On December 17, Mr. Truong Cong Thai - Vice Chairman of Dak Lak Provincial People's Committee - said that the Provincial People's Committee has requested investors to coordinate with functional units to urgently complete related procedures to prepare for the groundbreaking, technical traffic opening and inauguration of 3 projects.
Accordingly, on December 19, Dak Lak province will start the Cu Lao Mai Nha high-end resort project (east of the province), invested by Xuan Thien Ninh Binh Company Limited, with a total investment of nearly 5,000 billion VND.
Along with that, the province will hold the inauguration ceremony of the Ho Chi Minh Road Project, the East bypass section of Buon Ma Thuot (with a total investment of more than VND1,800 billion) and open technical traffic for Component Project 3, part of the Khanh Hoa - Buon Ma Thuot Expressway Project (with a total investment of VND6,165 billion).
Dak Lak province has identified these as 3 practical key projects to celebrate the 14th National Congress of the Party.
Before this time, the Provincial People's Committee assigned the Provincial Management Board of Investment Projects for Construction of Traffic Works and Rural Development of the province (Board A - investor) to preside over and coordinate with localities to focus on resolving the problems.
This includes issues related to the area of land clearance expanded and arising, especially 33 plots of land in Ea Knuc commune, the intersection of Provincial Road 10.
Committee A urgently organizes a dialogue and mobilizes people to comply with the approved compensation plan. If necessary, continue to consolidate the dossier to apply construction protection measures according to regulations, ensuring the handover of the site in December 2025 at the request of the Prime Minister and the Ministry of Construction.
Along with that, the investor will coordinate with the electricity industry and related units to complete the relocation of 500kV power poles and the remaining technical infrastructure works.
The Provincial People's Committee also requested contractors to take advantage of favorable weather conditions, increase human resources, machinery, organize construction in "3 shifts, 4 teams" to compensate for the slow progress, ensure the completion of items, meet technical traffic conditions and inauguration according to the set plan.
However, the leader of the Dak Lak Provincial People's Committee emphasized that absolutely do not follow the schedule but take the requirements for construction quality and labor safety lightly.