Planning to build a overpass on the La Son - Hoa Lien expressway to prevent landslides

PHÚC ĐẠT |

HUE - The investor is planning to build a overpass at Km50+800 (La Son - Hoa Lien expressway) to prevent the risk of landslides.

On November 23, a representative of the Ho Chi Minh Road Project Management Board said that they are developing a plan to build a overpass at Km50+800 (La Son - Hoa Lien Expressway, Da Nang City) to prevent the risk of landslides. This November, there will be a specific plan.

Along with that, from 5:00 a.m. on November 21 to 5:00 p.m. on December 5, passenger cars and trucks on 6 axes are prohibited from traveling through the La Son - Hoa Lien Expressway. The remaining vehicles are only allowed to travel from 5am to 5pm every day. This is a temporary measure to ensure safety when many points on the route are still at risk of landslides after many days of heavy rain.

According to the Ho Chi Minh Road Project Management Board, the flood at the end of October 2025 caused severe damage to many sections of the North - South expressway expansion project in the East, La Son - Hoa Lien section. More than 5,000m3 of mud and soil have covered the road, 1,000 - 1,500m3 of silted rocks and over 1,000m3 of negative slopes have been eroded. The harsh terrain and saturated soil made the repair difficult.

Tinh trang sat lo tren cao toc La Son - Hoa Lien dang duoc khac phuc, xu ly khan truong. Anh: Tran Hiep
The landslide on the La Son - Hoa Lien expressway is being urgently resolved and handled. Photo: Tran Hiep

In recent days, Hue and Da Nang have continued to have heavy rain, as a result of which small landslides continued to appear at Km42+700 - Km42+800. This phenomenon shows that the slope is still unstable, and a large slide can form at any time. Although the force and equipment are on duty 24/7, allowing vehicles to travel at night is considered unsafe.

Therefore, the two sections Km42+700 - Km42+800 and Km50+700 - Km50+800 continue to operate with only one lane, with a permanent regulating force from November 21 to December 5. After the monitoring phase, if safety conditions are confirmed, the route will be opened to 2 lanes and return to normal operation.

Recently, the Project Management Board has mobilized many leveling machines, straightening the flow to limit erosion, and reinforcing damaged points, some landslide bridge abutments have been basically handled.

PHÚC ĐẠT
RELATED NEWS

Passenger bus fire on the highway section through Thanh Hoa

|

Thanh Hoa - A passenger bus was traveling on the highway when it suddenly caught fire, fortunately the incident did not cause any human casualties.

The overwhelming joy of highway construction workers being rescued from the fierce flood in Dak Lak

|

Dak Lak - A group of workers working on the North-South expressway trapped in the severe flood area have been rescued promptly and safely.

Temporarily closing some sections of the expressway towards Khanh Hoa to divert traffic

|

The Traffic Police Department is temporarily closing some sections of the expressway from Lam Dong to Khanh Hoa to regulate vehicles to National Highway 1, reducing traffic flow to flooded areas.

Expectations to increase autonomy, solve difficulties in press economics

|

According to the program of the 10th Session, tomorrow (November 24), the National Assembly will discuss in the hall the draft Press Law (amended).

Massive landslides at 33 locations near Khanh Le Pass, 22,158m3 of rock and soil blocking Lam Dong road to Khanh Hoa

|

Lam Dong - National Highway 27C connecting Da Lat - Nha Trang (Khanh Hoa) near Khanh Le Pass continues to have landslides at many points, causing traffic congestion.

Weather forecast for the North is about to change due to increased cold air

|

According to the meteorological agency, due to the impact of the strengthening cold air, from November 25, the North will be cold, with some mountainous areas experiencing severe cold.

The 12,500 billion VND dream of Vietnamese cinema seen from the breakthrough in 2025

|

"Truy tim dragon dien huong" surpassed the 100 billion VND revenue mark, bringing the total number of "hundred billion" works in 2025 to 12 films.

Dust from Ring Road 4 construction site attacks houses, business stagnates

|

Hanoi - People and businesses along National Highway 6 are miserable because of the dust from the Ring Road 4 project, dusty houses, stagnant business, and health is threatened every day.

Passenger bus fire on the highway section through Thanh Hoa

QUÁCH DU |

Thanh Hoa - A passenger bus was traveling on the highway when it suddenly caught fire, fortunately the incident did not cause any human casualties.

The overwhelming joy of highway construction workers being rescued from the fierce flood in Dak Lak

BẢO TRUNG |

Dak Lak - A group of workers working on the North-South expressway trapped in the severe flood area have been rescued promptly and safely.

Temporarily closing some sections of the expressway towards Khanh Hoa to divert traffic

Duy Tuấn |

The Traffic Police Department is temporarily closing some sections of the expressway from Lam Dong to Khanh Hoa to regulate vehicles to National Highway 1, reducing traffic flow to flooded areas.