By the end of June, the National Highway 91 expansion project must disburse all VND 3,235 billion

Tạ Quang |

Can Tho - To ensure progress and quality, by the end of June 2025, the project to upgrade and expand National Highway 91 must disburse all the capital allocated in 2025.

Recently, Permanent Vice Chairman of Can Tho City People's Committee Duong Tan Hien signed an official dispatch requesting increased responsibility and completion of procedures to implement the National Highway 91 Upgrade and Expansion Project (from Km0 - Km7).

Cot Km7 cua Quoc lo 91 o Can Tho. Anh: Ta Quang
Km7 column of National Highway 91 in Can Tho. Photo: Ta Quang

Relevant departments and branches, including the Department of Agriculture and Environment, the Department of Construction, the Department of Industry and Trade, the Can Tho City Land Fund Development Center, the People's Committees of Ninh Kieu and Binh Thuy districts and related units, need to promptly resolve problems and bottlenecks according to their authority.

The Can Tho City Construction Investment Project Management Board needs to proactively coordinate closely with relevant departments, branches and localities to urgently complete compensation, support, resettlement, relocation of technical infrastructure works, and speed up the project implementation progress (strive to start construction of some items/packages on the occasion of the April 30 holiday).

At the same time, ensuring progress and quality, by the end of June 2025, all of the VND 3,235 billion allocated in 2025 must be disbursed.

Quoc lo 91 nhin tu tren cao. Anh: Ta Quang
National Highway 91 seen from above. Photo: Ta Quang

The project to upgrade and expand National Highway 91 (section from Km0 - Km7) with a total investment of nearly VND 7,238 billion is being urgently implemented by Can Tho City. This is a key project, of great significance in the city's socio-economic development.

The project has a total planned land area of about 27.25 hectares; affecting about 1,066 households, individuals and organizations; with a need for resettlement of about 300 plots.

The National Highway 91 Upgrade and Expansion Project (section from Km0 - Km7), Can Tho City is a Group A project, a level 1 road traffic project, with implementation period from 2023 - 2027. The overall goal of the project is to complete the transport infrastructure, striving to build Can Tho into a modern and civilized city, basically becoming an industrial city.

Tạ Quang
TIN LIÊN QUAN

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

|

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

Can Tho resolves the backlog of the National Highway 91 expansion project

|

Can Tho - Authorities are actively resolving the outstanding issues of the National Highway 91 expansion project, including compensation payment and resettlement arrangements.

Can Tho advances more than 410 billion VND to upgrade 7km of National Highway 91

|

Can Tho - Can Tho City People's Committee has allocated more than 410 billion VND in advance capital for the project to upgrade and expand National Highway 91 (section from Km0 - Km7).

Big fire at night in Ba Vi National Park

|

Hanoi - A large fire suddenly broke out in the Chang Re mountain area - Ba Vi National Park.

Binh Thuan celebrates 50 years of construction, innovation and development

|

Binh Thuan - On the evening of April 19, in Phan Thiet city, Binh Thuan province held a ceremony to celebrate the 50th anniversary of the Liberation of the province.

For the first time, Con Dao has a sea turtle conservation tour worth more than 20 million VND

|

Ba Ria - Vung Tau - Tourists will experience eating, staying and doing work related to sea turtle rescue with the forest rangers in Con Dao.

Nghe An has 3,530 surplus cadres after administrative unit arrangement

|

Nghe An - The whole province will have a surplus of about 3,530 cadres and civil servants after the arrangement of commune-level administrative units.

Reasons for choosing Bac Giang City as the administrative center of Bac Ninh province after the merger

|

Bac Ninh - The project to reorganize Bac Ninh and Bac Giang provinces clearly states the reasons for choosing Bac Giang city as the administrative center after the merger.

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

Tạ Quang |

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

Can Tho resolves the backlog of the National Highway 91 expansion project

YẾN PHƯƠNG |

Can Tho - Authorities are actively resolving the outstanding issues of the National Highway 91 expansion project, including compensation payment and resettlement arrangements.

Can Tho advances more than 410 billion VND to upgrade 7km of National Highway 91

YẾN PHƯƠNG |

Can Tho - Can Tho City People's Committee has allocated more than 410 billion VND in advance capital for the project to upgrade and expand National Highway 91 (section from Km0 - Km7).