Ca Mau - Cai Nuoc expressway is urgently under construction

NHẬT HỒ |

Ca Mau - Minister of Construction Tran Hong Minh noted that when handling weak soil foundations, closely monitor, focus on quality, and not ignore quality because of progress.

In the afternoon of January 9, a delegation from the Ministry of Construction led by Minister Tran Hong Minh inspected the construction of the Ca Mau - Cai Nuoc expressway section under the Ca Mau - Dat Mui expressway project.

Reporting to the working delegation, the Director of Project Management Unit 166 said that the project has two construction packages, the value of implementation to date has reached 0.41% compared to the contract value.

In Package XL01, 226 engineers and workers have been mobilized, gathering 75 motorbikes of all kinds. Currently, the contractor is constructing camps, auxiliary yards, cement concrete plants, girder casting tanks, deploying organic mining and paving of service roads at priority locations, the access level is about 11.5km.

At Package XL02, 30 workers and engineers were mobilized and 20 motorbikes of all kinds were gathered. At the same time, the headquarters of the Management Board on DT986 road was completed, and the construction of service roads and service roads was completed.

Bo truong Bo Xay dung Tran Hong Minh tang qua cho cong nhan lam viec tai cao toc Ca Mau - Cai Nuoc. Anh: Nhat Ho
Minister of Construction Tran Hong Minh presents gifts to workers working on the Ca Mau - Cai Nuoc expressway. Photo: Nhat Ho.

At the inspection, Minister of Construction Tran Hong Minh requested the contractor to maximize manpower and machinery, have specific construction plans, scientific and safe construction organization methods to ensure project completion progress, and promptly report specific difficulties and obstacles to remove and resolve.

The Minister requested the contractor to carefully calculate that all construction plans must be methodical, ensuring labor safety, environmental sanitation, traffic safety, and making the highest efforts to deploy construction according to the set goals and plans.

Minister Tran Hong Minh also noted that in handling weak soil foundations, it is necessary to closely supervise, pay attention to quality management of works, and not ignore quality because of progress.

Mr. Lam Van Bi, Standing Vice Chairman of Ca Mau Provincial People's Committee, said that the local government is committed to closely coordinating and creating the most favorable conditions for contractors to accelerate the project completion progress according to the plan.

On this occasion, Minister of Construction Tran Hong Minh presented gifts to encourage engineers and workers working on the construction site. The Minister wished that the team of engineers and workers would strive to overcome all difficulties and join forces for the development of the country.

Ca Mau - Cai Nuoc expressway has a total length of more than 25km; the starting point at Km0 coincides with the ending point of the Hau Giang - Ca Mau expressway project at the IC12 intersection (Southern Coastal Corridor Road, belonging to Ho Thi Ky commune, Ca Mau province); the ending point at Km 42+168 (belonging to Phu My commune, Ca Mau province).

NHẬT HỒ
RELATED NEWS

Ca Mau implements a project of more than 26,820 billion VND to respond to landslides

|

Ca Mau - Faced with the increasing erosion of coastlines and riverbanks, Ca Mau is implementing a large-scale project to protect and exploit effectively.

Ca Mau repositions the shrimp industry chain to increase export value

|

Ca Mau - As the "carp capital" of the country, Ca Mau repositions the shrimp industry chain to break through in shrimp exports.

Ganh Hao Border Guard Station, Ca Mau rescues crew member at sea

|

Ca Mau - On the morning of January 7, Ganh Hao Border Guard Station (Ca Mau Border Guard) said that the unit promptly supported bringing a seriously ill crew member to the emergency room.

Ca Mau mobilizes 30 reserve vehicles but is deserted on the first day of Tet holiday

|

Ca Mau - Preparing to serve New Year's travel, Ca Mau Bus Station mobilized 30 reserve buses but there was no passenger congestion.

Key project in Ca Mau constructed throughout Tet to reach the finish line early

|

Ca Mau - On the first day of the New Year holiday in 2026, the delegation of the Ca Mau Provincial Party Committee visited and encouraged workers at the construction site.

Ca Mau arranges a series of public non-business units

|

On the afternoon of December 31, Ca Mau province announced decisions on arranging public non-business units and personnel work.

Hau Giang - Ca Mau expressway delays operating time

|

Can Tho - My Thuan Project Management Board has issued a notice on adjusting the operating time of the Hau Giang - Ca Mau expressway.

Ca Mau meets generations of National Assembly Deputies

|

Ca Mau - Commemorating the 80th anniversary of the first General Election Day (January 6, 1946 - January 6, 2026), on the afternoon of December 30, Ca Mau province organized a meeting with generations of National Assembly Deputies.

Ca Mau: Results of personnel consolidation of the Provincial People's Committee for the new term

|

Ca Mau - Provincial People's Council elected Mr. Hoang Phuong Thao - Provincial Party Committee Member, Chief Inspector of the province - to hold the position of Member of the Provincial People's Committee, term 2021-2026.

Ca Mau implements a project of more than 26,820 billion VND to respond to landslides

NHẬT HỒ |

Ca Mau - Faced with the increasing erosion of coastlines and riverbanks, Ca Mau is implementing a large-scale project to protect and exploit effectively.

Ca Mau repositions the shrimp industry chain to increase export value

NHẬT HỒ |

Ca Mau - As the "carp capital" of the country, Ca Mau repositions the shrimp industry chain to break through in shrimp exports.

Ganh Hao Border Guard Station, Ca Mau rescues crew member at sea

NHẬT HỒ |

Ca Mau - On the morning of January 7, Ganh Hao Border Guard Station (Ca Mau Border Guard) said that the unit promptly supported bringing a seriously ill crew member to the emergency room.

Ca Mau mobilizes 30 reserve vehicles but is deserted on the first day of Tet holiday

NHẬT HỒ |

Ca Mau - Preparing to serve New Year's travel, Ca Mau Bus Station mobilized 30 reserve buses but there was no passenger congestion.

Key project in Ca Mau constructed throughout Tet to reach the finish line early

NHẬT HỒ |

Ca Mau - On the first day of the New Year holiday in 2026, the delegation of the Ca Mau Provincial Party Committee visited and encouraged workers at the construction site.

Ca Mau arranges a series of public non-business units

NHẬT HỒ |

On the afternoon of December 31, Ca Mau province announced decisions on arranging public non-business units and personnel work.

Hau Giang - Ca Mau expressway delays operating time

Tạ Quang |

Can Tho - My Thuan Project Management Board has issued a notice on adjusting the operating time of the Hau Giang - Ca Mau expressway.

Ca Mau meets generations of National Assembly Deputies

NHẬT HỒ |

Ca Mau - Commemorating the 80th anniversary of the first General Election Day (January 6, 1946 - January 6, 2026), on the afternoon of December 30, Ca Mau province organized a meeting with generations of National Assembly Deputies.

Ca Mau: Results of personnel consolidation of the Provincial People's Committee for the new term

NHẬT HỒ |

Ca Mau - Provincial People's Council elected Mr. Hoang Phuong Thao - Provincial Party Committee Member, Chief Inspector of the province - to hold the position of Member of the Provincial People's Committee, term 2021-2026.