Prime Minister requests no change in completion schedule of Long Thanh airport project

PHẠM ĐÔNG |

The Prime Minister requested the organization of "3 shifts, 4 teams", ensuring the completion of the Long Thanh airport project in 2025 in accordance with the commitment.

On August 7, the Government Office announced that it had just issued document No. 401/TB-VPCP announcing the conclusion of Prime Minister Pham Minh Chinh at the online conference to review the first 6 months of 2025 of the State Steering Committee for important national projects and works, key projects in the transport sector (19th session) and review the peak emulation period "500 days and nights of emulation to complete 3,000 km of expressway".

In the 18th meeting on June 22, 2025, the Prime Minister assigned 20 tasks. Up to now, 4 tasks have been completed on time, and 12 tasks are being actively implemented as regular direction and management work.

There are 4 tasks that do not meet the required progress:

1. VEC has not yet approved the Ho Chi Minh City - Long Thanh Expressway expansion project in July 2025.

2. Hanoi City has not started the construction of component project 3 of Ring Road 4 in July 2025.

3. Nghe An, Quang Tri, Quang Ngai, Khanh Hoa, Lam Dong, Dong Nai provinces have not yet handed over the entire site of 8 rest stops for the North - South expressway projects in the 2021-2025 period in July 2025.

4. Dong Nai province has not yet handed over the entire site at DATP1 Bien Hoa - Vung Tau in July 2025.

The Prime Minister requested relevant agencies and localities to urgently focus on directing the early completion of these tasks.

The head of the Government requested the provinces of Dong Nai, Ho Chi Minh City, Tuyen Quang, Khanh Hoa, Dak Lak, and Dong Thap to focus on directing investors and contractors to supplement human resources and equipment, increase construction teams, organize 3 shifts, 4 teams, and apply technical solutions to shorten construction time.

Thereby speeding up the progress of the Ho Chi Minh City Ring Road 3 project, Bien Hoa - Vung Tau, Tuyen Quang - Ha Giang, Khanh Hoa - Buon Ma Thuot, component project 1 Cao Lanh - An Huu and being responsible to the Prime Minister if the project is not completed in 2025.

Lang Son and Cao Bang provinces have directed investors to take advantage of good weather to speed up the construction progress of Huu Nghi - Chi Lang and Dong Dang - Tra Linh projects, ensuring the route is open by the end of 2025.

The Ministry of Construction, the provinces and cities: Ho Chi Minh City, Da Nang, Hue, Hai Phong, Hung Yen, Ninh Binh, Thanh Hoa, Nghe An, Quang Tri, Quang Ngai, Khanh Hoa, Lam Dong, Dak Lak, Gia Lai, Vinh Long, Dong Thap, Ca Mau, An Giang speed up the construction progress of the coastal road system, striving to complete a total of 2,000 km of coastal roads by 2025.

The Prime Minister also requested preparations for the groundbreaking ceremony and inauguration of projects and works to celebrate the 80th Anniversary of National Day on August 19, 2025.

For the Long Thanh airport project, the Prime Minister requested the Ministry of Finance to direct ACV and relevant agencies and units to accelerate, make breakthroughs, supplement human resources, equipment, construction teams, organize "3 shifts, 4 teams", strictly control quality and safety; complete and put into operation in December 2025 in accordance with ACV's commitment.

The head of the Government noted to plant many trees to create a green, clean, beautiful landscape...; prepare human resources and build exploitation scenarios to ensure smooth and professional operation immediately after the project is completed.

Ministries and branches speed up the implementation of construction of headquarters of management agencies, air traffic control towers and other related works to ensure synchronous exploitation.

The Ministry of Construction, Ho Chi Minh City, Hanoi, and Lam Dong province have completed procedures to start the Dau Giay - Tan Phu project, component project 3 of Hanoi Ring Road 4 on the occasion of August 19, 2025; start the Tan Phu - Bao Loc, Ho Chi Minh City - Moc Bai project in the fourth quarter of 2025.

PHẠM ĐÔNG
RELATED NEWS

Complete and open route 2 connecting Long Thanh airport before September 2

|

Dong Nai - Route No. 2 under package 6.12 for the construction of the traffic system connecting Long Thanh airport is expected to open to traffic before September 2

The road connecting Gia Binh airport is on the list of national key projects

|

The Prime Minister decided to add many important national projects, key to the transport sector, including the road connecting Gia Binh airport to Hanoi.

Basically complete Long Thanh airport in 2025

|

With the goal of basically completing in 2025, the Deputy Prime Minister requested to ensure timely and adequate supply of construction materials for Long Thanh airport.

Chain collision between 4 cars on Van Phong - Nha Trang expressway

|

Khanh Hoa - In the early morning of February 8, a multi-vehicle traffic accident occurred on the Van Phong - Nha Trang highway between 4 cars.

Ecotourism, Can Tho orchards are busy welcoming guests near Tet

|

Can Tho - Approaching Tet, tourists choose to go to eco-tourism spots, orchards to play and experience to be close to nature.

Da Nang landlord gives big lucky money to students

|

Da Nang - In the days leading up to Tet, a female landlady on Me Suot street decided to give lucky money of 500,000 VND for each student rented room.

Near Tet, buyers anxiously wait because online orders are delivered late

|

Near Tet, increased online shopping demand has caused many orders to be delivered behind schedule, and buyers are in a state of anxious waiting as the holiday is approaching.

Year-end ship trip of frontline island soldiers

|

Hai Phong - On the last train of the year, Bach Long Vi island soldiers carry wishes from their homeland and determination to keep a peaceful spring for the Fatherland.

Complete and open route 2 connecting Long Thanh airport before September 2

HÀ ANH CHIẾN |

Dong Nai - Route No. 2 under package 6.12 for the construction of the traffic system connecting Long Thanh airport is expected to open to traffic before September 2

The road connecting Gia Binh airport is on the list of national key projects

PHẠM ĐÔNG |

The Prime Minister decided to add many important national projects, key to the transport sector, including the road connecting Gia Binh airport to Hanoi.

Basically complete Long Thanh airport in 2025

PHẠM ĐÔNG |

With the goal of basically completing in 2025, the Deputy Prime Minister requested to ensure timely and adequate supply of construction materials for Long Thanh airport.