Vinh Hao - Phan Thiet Expressway still has 1 rest stop that has not been handed over the site

DUY TUẤN |

The Vinh Hao - Phan Thiet Expressway through Lam Dong province has been approved for 2 rest stops at Km 144+560 (Tuy Phong commune) and at Km205+092 (Ham Thuan Bac commune). Currently, the rest stop at Km205 has gradually taken shape with many main items. However, the rest stop at km144 has not yet been handed over the site.

On November 18, Mr. Pham Quoc Huy - Deputy Head of Project Management Board 7 (Ministry of Construction) - said that the rest stop at Km144 had just been handed over 1.67/10.86ha, reaching 15.39%. The remaining 9 hectares have not been handed over for construction, leading to delays in the progress of this rest stop.

Mr. Huy also said that the reason for not handing over the site for construction is because this land area is being disputed and complaints are occurring. Currently, Lam Dong Provincial People's Committee is urgently removing obstacles to have a site handed over to the construction investor. On the other hand, the litigation agencies are also supporting the settlement of disputes and complaints to promptly hand over the project site.

As for the rest stop at Km205, Mr. Huy said that the basic progress meets the requirements according to the contract, and it is expected to be completed and put this rest stop into operation in early January 2026. This rest stop will serve people traveling on the highway during the Lunar New Year.

Previously, on June 27, 2024, the Vietnam Expressway Administration (under the old Ministry of Transport, now the Ministry of Construction) approved the results of selecting investors to build and operate 2 rest stops on the Vinh Hao - Phan Thiet Expressway. The winning investor contract will implement this project for 15 months. Investors are required to complete at least essential public service works including parking lots, toilets, and operating houses before December 31, 2025.

The expressway section through Lam Dong Vinh Hao - Phan Thiet province is over 100km long and has been open to traffic since May 2023. By June 2024, the service road, overpass and intersection items will be completed.

Currently, 2 locations on this expressway are flooded during heavy rain. The Management Board of the Vinh Hao - Phan Thiet Expressway Project is implementing solutions to completely overcome the flooding situation. The bidding packages for the construction of the intelligent traffic monitoring system (TS) and vehicle weight control on this expressway are also being rushed to complete to collect tolls in early 2026.

DUY TUẤN
RELATED NEWS

Revealing the long figure of many items at the rest stop on the Vinh Hao - Phan Thiet Expressway

|

Lam Dong - The rest stop at Km205 on the Vinh Hao - Phan Thiet expressway has gradually taken shape with the main items starting to appear.

Vinh Hao - Phan Thiet Expressway is about to have a smart load monitoring and weighing system

|

Lam Dong - The smart traffic monitoring system and load weighing on the Vinh Hao - Phan Thiet expressway are being completed, expected to be put into operation to collect tolls from the beginning of 2026.

The surface of the Vinh Hao - Phan Thiet expressway is flooded again

|

Lam Dong - Vinh Hao - Phan Thiet Expressway was flooded again in 2 sections due to heavy rain, causing temporary road closures at Ma Lam intersection.

New survey results on President Trump's support rate

|

President Donald Trump's support rate is affected by the handling of the investigation into the proxy billionaire Jeffrey Epstein.

The current status of the project has lasted for nearly 2 decades, affecting nearly 1,000 investors in Quang Ninh

|

Quang Ninh - Many people have invested in the project but have not received red books for nearly 2 decades, despite many meetings and directives.

River water rises rapidly, many areas in Dak Lak are at risk of flash floods

|

Dak Lak - The water level of major rivers in the province continues to rise, possibly above alert level 3, with the risk of causing flash floods and landslides on a large scale.

Preschool teacher in mountainous Nghe An, struggling to double

|

Nghe An - In the mountainous area of Nhon Mai, teachers of Mai Son Kindergarten still attend classes, encouraging each student to return to school.

Ukraine restarts diplomatic process to end conflict

|

Ukraine has emphasized diplomatic efforts in the context of needing more international support.

Revealing the long figure of many items at the rest stop on the Vinh Hao - Phan Thiet Expressway

Duy Tuấn |

Lam Dong - The rest stop at Km205 on the Vinh Hao - Phan Thiet expressway has gradually taken shape with the main items starting to appear.

Vinh Hao - Phan Thiet Expressway is about to have a smart load monitoring and weighing system

Duy Tuấn |

Lam Dong - The smart traffic monitoring system and load weighing on the Vinh Hao - Phan Thiet expressway are being completed, expected to be put into operation to collect tolls from the beginning of 2026.

The surface of the Vinh Hao - Phan Thiet expressway is flooded again

Duy Tuấn |

Lam Dong - Vinh Hao - Phan Thiet Expressway was flooded again in 2 sections due to heavy rain, causing temporary road closures at Ma Lam intersection.