North-South expressway under construction through Lam Dong is reflected to cause cracks in people's houses

Xuyên Đông |

The Ministry of Construction has just responded to voters in Lam Dong about compensation when the North-South expressway construction caused cracks in the house of 1 household.

Voters in Tan Lap commune, Lam Dong province reflect many inadequate contents related to the North-South expressway.

According to voters, Mr. Huynh Cong Son's household in the area has houses cracked and damaged due to the impact of motor vehicles and construction activities during the construction of the North-South expressway, but so far the inspection and assessment of the extent of damage and remedial plans have not been thoroughly implemented.

Voters also reflected that the people's road from the beginning of the underpass under the expressway to the overpass in Tan Lap commune is currently the only way to serve the living, production and transportation needs of households, but it has seriously deteriorated, causing difficulties for travel and traffic unsafety.

Voters proposed that the Ministry of Construction direct the Project Management Board and related units to urgently coordinate with the People's Committee of Lam Dong province and the Tan Lap commune government to organize actual inspection of the current status of the above-mentioned people's road, and have solutions for repair and upgrade.

People also requested the Ministry of Construction to review and specifically assess the extent of damage to households affected by housing and property, and clarify the responsibilities of relevant organizations and individuals to have support, compensation, and remedial measures in accordance with legal regulations.

After studying, the Ministry of Construction responded as follows:

- Regarding the payment of compensation money to Mr. Huynh Cong Son's household whose house was cracked due to the impact during the construction of the expressway project:

According to the project investor's report, the insurance unit is currently organizing appraisal and will complete the compensation payment work in March 2026.

- Regarding the restoration of people's roads serving project construction:

According to the project investor's report, all local residential roads used as service roads to serve project construction have been rebuilt by the investor and handed over to the locality.

The residential road from the beginning of the underpass under the expressway to the overpass in Tan Lap commune, as proposed by voters, is not within the scope of roads used as service roads for project construction, so it is not the responsibility of the project for repair and remediation.

However, the Ministry of Construction will direct the investor to coordinate with local authorities to study solutions.

The Ministry of Construction requests the Delegation of National Assembly Deputies of Lam Dong province to give opinions to the People's Committee of Lam Dong province to direct localities and relevant units to closely coordinate with the investor to handle and comply with the provisions of law on investment to ensure serving the living and farming needs of the people.

Xuyên Đông
RELATED NEWS

Complete overpass connecting Tuyen Quang - Phu Tho expressway

|

Phu Tho - The route connecting the Noi Bai - Lao Cai expressway with the Tuyen Quang - Phu Tho expressway has completed the provincial road 315 overpass and many other important items.

Efforts to maintain the pace of expressway construction in the face of gasoline and oil price fluctuations

|

Lang Son - Fluctuations in gasoline supply are putting pressure on the Dong Dang - Tra Linh expressway construction site.

Passenger car deformed after container collision on the North-South expressway

|

Functional agencies have just initially announced the collision between a container truck and a passenger car on the North-South expressway through Thanh Hoa.

Cars parked rampant on Tang Bat Ho street causing traffic obstruction

|

Hanoi - Traffic police will strengthen patrols and handle the situation of cars stopping and parking in violation of regulations on Tang Bat Ho street.

16th National Assembly deputies candidates meet with voters in Bac Ninh

|

Candidates for National Assembly Deputies of the 16th term meet with voters at constituency No. 3, Bac Ninh province.

Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

|

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Holiday schedule for Hung Kings Commemoration Day 2026 and occasion April 30 - May 1

|

In 2026, the holiday schedule for the Hung Kings Commemoration Day and the occasion April 30 - May 1 for workers has been determined according to the provisions of the Labor Code.

Thanh Hoa Department of Education and Training concludes the case of teachers of To Hien Thanh High School correcting scores

|

Thanh Hoa - The Department of Education and Training (GDĐT) of the province has the results of inspection and verification of the case of amending semester exam scores that occurred at To Hien Thanh High School.

Complete overpass connecting Tuyen Quang - Phu Tho expressway

Tô Công |

Phu Tho - The route connecting the Noi Bai - Lao Cai expressway with the Tuyen Quang - Phu Tho expressway has completed the provincial road 315 overpass and many other important items.

Efforts to maintain the pace of expressway construction in the face of gasoline and oil price fluctuations

Khánh Linh |

Lang Son - Fluctuations in gasoline supply are putting pressure on the Dong Dang - Tra Linh expressway construction site.

Passenger car deformed after container collision on the North-South expressway

Minh Chuyên |

Functional agencies have just initially announced the collision between a container truck and a passenger car on the North-South expressway through Thanh Hoa.