Preparing for construction of the highway connecting the forest with the sea

BẢO TRUNG |

Dak Lak - Investors and contractors are urgently speeding up the construction progress of the Khanh Hoa - Buon Ma Thuot expressway project to complete it by the end of 2025.

On September 26, the Dak Lak Province Traffic Construction and Rural Development Project Management Board informed that the unit has developed a detailed progress plan for the 3-phase project of the Khanh Hoa - Buon Ma Thuot Expressway Project.

Accordingly, the investor and contractors synchronously deploy measures to speed up construction progress, striving to complete Component Project 3 before September 2, 2025.

Specifically, strive to basically complete the main roadbed before December 31, 2024 and complete the entire road before February 28, 2025; strive to basically complete the crushed stone foundation before April 30, 2025.

Units will start constructing the road surface from November 2024 and strive to complete the road surface in July 2025; basically complete the cross-drainage system and residential underpass before October 30, 2024 and complete the entire system before December 31, 2024.

A representative of Son Hai Group shared: "The unit is currently one of three contractors constructing component project 3 of the Khanh Hoa - Buon Ma Thuot expressway with package number 1 (belonging to Km69+500-Km86).

Although the weather is in the rainy season, it basically does not affect the project construction process. The contractor is confident that by November 2024, the road surface construction will begin and strive to complete the road surface in July 2025."

As Lao Dong reported, the Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1 is divided into 3 component projects.

Of which, Component Project 1 is managed by Khanh Hoa Provincial People's Committee, with a length of 31.5km; Component Project 2 is managed by the Ministry of Transport, with a length of nearly 37km, and Component Project 3 is managed by Dak Lak Provincial People's Committee, with a length of more than 48km.

BẢO TRUNG
RELATED NEWS

Rights when participating in electronic labor contracts of workers

|

The Government has just issued Decree 337/2025/ND-CP (effective from January 1, 2026) Regulating electronic labor contracts.

Bar owner speaks out about employee threatening to beat tourists at Nha Trang beach

|

Khanh Hoa - The bar owner has just spoken out about the incident of an employee threatening to beat a foreign tourist in the Nha Trang beach park area.

Venezuelan interim President warned by Trump

|

Mr. Trump warned that the Venezuelan interim President would have to "pay a very high price, even higher than Mr. Maduro", if he did not do the right thing.

PSG narrows the gap at the top of Ligue 1

|

In the early morning of January 5 (Vietnam time), Paris Saint-Germain (PSG) won 2-1 against Paris FC in round 17 of Ligue 1.

Man City drops victory over Chelsea in injury time

|

In the early morning of January 5 (Vietnam time), Man City shared points unfortunately with a score of 1-1 against Chelsea in the 20th round of the Premier League.

Medical staff in Nghe An have not received COVID-19 epidemic prevention allowance

|

Nghe An - Doctors and medical staff of Nghi Loc General Hospital propose not to receive epidemic prevention allowances according to Decree 05.

3 trillion-dollar intersections connecting Ho Chi Minh City and Ben Luc - Long Thanh expressway

MINH QUÂN |

Ho Chi Minh City will invest thousands of billions of VND to build three intersections connecting to the Ben Luc - Long Thanh expressway, including the intersections of Rung Sac Road, National Highway 50 and Nguyen Van Tao Road.

Dong Nai sets date for handing over Bien Hoa - Vung Tau expressway site

HÀ ANH CHIẾN |

On September 25, information from the People's Committee of Dong Nai province said that by October 15, the province will basically hand over the land for the Bien Hoa - Vung Tau expressway.

300 billion VND intersection connecting Noi Bai - Lao Cai expressway

Trần Bùi |

Yen Bai - After 1.5 years of construction, the IC 13 intersection project of Noi Bai - Lao Cai expressway has gradually been completed, ready for completion in the first quarter of 2025.

Ready to start construction of 10,000 billion VND highway connecting Hoa Binh - Moc Chau

An Khánh - Minh Chuyên |

Hoa Binh province has prepared all conditions to be ready for the groundbreaking ceremony of the Hoa Binh - Moc Chau expressway project this September.