Progress of a series of key transport projects in Bac Ninh

Vân Trường |

Bac Ninh - On April 23, Vice Chairman of the Provincial People's Committee Phan The Tuan chaired a working session to assess the progress of site clearance (GPMB) for key transport projects.

At the meeting, the progress of some major transport projects was reviewed.

The Van Ha bridge project (connecting Van Ha ward and Kinh Bac ward) has a total capital of nearly 420 billion VND, and has now started construction of bridge piers, drilling, and girder casting; the disbursed value reached more than 109 billion VND. Localities strive to complete the handover of land before May 31 to ensure progress.

The project to renovate and upgrade DT. 291 (total investment of more than 477 billion VND) has started the main bidding package, deploying roadbed excavation. Site clearance is being carried out, and the first phase of site handover is expected before May 30, the next phases will be completed in July and October 2026.

Meanwhile, the project of connecting Van Trung Industrial Park with Quang Chau Industrial Park (more than 443 billion VND) has completed investment preparation procedures but has not been allocated capital in 2026, posing a risk of delay in progress.

The project to upgrade and expand DT. 293 has started construction, contractors are mobilizing manpower and equipment to deploy construction throughout the route. Site clearance work in localities has achieved positive results, some areas have completed inventory, developed compensation plans, and strived to hand over land in May and June 2026.

Opinions at the meeting assessed that the site clearance work was basically implemented synchronously, and many households agreed. However, there are still obstacles related to land origin, compensation policies, resettlement and technical infrastructure relocation.

Concluding the working session, Vice Chairman of Bac Ninh Provincial People's Committee Phan The Tuan emphasized that site clearance is a key task, deciding the progress of projects. Mr. Tuan requested the Project Management Board to conduct a comprehensive review, develop a detailed plan, closely monitor the site, urge contractors to mobilize human resources and equipment; ensure quality, labor safety and project safety.

Localities need to strengthen coordination, promptly remove obstacles, promote propaganda to get people's consensus, and strictly handle cases of non-compliance to ensure the progress of site handover.

Regarding the Van Ha bridge project, provincial leaders requested to complete site handover in May 2026. For the DT. 291 project, it is necessary to choose construction solutions suitable to the terrain and proactively develop disaster prevention plans. For the connecting route of Van Trung Industrial Park - Quang Chau Industrial Park, it is necessary to soon allocate capital for implementation because it plays an important role in attracting investment.

Vân Trường
RELATED NEWS

Bac Ninh promotes progress of Yen Lu Industrial Park project

|

Bac Ninh - Vice Chairman of the Provincial People's Committee Pham Van Thinh requested to accelerate the progress of the Yen Lu Industrial Park and Yen Lu Industrial Park project (extended part) phase 1.

Bac Ninh: Apartments for workers priced from 223 million VND

|

Bac Ninh - The social housing project for workers in Yen Phong commune will be opened for sale in the second phase, priced from 223 million VND/unit.

610 vehicles fined remotely for the same offense, in 1 week in Bac Ninh

|

Bac Ninh - In one week, there were 610 cases of being fined for speeding.

Ho Chi Minh City Department of Culture and Sports intervenes in the case of B Ray causing controversy due to offensive rap lyrics

|

The Ho Chi Minh City Department of Culture and Sports said that it has grasped the reflected information and is coordinating with relevant agencies to consider the case of rapper B Ray showing offensive rap lyrics.

Hanoi Chairman proposes 3 solutions to soon bring the revised Capital Law into life

|

Chairman of Hanoi People's Committee Vu Dai Thang affirmed that the city will proactively and synchronously implement many solutions to soon bring the revised Capital Law into life.

National Assembly finalizes birth certificates, marriage certificates must be signed by the Chairman of the Commune People's Committee

|

The Law on Civil Status (amended) stipulates that the Chairman of the Commune-level People's Committee must directly sign birth certificates and marriage certificates.

Lao Cai gold - the first gold enterprise to list on the stock exchange fluctuates due to debt

|

Losing the right to exploit Minh Luong gold mine, accumulated losses exceeding charter capital, Lao Cai Gold Company is facing the most difficult period since listing on the stock exchange.

Dismantling construction that collapsed people's houses in Da Nang, many houses are cracked

|

A project on Tran Quy Cap street (Da Nang) during dismantling caused the collapse of a house and damage to many adjacent houses.

Bac Ninh promotes progress of Yen Lu Industrial Park project

Vân Trường |

Bac Ninh - Vice Chairman of the Provincial People's Committee Pham Van Thinh requested to accelerate the progress of the Yen Lu Industrial Park and Yen Lu Industrial Park project (extended part) phase 1.

Bac Ninh: Apartments for workers priced from 223 million VND

Vân Trường |

Bac Ninh - The social housing project for workers in Yen Phong commune will be opened for sale in the second phase, priced from 223 million VND/unit.

610 vehicles fined remotely for the same offense, in 1 week in Bac Ninh

Vân Trường |

Bac Ninh - In one week, there were 610 cases of being fined for speeding.