Land clearance problems, 122 billion VND project in Can Tho has been stuck for 2 years

YẾN PHƯƠNG |

Can Tho - The traffic project worth more than 122 billion VND has been delayed for more than 2 years, due to problems with 175m of uncleared land.

The project to upgrade and expand Tran Phu Street Phase 1 (in Ninh Kieu District, Can Tho City) is over 1km long, with a total investment of over VND 122.4 billion, starting in October 2021, expected to be completed in October 2022. However, the project has not been completed yet.

Anh: Yen Phuong
Tran Phu Street is more than 1km long in Ninh Kieu District, Can Tho City. Photo: Yen Phuong

According to the reporter's records, the entire Tran Phu route is currently with 3 lanes, spacious and clean, but it is still not synchronous. At the location from Hung Vuong roundabout to Tran Phu Street, there is a section of road with an old, low, narrow roadbed, with a clear difference compared to the new roadbed.

Anh: Yen Phuong
The road is low, narrow and has many potholes. Photo: Yen Phuong

As a household whose house is affected by the project, Ms. Nguyen Thi Ngoc Dao (Ninh Kieu district) said that her family used to do business and rent, but in recent years, it has not been able to do business and rent, leading to a loss of income.

"The roadbed at this section is rough, narrow and has many potholes, causing inconvenience to people's travel, especially during rush hour. Garbage trucks traveling to the garbage collection point are also difficult. On days of heavy rain or high tides, high water flooded into the house, Ms. Dao shared.

Anh: Yen Phuong
Every afternoon, this road has many garbage trucks moving to the garbage collection point. Photo: Yen Phuong

Speaking with Lao Dong on March 17, Mr. Nguyen Hoang Giang - Director of Tri Viet Construction Investment Joint Stock Company (construction unit) - said that for the project to Upgrade and Expand Tran Phu Street Phase 1, the unit has completed over 80% of the project volume. However, there are still 175m of site that have not been handed over, from Nguyen Trai Street to the commercial center.

"We have completed the road on the other side for more than 2 years but have not been able to hand over the project, because we have to wait for the site for this section to construct. If there is a site, in favorable weather conditions, the unit plans to complete the construction within more than 2 months," said Mr. Giang.

Anh: Yen Phuong
Many households had to close their doors, making business difficult. Photo: Yen Phuong

The fact that the site has not been handed over has generally affected the project progress. Therefore, the construction unit also hopes that the locality and the investor will pay attention to site clearance to carry out the construction of the remaining road section, complete the project, and facilitate people to participate in traffic and business and trading.

According to the leader of Ninh Kieu District People's Committee, the project has been suspended for quite a long time due to land clearance problems. The district has conducted statistics to analyze each case in order to find a solution. However, there are still cases with land areas over 15m2, not eligible for resettlement according to regulations, but also not eligible for a construction permit.

At the inspection of basic construction work in Ninh Kieu district on March 14, Mr. Nguyen Tien Phong - Secretary of Ninh Kieu District Party Committee - requested the District Project Management and Land Fund Development Board to coordinate with departments, professional offices and wards to speed up the progress of compensation, support and resettlement for affected cases; at the same time, recommended that the city adjust the planning for the Tran Phu Road Upgrade and Expansion Project Phase 1 to suit the actual local situation.

YẾN PHƯƠNG
TIN LIÊN QUAN

Scene of the house wall collapse while being demolished in Can Tho

|

Can Tho - On the afternoon of March 15, a house wall collapsed near the Mau Than - 3 Thang 2 - Tran Hung Dao intersection (Ninh Kieu district), causing a worker to suffer minor injuries.

Can Tho resolves the backlog of the National Highway 91 expansion project

|

Can Tho - Authorities are actively resolving the outstanding issues of the National Highway 91 expansion project, including compensation payment and resettlement arrangements.

The reason why a 1km stretch of road in Can Tho is still unfinished

|

Can Tho - The project to upgrade and expand Tran Phu Street (Ninh Kieu District) has been suspended for quite a long time due to problems with site clearance.

Reviewing land in Dong Anh to relocate people around Hoan Kiem Lake

|

Hanoi - The leader of Dong Anh district said that the district is conducting a land review in the area to serve the resettlement of households around Hoan Kiem Lake.

Can Tho's largest landfill is overloaded, at risk of dike breach

|

Can Tho - Dong Thang landfill with a "huge" amount of waste is at risk of breaking the dike, causing serious pollution consequences.

Signing the emulation agreement for 2025 of the Southeast Emulation Cluster

|

Binh Thuan and 6 provinces in the Emulation Cluster of Southeast provinces signed an emulation agreement in 2025.

Trump Group wants to speed up a $1.5 billion project in Hung Yen

|

Trump Organization wants to accelerate the $1.5 billion project in Hung Yen province; hopes the project will be completed in the next 2 years (March 2027).

New information on funding for breaking the Shark Dock, restoring infrastructure

|

Hanoi - The budget for demolishing the Shark Dock and returning infrastructure is expected to decrease from 18 billion VND to about 11 billion VND.

Scene of the house wall collapse while being demolished in Can Tho

QUANG PHƯƠNG |

Can Tho - On the afternoon of March 15, a house wall collapsed near the Mau Than - 3 Thang 2 - Tran Hung Dao intersection (Ninh Kieu district), causing a worker to suffer minor injuries.

Can Tho resolves the backlog of the National Highway 91 expansion project

YẾN PHƯƠNG |

Can Tho - Authorities are actively resolving the outstanding issues of the National Highway 91 expansion project, including compensation payment and resettlement arrangements.

The reason why a 1km stretch of road in Can Tho is still unfinished

YẾN PHƯƠNG |

Can Tho - The project to upgrade and expand Tran Phu Street (Ninh Kieu District) has been suspended for quite a long time due to problems with site clearance.