The road project worth over VND770 billion in Hue is about to be completed after more than 10 years of waiting

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE - The Phong Dien - Dien Loc rescue road project with a total investment of more than 770 billion VND is about to be completed after more than 10 years of waiting.

Ngay 7.7, trao doi voi PV Bao Lao Dong, dai dien Ban Quan ly du an dau tu xay dung cac cong trinh giao thong TP Hue cho biet, du an duong cuu ho, cuu nan Phong Dien - Dien Loc dang buoc vao giai doan cuoi cung voi nhieu hang muc chu chot da hoan thanh.
On July 7, speaking with a reporter from Lao Dong Newspaper, a representative of the Hue City Traffic Construction Investment Project Management Board said that the Phong Dien - Dien Loc rescue project is entering the final stage with many key items completed.
Theo bao cao tien do, den thoi diem hien tai, doan tuyen tu Km1+500 den Km9+800, cau Thiem va cau Bau Bang da duoc ban giao va dua vao su dung. Cau Vuot duong sat, mot hang muc quan trong da hoan thanh, don vi thi cong dang tap trung lam lan can, ve sinh va thu don hien truong.
According to the progress report, up to now, the section from Km1+500 to Km9+800, Thiem Bridge and Bau Bang Bridge have been handed over and put into use. The railway overpass, an important item, has been completed, the construction unit is focusing on railing, cleaning and clearing the site.
Doan dau tuyen tu Km0 den Km1+500, bao gom ca 4 duong gom dan sinh trong pham vi cau vuot duong sat cung da hoan tat. Tuong tu, phan cau cua hai cau Hoa Xuan 1 va Hoa Xuan 2 da hoan thanh.
The first section of the route from Km0 to Km1+500, including all 4 residential access roads within the railway overpass, has also been completed. Similarly, the bridge sections of Hoa Xuan 1 and Hoa Xuan 2 bridges have been completed.
Doan nut giao voi quoc lo 1A hien da co ban hoan thien. Cac nha thau dang khan truong thi cong son ke vach tai dai phan cach giua va xu ly cac nut giao noi dong.
The intersection with National Highway 1A is now basically completed. Contractors are urgently painting lines on the median strip and handling in-field intersections.
Dong thoi, cong tac trong cay xanh, lap dat dien chieu sang, don dep ve sinh cung dang duoc day manh, phan dau hoan thanh truoc ngay 15.7.2025.
At the same time, the work of planting trees, installing lighting, and cleaning is also being accelerated, striving to complete before July 15, 2025.
Ve ke hoach von, den nay tong muc von duoc bo tri cho du an la 666 ti dong.
Regarding the capital plan, the total capital allocated for the project is currently VND66 billion.
Ghi nhan cua PV Bao Lao Dong nhung ngay dau thang 7, toan tuyen da co ban thong suot, rat nhieu phuong tien da luu thong tren tuyen duong sau hon 10 nam cho doi.
According to Lao Dong Newspaper's reporter in early July, the entire route was basically smooth, many vehicles were circulating on the route after more than 10 years of waiting.
Cac cong nhan tat bat voi cong tac don dep hai ben le duong.
Workers are busy clearing both sides of the road.
Cac bien bao giao thong cung da duoc lap dat day du.
Traffic signs have also been fully installed.
Ban Quan ly du an cho biet, don vi thi cong dang tap trung day nhanh viec thi cong doan cuoi tuyen va cac nut giao dan sinh nham hoan thanh toan bo cong trinh, khanh thanh vao 2.9.2025.
The Project Management Board said that the construction unit is focusing on speeding up the construction of the final section of the route and the intersections for people to complete the entire project and inaugurate it on September 2, 2025.

The Phong Dien - Dien Loc rescue road project worth more than 770 billion VND was started in 2012 with a total length of more than 16.2km. The starting point of the project intersects with National Highway 1A in Phong Dien Ward and the end point is at Phong Phu Ward beach, Hue City.

The project was approved in 2010 by the Hue City Traffic Construction Investment Project Management Board as the investor.

The goal of the project is to complete the infrastructure of the Tam Giang - Cau Hai lagoon area, proactively prevent and respond to natural disasters and promote socio-economic development.

The project is expected to be completed after 3 years from the start date. However, it has been 13 years since the project was ready to reach the finish line. The reason is that this project is included in the list of projects allocated capital from the Central Rescue and Road Construction Program. However, after the Government tightened public investment, this project had to temporarily suspend construction.

Faced with that situation, in January 2024, the People's Council of Thua Thien Hue province (now the People's Council of Hue city) adjusted and added more than 100 billion VND.

PHÚC ĐẠT - NGUYỄN LUÂN
TIN LIÊN QUAN

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

|

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Prosecution of the case and 5 defendants related to the investment project to build a second facility of the two hospitals

|

The Investigation Police Agency has prosecuted the case and prosecuted 5 defendants related to the case that occurred in 2 investment projects to build the second facility of Bach Mai and Viet Duc Hospitals.

The contrasting picture behind PJICO's growth figures

|

Motor vehicle insurance brings a large source of income to PJICO, but also carries high risks because all compensation is borne by the enterprise itself.

Fire in a tourist electric vehicle parking lot in Huong Tich pagoda area, many cars burned down

|

Ha Tinh - At noon on July 8, a major fire broke out at the electric car parking lot in the Huong Tich pagoda tourist area, burning down 9 electric cars and 1 car.

Consider handling organizations and individuals if there are violations in the bidding package proposed by Son Hai Group

|

The Ministry of Finance has just sent a document reporting to the Government on the bid package previously proposed by Son Hai Group.

Big fire at fabric warehouse in Da Nang, many assets and equipment burned down

|

Da Nang - As of 10:00 a.m. on July 8, the Da Nang Fire Police force was still trying to handle the fire at a fabric warehouse on Nguyen Dinh Tuu Street, An Khe Ward.

A major road in Hanoi is under repair, vehicles are banned from circulating from night to morning

|

Hanoi - From 10pm - 6am, vehicles are prohibited from traveling on Ring Road 3 from Nguyen Trai - Thang Long Avenue to repair the expansion joints and bridge deck.

Landslide on National Highway 15D, road to La Lay International Border Gate cut off

|

Quang Tri - The landslide occurred while the construction unit was expanding the curve on National Highway 15D to the La Lay international border gate, causing traffic disruption.

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Prosecution of the case and 5 defendants related to the investment project to build a second facility of the two hospitals

Vương Trần |

The Investigation Police Agency has prosecuted the case and prosecuted 5 defendants related to the case that occurred in 2 investment projects to build the second facility of Bach Mai and Viet Duc Hospitals.

Bị thu hồi đất làm dự án, dân tạm cư cả năm vì khu tái định cư xây chưa xong

HƯNG THƠ |

Quảng Trị - Sau khi bàn giao nhà cửa cho dự án giao thông trọng điểm, người dân phải sống tạm bợ vì khu tái định cư chậm tiến độ.