Preparing for construction of the highway connecting the forest with the sea

BẢO TRUNG |

Dak Lak - Investors and contractors are urgently speeding up the construction progress of the Khanh Hoa - Buon Ma Thuot expressway project to complete it by the end of 2025.

On September 26, the Dak Lak Province Traffic Construction and Rural Development Project Management Board informed that the unit has developed a detailed progress plan for the 3-phase project of the Khanh Hoa - Buon Ma Thuot Expressway Project.

Accordingly, the investor and contractors synchronously deploy measures to speed up construction progress, striving to complete Component Project 3 before September 2, 2025.

Specifically, strive to basically complete the main roadbed before December 31, 2024 and complete the entire road before February 28, 2025; strive to basically complete the crushed stone foundation before April 30, 2025.

Units will start constructing the road surface from November 2024 and strive to complete the road surface in July 2025; basically complete the cross-drainage system and residential underpass before October 30, 2024 and complete the entire system before December 31, 2024.

A representative of Son Hai Group shared: "The unit is currently one of three contractors constructing component project 3 of the Khanh Hoa - Buon Ma Thuot expressway with package number 1 (belonging to Km69+500-Km86).

Although the weather is in the rainy season, it basically does not affect the project construction process. The contractor is confident that by November 2024, the road surface construction will begin and strive to complete the road surface in July 2025."

As Lao Dong reported, the Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1 is divided into 3 component projects.

Of which, Component Project 1 is managed by Khanh Hoa Provincial People's Committee, with a length of 31.5km; Component Project 2 is managed by the Ministry of Transport, with a length of nearly 37km, and Component Project 3 is managed by Dak Lak Provincial People's Committee, with a length of more than 48km.

BẢO TRUNG
RELATED NEWS

Announcing decisions on personnel work in Ninh Binh, Lao Cai, Thai Nguyen

|

From March 2-6, localities in Ninh Binh, Lao Cai, Thai Nguyen... have announced and implemented decisions on personnel work.

Proposal for a credit mechanism with 6-7% interest rates to develop affordable housing

|

HoREA proposes many mechanisms on credit, land and buying and selling regulations to promote the development of affordable commercial housing.

Pollution "black spot" at Hue University planning area removed

|

HUE - The "black spot" of pollution that has existed for many years in the Hue University planning area has been eliminated thanks to the drastic involvement of functional agencies.

Wishes of union members and workers in Dak Lak before the election day

|

Dak Lak - Union members and workers in the area have expressed many thoughts and aspirations before the election day.

Russia announces control of 9 more Ukrainian settlements in the week

|

On March 6, the Russian Ministry of Defense said that the country's forces had controlled 9 new settlements in the week from February 28 to March 6.

Gasoline prices increase, taxi drivers worry about reduced income

|

High gasoline and oil prices have caused many technology taxi drivers to worry that their income will decrease.

Liverpool into FA Cup quarter-finals

|

In the early morning of March 7 (Vietnam time), Liverpool reached the FA Cup quarter-finals after a 3-1 victory over Wolves.

Chinese AI short film causes fever: Investing 10 million VND, reaching 500 million views after 3 days

|

The AI short film "Hoac khu benh" caused a fever with hundreds of millions of views despite its extremely low budget, sparking debate about the future of cinema.

3 trillion-dollar intersections connecting Ho Chi Minh City and Ben Luc - Long Thanh expressway

MINH QUÂN |

Ho Chi Minh City will invest thousands of billions of VND to build three intersections connecting to the Ben Luc - Long Thanh expressway, including the intersections of Rung Sac Road, National Highway 50 and Nguyen Van Tao Road.

Dong Nai sets date for handing over Bien Hoa - Vung Tau expressway site

HÀ ANH CHIẾN |

On September 25, information from the People's Committee of Dong Nai province said that by October 15, the province will basically hand over the land for the Bien Hoa - Vung Tau expressway.

300 billion VND intersection connecting Noi Bai - Lao Cai expressway

Trần Bùi |

Yen Bai - After 1.5 years of construction, the IC 13 intersection project of Noi Bai - Lao Cai expressway has gradually been completed, ready for completion in the first quarter of 2025.

Ready to start construction of 10,000 billion VND highway connecting Hoa Binh - Moc Chau

An Khánh - Minh Chuyên |

Hoa Binh province has prepared all conditions to be ready for the groundbreaking ceremony of the Hoa Binh - Moc Chau expressway project this September.