finalizing the roadmap for building Tran Hung Dao, Ngoc Hoi, Tu Lien bridges

KHÁNH AN |

It is expected that in the period from 2025 to 2030, Hanoi will complete the construction of 3 bridges across the Red River including Tran Hung Dao, Ngoc Hoi and Tu Lien.

On February 25, at the 21st session, the Hanoi People's Council passed a Resolution approving investment policies and adjusting investment policies for a number of public investment projects in the city, including the Tran Hung Dao, Ngoc Hoi and Tu Lien bridge construction projects.

Tran Hung Dao Bridge

Phoi canh cau Tran Hung Dao. Anh: Don vi thiet ke
Perspective of Tran Hung Dao Bridge. Photo: Design Unit

Tran Hung Dao Bridge has a total length of about 5.6km. The starting point is at the Tran Hung Dao - Tran Thanh Tong intersection in Hoan Kiem district. The end point connects with Vu Duc Than street, Long Bien district.

The approach roads at both ends of the investment bridge have a cross-section of 30m, a total length of about 2.25km (about 0.25km in the city center, about 2.0km in Long Bien).

Regarding the main bridge over the Red River, build an eternal bridge according to current bridge design standards.

At the same time, a direct underpass will be built at the intersection with Nguyen Van Linh Street/Hai Phong Railway with a scale of 4 lanes, about 19.5m wide, a total length of about 650m with a closed tunnel length of about 150m.

Complete investment in construction at 4 intersections: Different level intersection with Tran Khanh Du and Nguyen Khoi streets; intersection with Ta Hong dyke road (Long Bien - Xuan Quan road) and Co Linh road; equal intersection with Nguyen Son road; different level intersection with Nguyen Van Linh road/Hanoi - Hai Phong railway.

The project is divided into 2 component project groups. In which, the site clearance project group includes 3 site clearance projects in Hoan Kiem and Hai Ba Trung Long Bien districts. The construction investment project group has 1 investment project to build Tran Hung Dao bridge.

The total investment of the project is more than 15,967 billion VND. The project implementation period is in the period of 2025-2027.

Ngoc Hoi Bridge

Vi tri xay dung cau Ngoc Hoi noi huyen Thanh Tri (Ha Noi) voi huyen Van Giang (Hung Yen). Anh: Tuan Anh
The construction location of Ngoc Hoi bridge connects Thanh Tri district (Hanoi) with Van Giang district (Hung Yen). Photo: Tuan Anh

The total length of Ngoc Hoi Bridge and the approach roads at both ends of the bridge is about 7.5km. Of which, the main bridge and approach bridge are 7.2km long and 33m wide. The road at the beginning of the bridge on the Hung Yen side is about 300m long and 60m wide.

The starting point of the investment project is in Thanh Tri district, Hanoi (connecting with the end point of the Ring Road 3.5 project from Phuc La, Van Phu to Phap Van - Cau Gie expressway, about 360m from Phap Van - Cau Gie expressway towards Huu Hong dike).

The end point is in Van Giang district, Hung Yen province (Km7+500) connecting with Ring Road 3.5 in Van Giang district, Hung Yen province, 700m from the Ta Hong dike towards the Hanoi - Hai Phong expressway.

The total investment of the project is 11,844 billion VND. The implementation period is in the period of 2025-2030.

Tu Lien Bridge

Phoi canh cau Tu Lien. Anh: Don vi thiet ke
Perspective of Tu Lien Bridge. Photo: Design Unit

Invest in the construction of Tu Lien Bridge and the road at both ends of the bridge from the intersection with Nghi Tam Street to the intersection with Truong Sa Street with a total length of about 5.15km. The starting point connects with Nghi Tam Street, Tay Ho District, the end point passes through the intersection with Truong Sa Street.

The approach road to Tay Ho bridge (overpass and parallel road) is planned to be 48m wide. The East Anh approach road is planned to be 60m wide.

Tu Lien main bridge across the Red River is 1km long, 43m wide (including the cable-stayed arrangement). The Duong River overpass is about 0.3km long and 44m wide. The current Duong left dike overpass is about 0.08km long and 35m wide. The approach bridge to the West of Ho and Long Bien is about 1.4km long with a width ranging from 27.5m - 44m. The Dong Anh approach bridge (exceeding the planned TC13 axis) is about 0.4km long and 35m wide.

At the same time, an underpass will be built with 4 lanes for motor vehicles and 2 lanes for non-motor vehicles with a width of 24.5m on Tu Lien Street, with a total tunnel length of about 1.265km.

The project is divided into 4 component projects. Including 3 site clearance projects (in Tay Ho, Dong Anh, Long Bien districts) and 1 construction investment project.

The total preliminary investment of the project is VND 20,171 billion. The project will be implemented in the period of 2025 - 2027.

KHÁNH AN
TIN LIÊN QUAN

Hanoi builds 3 underpasses for Tu Lien bridge project

|

Hanoi - The implementation of the Tu Lien bridge project will build 3 underpasses (including 2 closed tunnels about 0.16km and 0.1km long; 1 open tunnel about 1.05km long).

Location of the underpass under the Tran Hung Dao bridge project

|

Hanoi - On the Tran Hung Dao bridge project route and the approach road to the bridge, there will be a direct underpass about 19.5m wide; the total length is about 650m.

Roadmap for the construction of Ngoc Hoi bridge connecting Hanoi with Hung Yen

|

The Ngoc Hoi bridge construction project connecting Hanoi with Hung Yen is divided into 2 component project groups, with implementation period from 2025-2030.

2025 storm forecast from the unit accurately forecasting super typhoons 2024

|

The latest storm forecast for the 2025 hurricane season has been released by WeatherBell Analytics. This is the unit that has issued an accurate forecast of the 2024 severe storm season with many super typhoons.

Announcing the Inspection Decision to the Central Public Security Party Committee

|

On the morning of February 25, Inspection Team No. 1917 of the Politburo and the Secretariat held a conference to announce the inspection decision for 2025 for the Central Public Security Party Committee.

Doctors' Journey to Revive Patients

|

Severe cases and work pressure have never eased the enthusiasm of doctors at Da Nang Hospital.

The 5 city trade unions need to focus on developing union members

|

Can Tho - Mr. Nguyen Dinh Khang - Member of the Party Central Committee, President of the Vietnam General Confederation of Labor suggested that the 5-city Labor Confederations need to focus on developing union members in 2025.

The State Bank has a new Deputy Governor

|

Mr. Nguyen Ngoc Canh - Vice Chairman of the State Capital Management Committee at Enterprises - was appointed Deputy Governor of the State Bank from March 1, 2025.

Hanoi builds 3 underpasses for Tu Lien bridge project

KHÁNH AN |

Hanoi - The implementation of the Tu Lien bridge project will build 3 underpasses (including 2 closed tunnels about 0.16km and 0.1km long; 1 open tunnel about 1.05km long).

Location of the underpass under the Tran Hung Dao bridge project

KHÁNH AN |

Hanoi - On the Tran Hung Dao bridge project route and the approach road to the bridge, there will be a direct underpass about 19.5m wide; the total length is about 650m.

Roadmap for the construction of Ngoc Hoi bridge connecting Hanoi with Hung Yen

KHÁNH AN |

The Ngoc Hoi bridge construction project connecting Hanoi with Hung Yen is divided into 2 component project groups, with implementation period from 2025-2030.