Preparing for construction of the highway connecting the forest with the sea

BẢO TRUNG |

Dak Lak - Investors and contractors are urgently speeding up the construction progress of the Khanh Hoa - Buon Ma Thuot expressway project to complete it by the end of 2025.

On September 26, the Dak Lak Province Traffic Construction and Rural Development Project Management Board informed that the unit has developed a detailed progress plan for the 3-phase project of the Khanh Hoa - Buon Ma Thuot Expressway Project.

Accordingly, the investor and contractors synchronously deploy measures to speed up construction progress, striving to complete Component Project 3 before September 2, 2025.

Specifically, strive to basically complete the main roadbed before December 31, 2024 and complete the entire road before February 28, 2025; strive to basically complete the crushed stone foundation before April 30, 2025.

Units will start constructing the road surface from November 2024 and strive to complete the road surface in July 2025; basically complete the cross-drainage system and residential underpass before October 30, 2024 and complete the entire system before December 31, 2024.

A representative of Son Hai Group shared: "The unit is currently one of three contractors constructing component project 3 of the Khanh Hoa - Buon Ma Thuot expressway with package number 1 (belonging to Km69+500-Km86).

Although the weather is in the rainy season, it basically does not affect the project construction process. The contractor is confident that by November 2024, the road surface construction will begin and strive to complete the road surface in July 2025."

As Lao Dong reported, the Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1 is divided into 3 component projects.

Of which, Component Project 1 is managed by Khanh Hoa Provincial People's Committee, with a length of 31.5km; Component Project 2 is managed by the Ministry of Transport, with a length of nearly 37km, and Component Project 3 is managed by Dak Lak Provincial People's Committee, with a length of more than 48km.

BẢO TRUNG
RELATED NEWS

Trump requests postponement of attack on Iranian energy facility

|

Mr. Trump has suspended plans to bomb energy facilities, while tensions with Iran have not shown significant signs of cooling down.

Wastewater overflows alleys in Ho Chi Minh City, people live in prolonged pollution

|

Ho Chi Minh City - People reflect that dirty wastewater overflows into a small alley in An Phu Dong ward, emitting a strong odor, causing pollution that has not been treated for many months.

Deadline for the Ministry of Home Affairs to report on salary reform plans

|

The Ministry of Home Affairs prepares carefully, proposes specific plans for implementing salary reform according to the roadmap, and reports to the Deputy Prime Minister on March 30.

Live volleyball VTV Binh Dien Long An vs Vietinbank at Hoa Lu Cup final

|

Live match between VTV Binh Dien Long An and Vietinbank in the final of the Hoa Lu Cup 2026 volleyball tournament, taking place at 4:00 PM today (March 23).

Tao Quan 2026 special edition is about to air, without People's Artist Xuan Bac and Cong Ly

|

Tao Quan 2026 is about to return, bringing together a cast of familiar artists such as People's Artist Quoc Khanh, People's Artist Tu Long, Meritorious Artist Chi Trung, Meritorious Artist Quang Thang, and artist Van Dung.

Deputy Director of Quang Ninh Provincial Police becomes Deputy Head of the Provincial Party Committee's Internal Affairs Commission

|

Quang Ninh - On the morning of March 23, the Standing Committee of the Quang Ninh Provincial Party Committee held a conference to announce decisions on personnel work of the Provincial Party Committee's Internal Affairs Committee.

3 trillion-dollar intersections connecting Ho Chi Minh City and Ben Luc - Long Thanh expressway

MINH QUÂN |

Ho Chi Minh City will invest thousands of billions of VND to build three intersections connecting to the Ben Luc - Long Thanh expressway, including the intersections of Rung Sac Road, National Highway 50 and Nguyen Van Tao Road.

Dong Nai sets date for handing over Bien Hoa - Vung Tau expressway site

HÀ ANH CHIẾN |

On September 25, information from the People's Committee of Dong Nai province said that by October 15, the province will basically hand over the land for the Bien Hoa - Vung Tau expressway.

300 billion VND intersection connecting Noi Bai - Lao Cai expressway

Trần Bùi |

Yen Bai - After 1.5 years of construction, the IC 13 intersection project of Noi Bai - Lao Cai expressway has gradually been completed, ready for completion in the first quarter of 2025.

Ready to start construction of 10,000 billion VND highway connecting Hoa Binh - Moc Chau

An Khánh - Minh Chuyên |

Hoa Binh province has prepared all conditions to be ready for the groundbreaking ceremony of the Hoa Binh - Moc Chau expressway project this September.