Preparing for construction of the highway connecting the forest with the sea

BẢO TRUNG |

Dak Lak - Investors and contractors are urgently speeding up the construction progress of the Khanh Hoa - Buon Ma Thuot expressway project to complete it by the end of 2025.

On September 26, the Dak Lak Province Traffic Construction and Rural Development Project Management Board informed that the unit has developed a detailed progress plan for the 3-phase project of the Khanh Hoa - Buon Ma Thuot Expressway Project.

Accordingly, the investor and contractors synchronously deploy measures to speed up construction progress, striving to complete Component Project 3 before September 2, 2025.

Specifically, strive to basically complete the main roadbed before December 31, 2024 and complete the entire road before February 28, 2025; strive to basically complete the crushed stone foundation before April 30, 2025.

Units will start constructing the road surface from November 2024 and strive to complete the road surface in July 2025; basically complete the cross-drainage system and residential underpass before October 30, 2024 and complete the entire system before December 31, 2024.

A representative of Son Hai Group shared: "The unit is currently one of three contractors constructing component project 3 of the Khanh Hoa - Buon Ma Thuot expressway with package number 1 (belonging to Km69+500-Km86).

Although the weather is in the rainy season, it basically does not affect the project construction process. The contractor is confident that by November 2024, the road surface construction will begin and strive to complete the road surface in July 2025."

As Lao Dong reported, the Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1 is divided into 3 component projects.

Of which, Component Project 1 is managed by Khanh Hoa Provincial People's Committee, with a length of 31.5km; Component Project 2 is managed by the Ministry of Transport, with a length of nearly 37km, and Component Project 3 is managed by Dak Lak Provincial People's Committee, with a length of more than 48km.

BẢO TRUNG
RELATED NEWS

Reason why the largest waste treatment plant in Thanh Hoa has not yet received waste again

|

Thanh Hoa - According to assessments, the treatment of accumulated waste at the largest waste treatment plant in Thanh Hoa is somewhat slow, because after nearly 1 month, the plant still cannot receive more.

When ordinary Vietnamese people become "tourism ambassadors

|

It's not always that million-dollar advertising campaigns or elaborately staged travel videos remind tourists of a country.

Trump issues 48-hour ultimatum to Iran over the Strait of Hormuz

|

Mr. Trump threatened Iran that he would attack the country's power plant if it did not end the blockade of the Strait of Hormuz.

Trade union news: Dong Nai will provide job counseling for 33,000 people in the second quarter

|

Trade union news on March 22: Dong Nai will provide job counseling for 33,000 people in the second quarter; Expected base salary increase for the army and police from July 1...

Nghe An traffic police take critically ill people to the emergency room in time

|

Nghe An - Traffic police quickly used specialized vehicles to take the seriously injured woman to a medical facility, helping the victim overcome the critical condition.

Many cars have broken windows while running on the expressway through Quang Tri

|

Quang Tri - Many cars moving on the highway are suspected of being hit by rocks and breaking windows, functional forces are investigating and clarifying the cause.

Chelsea loses 4 consecutive matches

|

In the early morning of March 22 (Vietnam time), the 0-3 defeat to Everton in the Premier League marked Chelsea's fourth consecutive defeat in all competitions.

Appointment and transfer of personnel in Hai Phong, Tay Ninh, Thanh Hoa, Ha Tinh

|

From March 16-21, decisions on appointment and transfer of personnel were implemented in many localities such as Hai Phong, Tay Ninh, Thanh Hoa, Dien Bien, Ha Tinh.

3 trillion-dollar intersections connecting Ho Chi Minh City and Ben Luc - Long Thanh expressway

MINH QUÂN |

Ho Chi Minh City will invest thousands of billions of VND to build three intersections connecting to the Ben Luc - Long Thanh expressway, including the intersections of Rung Sac Road, National Highway 50 and Nguyen Van Tao Road.

Dong Nai sets date for handing over Bien Hoa - Vung Tau expressway site

HÀ ANH CHIẾN |

On September 25, information from the People's Committee of Dong Nai province said that by October 15, the province will basically hand over the land for the Bien Hoa - Vung Tau expressway.

300 billion VND intersection connecting Noi Bai - Lao Cai expressway

Trần Bùi |

Yen Bai - After 1.5 years of construction, the IC 13 intersection project of Noi Bai - Lao Cai expressway has gradually been completed, ready for completion in the first quarter of 2025.

Ready to start construction of 10,000 billion VND highway connecting Hoa Binh - Moc Chau

An Khánh - Minh Chuyên |

Hoa Binh province has prepared all conditions to be ready for the groundbreaking ceremony of the Hoa Binh - Moc Chau expressway project this September.