of the Tuyen Quang - Ha Giang expressway.

Tuyen Quang sets a goal to eliminate the white area of national power grids

|

Tuyen Quang province strives to complete the investment in power supply for villages and residential areas that do not yet have national grid electricity by the end of the second quarter of 2027.

Tourism development road worth nearly 500 billion VND in Tuyen Quang is about to reach the finish line

|

The nearly 9km long road connecting My Lam Tourist Area with the Tuyen Quang - Phu Tho expressway is expected to promote tourism development and attract investment.

Accident of ambulance and motorbike, 1 person died on the road without acceptance

|

Ho Chi Minh City - In Long Hoa commune, an accident occurred between an ambulance and a motorbike, killing 1 person, the police agency is verifying and clarifying.

Protection forest fire in Quang Tri, many forces mobilized to fight the fire

|

Quang Tri - Detecting a forest fire, Trieu Van Border Guard Station and units came to fight the fire.

Dong Dang - Tra Linh expressway construction site no holiday when completion deadline approaches

|

Cao Bang - Thousands of workers are constructing during the holiday at the Dong Dang - Tra Linh expressway construction site, accelerating for phase 1 to be completed on May 19.

Land fund planning for construction of rest stops on Tuyen Quang - Ha Giang expressway

Nguyễn Tùng |

Investing in rest stops helps develop the service economy, opening up new development space, and improving the operational efficiency of the Tuyen Quang - Ha Giang expressway.

Tuyen Quang sets a goal to eliminate the white area of national power grids

Nguyễn Tùng |

Tuyen Quang province strives to complete the investment in power supply for villages and residential areas that do not yet have national grid electricity by the end of the second quarter of 2027.

Tourism development road worth nearly 500 billion VND in Tuyen Quang is about to reach the finish line

Nguyễn Tùng |

The nearly 9km long road connecting My Lam Tourist Area with the Tuyen Quang - Phu Tho expressway is expected to promote tourism development and attract investment.