The trillion-dong expressway in Bac Kan is at risk of being behind schedule due to land clearance problems

Nguyễn Hoàn |

Bac Kan - The Cho Moi - Bac Kan trillion-dong expressway project is facing the risk of missing progress due to land clearance problems.

It has been nearly 3 months since the groundbreaking date, the Cho Moi - Bac Kan expressway worth more than 5,700 billion VND has not been able to be constructed simultaneously due to land clearance problems.

The project is invested by Project Management Board 2 (Ministry of Transport), starting construction in mid-March 2025.

Phoi canh tuyen cao toc Cho Moi - Bac Kan. Anh: Anh Minh
Perspective of the billion-dong expressway connecting Cho Moi - Bac Kan. Photo: Anh Minh

The route is nearly 29km long, with a scale of 4 lanes, a design speed of 80km/h, a roadbed width of 22m, with 16 bridges and 2 overpasses.

The starting point connects with the Thai Nguyen - Cho Moi route (in Cho Moi district), the end point connects with the Bac Kan - Cao Bang route (in Bac Kan city).

According to the investigation of Lao Dong Newspaper, the project directly affects 1,210 households, organizations and individuals, of which 175 households must be relocated.

However, the site clearance progress is facing many difficulties, causing contractors to not be able to carry out construction simultaneously.

Nguoi dan va chinh quyen thuc hien kiem ke tai san. Anh: Cong Luan
People and authorities conduct property inventories. Photo: Cong Luan.

According to the investor's representative, as of early June 2025, Bac Kan province has only handed over 27.2/255.14 hectares, reaching 10.6% of the volume; equivalent to 2.13/28.4km of the entire route. The new contractor has deployed 2 construction teams of the service road at Km26 and Km28.

Mr. Mac Van Nghiep - Project Executive Director (Project Management Board 2) said that the site clearance work is still slow compared to the plan due to problems in applying the new Land Law.

It was not until December 2024 that the Provincial People's Committee issued specific instructions, causing the determination and approval of land prices in localities to be prolonged.

In addition, some households buy and sell land by handwritten documents, without legal documents, causing difficulties in inventorying and verifying the origin.

In addition, there are still many poor and near-poor households building houses on agricultural land. Meanwhile, the resettlement area has not been built, affecting the relocation progress.

Du an cao toc Cho Moi - Bac Kan dang gap vuong mac trong cong tac ban giao mat bang. Anh: Viet Hung.
The Cho Moi - Bac Kan Expressway project is facing difficulties in site handover. Photo: Viet Hung.

In Cho Moi district, compensation has been paid in 3 installments, but only 50% of households have received the money.

Many cases have not agreed due to the related compensation price as well as the lack of clear support mechanism for assets outside the residential land area such as trees and structures.

As a construction unit of more than 20km of the expressway, Phuong Thanh Traffic Investment and Construction Joint Stock Company (Phuong Thanh Company) has only reached about 800m of the site.

According to Mr. Tran Ba Luan - Executive Director of Phuong Thanh Company, the unit has advanced a part of the cost to support expenses related to temporary relocation and land lease.

At the same time, coordinate with the government to encourage people to hand over the site soon, creating conditions for construction on schedule.

Regarding the project implementation, Mr. Dinh Quang Tuyen - Permanent Vice Chairman of the People's Committee of Bac Kan province said that the project is one of the major projects of the province.

Therefore, the locality is urgently and drastically implementing the work of supporting and compensating for site clearance for households in the affected area.

Ban dieu hanh du an va nha thau khao sat thuc dia tuyen cao toc Cho Moi - Bac Kan. Anh: Viet Hung.
The project management board and the contractor conducted a field survey of the Cho Moi - Bac Kan expressway. Photo: Viet Hung.

One of the major problems at present is the construction of resettlement areas. According to the survey, up to 80-90% of households want to take care of their new places of residence instead of going to resettlement areas.

The locality has supported an amount of no more than 200 million VND/household, but many households have not agreed because the cost of building new housing is higher.

Faced with that reality, the province is considering increasing the level of support for households that are self-resettled, and at the same time adding a policy to support assets on agricultural land that have been recovered, relocated cemeteries, temporary housing rental and other arising costs.

"The province's goal is to hand over enough land in June so that the contractor can organize construction simultaneously," Mr. Tuyen affirmed.

Nguyễn Hoàn
TIN LIÊN QUAN

Thousand-billion-dong expressway projects started construction last week

|

In the past week, many expressway projects with a total investment of thousands of billions were started.

3,750 personnel serve two billion-dong expressways in the border area

|

Lang Son - Two key expressway projects are entering the construction acceleration phase, with the goal of opening the route in 2025.

Overcoming the heat, workers cling to the trillion-dong highway

|

Western Region - Despite the harsh sunshine, engineers and workers are still working hard at the Chau Doc - Can Tho - Soc Trang expressway construction site.

Live Vietnam vs Australia women's volleyball at AVC Nations Cup 2025

|

Live volleyball between Vietnam and Australia at AVC Nations Cup 2025, taking place at 20:00 on June 12.

The case of 900 teachers in Lao Cai who failed to receive awards, the district said "due to awareness"

|

Lao Cai - More than 900 teachers in Bac Ha district are not considered for year-end rewards for not paying compulsory charity funds.

The Ministry of Public Security proposes to resolve the case of 705,000 people who have not been tested for driving licenses

|

The Ministry of Public Security spoke out about removing difficulties and bottlenecks, urgently resolving them in the testing work to issue driving licenses.

Germany plans to provide more weapons to Ukraine despite security risks

|

German Defense Minister Boris Pistorius visited Ukraine on June 12 to discuss the next military aid packages that Berlin will provide to Kiev.

Many cadres in Hanoi are paid more than 2 billion VND when retiring early

|

Hanoi - Among the cases that have just received the regime from the city, many officials have received more than 2 billion VND when retiring early.

Thousand-billion-dong expressway projects started construction last week

Xuyên Đông |

In the past week, many expressway projects with a total investment of thousands of billions were started.

3,750 personnel serve two billion-dong expressways in the border area

Khánh Linh |

Lang Son - Two key expressway projects are entering the construction acceleration phase, with the goal of opening the route in 2025.

Overcoming the heat, workers cling to the trillion-dong highway

PHƯƠNG ANH |

Western Region - Despite the harsh sunshine, engineers and workers are still working hard at the Chau Doc - Can Tho - Soc Trang expressway construction site.