On September 26, the Dak Lak Province Traffic Construction and Rural Development Project Management Board informed that the unit has developed a detailed progress plan for the 3-phase project of the Khanh Hoa - Buon Ma Thuot Expressway Project.
Accordingly, the investor and contractors synchronously deploy measures to speed up construction progress, striving to complete Component Project 3 before September 2, 2025.
Specifically, strive to basically complete the main roadbed before December 31, 2024 and complete the entire road before February 28, 2025; strive to basically complete the crushed stone foundation before April 30, 2025.
Units will start constructing the road surface from November 2024 and strive to complete the road surface in July 2025; basically complete the cross-drainage system and residential underpass before October 30, 2024 and complete the entire system before December 31, 2024.
A representative of Son Hai Group shared: "The unit is currently one of three contractors constructing component project 3 of the Khanh Hoa - Buon Ma Thuot expressway with package number 1 (belonging to Km69+500-Km86).
Although the weather is in the rainy season, it basically does not affect the project construction process. The contractor is confident that by November 2024, the road surface construction will begin and strive to complete the road surface in July 2025."
As Lao Dong reported, the Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1 is divided into 3 component projects.
Of which, Component Project 1 is managed by Khanh Hoa Provincial People's Committee, with a length of 31.5km; Component Project 2 is managed by the Ministry of Transport, with a length of nearly 37km, and Component Project 3 is managed by Dak Lak Provincial People's Committee, with a length of more than 48km.