The 3rd bridge across Cua Luc Bay is expected to have 2 levels

Nguyễn Hùng |

Quang Ninh - Quang Ninh City is preparing procedures to build Cua Luc 2 bridge - the 3rd bridge across Cua Luc Bay, belonging to the old Ha Long City.

On September 22, Quang Ninh City People's Committee held a meeting to listen to and give opinions on the pre-feasibility study report of the Cua Luc 2 bridge project.

According to the pre-feasibility study report, the project has a total length of 5.2km. The main bridge section is 1.28km long, the rest is the approach bridge and approach roads on both sides connecting to National Highway 18 and National Highway 279.

The project is designed with 10 car lanes, of which connecting to National Highway 18 is a multi-layered grade-separated intersection. The main bridge part is designed with 2 floors, of which the 1st floor is functional infrastructure serving commerce, tourism, and services.

The consulting unit has proposed a number of bridge architectural design options; solutions that allow to promote the ability to master domestic design, technology and construction.

Giving opinions on the pre-feasibility study report of this bridge project, Mr. Bui Van Khang - Deputy Secretary of the City Party Committee, Chairman of Quang Ninh City People's Committee - requested that this bridge must be one of the symbolic works identifying Quang Ninh city.

The bridge is not only a simple connecting traffic project, but also a unique architectural work, fully functional to serve commercial, tourism, service and festival organization development. Thereby, it is truly a driving force to promote the development space of Cua Luc Bay - the urban connection center of the city.

Mr. Khang requested the Construction Investment Project Management Board of Region I and departments and branches to complete the pre-feasibility study report of the project, prepare reports to submit to competent authorities, and at the same time review investment preparation procedures, and be ready to start the project in accordance with regulations.

Cầu Tình Yêu - cây cầu đầu tiên bắc qua vịnh Cửa Lục. Ảnh: Nguyễn Hùng
Love Bridge - the first bridge spanning Cua Luc Bay. Photo: Nguyen Hung

Previously, Quang Ninh had put into operation 2 bridges across Cua Luc Bay, including Tinh Yeu bridge and Binh Minh bridge.

To contribute to enhancing the value of the Cua Luc Bay area, creating motivation for investors to enter the area and concretizing the plans approved by the Prime Minister, Quang Ninh has started construction of a number of traffic works around Cua Luc Bay, including the coastal road project extending from Tran Quoc Nghien street (near pier P4 of Bai Chay bridge) through Binh Minh bridge to Bang bridge, with an investment of 2,618 billion VND.

Cua Luc Bay, 18km2 wide, the deepest point 17m, located right next to Ha Long Bay, is planned as a connecting center, multi-polar, smart, green growth city, international standards of Quang Ninh province.

According to the new administrative boundary map after the merger, the Cua Luc Bay area currently has a part of the area belonging to the wards: Bai Chay, Cao Xanh, Viet Hung, Hoanh Bo and Thong Nhat commune today.

Nguyễn Hùng
RELATED NEWS

Industrial facilities along Cua Luc Bay in the area of relocation

|

Quang Ninh - Quang Ninh advocates relocating and converting the function of industrial facilities around Cua Luc Bay when the role of this bay is different from before.

Researching the relocation of Ha Long Shipyard out of Cua Luc Bay

|

Quang Ninh - Among the industrial facilities included in the policy to relocate out of the Cua Luc Bay area of Quang Ninh province is Ha Long Shipyard.

Quang Ninh plans to build a third bridge across Cua Luc Bay in 2026

|

Quang Ninh - Cua Luc 2 Bridge is expected to start construction in 2026, aiming to complete the interconnection around Cua Luc Bay.

Details of the northwest coastal road of Cua Luc Bay, 2,860 billion VND

|

Quang Ninh - The Cua Luc Bay Northwest Coastal Road Project contributes to opening up a huge development space, from the Ha Long - Van Don Expressway to Cua Luc Bay.

Man in Da Nang killed by train while crossing railway

|

Da Nang - An accident occurred at a self-opened passageway across the railway, belonging to the Tam Thanh - Tam Ky section, on the afternoon of September 22.

Forecast of 5 provinces and cities with the heaviest rain from tonight to September 24, with some places over 250mm/24h

|

The focus of heavy rain from now until September 24th is the area from Hue to Da Nang and the east of Quang Ngai, Gia Lai, Dak Lak provinces, locally over 250mm/24h.

Hanoi Police inform about the case of a garbage truck colliding with a bus, one person broke his leg

|

Hanoi - A collision between a garbage truck and a bus caused a driver to break his leg.

Lam Dong announces emergency situation for natural disaster at Prenn Pass

|

Lam Dong - Prolonged heavy rain causes landslides and rocks at many locations on Prenn Pass, threatening traffic safety.

Industrial facilities along Cua Luc Bay in the area of relocation

Nguyễn Hùng |

Quang Ninh - Quang Ninh advocates relocating and converting the function of industrial facilities around Cua Luc Bay when the role of this bay is different from before.

Researching the relocation of Ha Long Shipyard out of Cua Luc Bay

Nguyễn Hùng |

Quang Ninh - Among the industrial facilities included in the policy to relocate out of the Cua Luc Bay area of Quang Ninh province is Ha Long Shipyard.

Quang Ninh plans to build a third bridge across Cua Luc Bay in 2026

Nguyễn Hùng |

Quang Ninh - Cua Luc 2 Bridge is expected to start construction in 2026, aiming to complete the interconnection around Cua Luc Bay.

Details of the northwest coastal road of Cua Luc Bay, 2,860 billion VND

Nguyễn Hùng |

Quang Ninh - The Cua Luc Bay Northwest Coastal Road Project contributes to opening up a huge development space, from the Ha Long - Van Don Expressway to Cua Luc Bay.