The appearance of the inter-commune road costing nearly 10 billion VND/km in Thai Nguyen

Nguyễn Hoàn |

Thai Nguyen - The project to expand the inter-commune road from Tien Hoi to Hoang Nong in the mountainous district of Dai Tu with a total investment of nearly 10 billion VND per km is gradually being completed.

The project to expand the Tien Hoi - Hoang Nong route with a total length of 8.7 km is invested by the Dai Tu District Investment and Construction Management Board with a total cost of more than 78 billion VND. The project will be implemented in October 2023.

This is a grade VI mountainous road, after investment in expansion and upgrading to a grade IV mountainous road, with a roadbed width of 7.5 m, a road surface width of 5.5 m, and a design speed of 40 km/h. It is expected to be completed in 2024.

On October 8, according to the reporter, after 1 year of construction, the Tien Hoi - Hoang Nong road project is now in the final stage. At the construction site, workers and machinery are mobilized to complete the drainage system, spread crushed stone, and compact the road surface.

Tuyen duong Tien Hoi - Hoang Nong du kien hoan thanh trong nam 2024. Anh: Viet Bac.
Tien Hoi - Hoang Nong route is expected to be completed in 2024. Photo: Viet Bac.

According to a worker at the project, the upgrading and renovation based on the old roadbed should be quite favorable. However, since the beginning of 2024, there has been too much rain, and construction has been interrupted frequently.

People living and doing business along the road are the ones who benefit the most as trade and travel are also more convenient. Most households whose land was acquired and affected by the project agreed, many households proactively donated land to build the road.

Ms. Hoang Thi Lien, Hoang Nong Commune (Dai Tu) said: "Before being repaired, the road was small, bad and full of potholes, only about 10 km long but it was very difficult to travel. We are very happy that the road has been upgraded, 2 households next to my house volunteered to demolish the gate to widen the road."

Talking to reporters, Mr. Tran Duc Quy - Chairman of Tien Hoi Commune People's Committee said that the Tien Hoi - Hoang Nong road project is in the process of completion. This is considered a traffic project of important significance to the socio-economic development of the locality.

"During the implementation process, there were some difficulties in mobilizing people to donate land for road construction. After propaganda and explanation, people understood and agreed.

Previously, the road was narrow and it was very difficult to travel. Now that the road has been widened, it will help vehicles move more easily and conveniently," the commune leader informed.

Some images recorded by PV:

1
Construction work resumed after the historic flood in Thai Nguyen in mid-September 2024. Photo: Viet Bac.
3
Some vulnerable locations are reinforced with stone revetment walls. Photo: Viet Bac.
De thuc hien du an, gan 700 ho dan hai xa Tien Hoi, Hoang Nong tu nguyen hien tren 14.600 m2. Anh: Viet Bac.
To implement the project, nearly 700 households in Tien Hoi and Hoang Nong communes voluntarily donated over 14,600 m2. Photo: Viet Bac.
Mat duong duoc cai tao, mo rong hon so voi cot duong cu. Anh: Viet Bac.
The road surface has been renovated and widened compared to the old roadbed. Photo: Viet Bac.
Nguoi dan mong muon du an som hoan thanh, thuan loi cho viec di lai. Anh: Viet Bac.
People hope the project will be completed soon, making it easier to travel. Photo: Viet Bac.
Bdbd
Many locations with construction pits, which pose potential safety risks, have had signs and ropes put up by the construction unit. Photo: Viet Bac.

Nguyễn Hoàn
TIN LIÊN QUAN

Clarifying responsibility for issuing wrong red books on prison land

|

Lam Dong - Provincial inspectors determined that 4.29 hectares of land of Dai Binh Prison had been illegally granted red books by local authorities to 7 households.

Inadequate treatment of officials and workers

|

National Assembly delegates said that the treatment of officials and employees working at drug rehabilitation facilities is not commensurate with the requirements and tasks of the job.

Nam Dinh has a new Provincial Party Secretary

|

Nam Dinh - Mr. Dang Khanh Toan was mobilized and appointed by the Politburo to hold the position of Secretary of Nam Dinh Provincial Party Committee.

Go Cong sea dike "fluctuates" before monsoon season

|

Tien Giang - Some sections of the Go Cong sea dike are degraded, local authorities in Go Cong Dong district have proposed investing in wave-reducing dikes.

Sad news

|

Mr. Ignatius Do Van Luan, born in 1956, father of comrade Do Thi Yen Phuong, father-in-law of comrade Nguyen Van Quang - reporter of Lao Dong Newspaper working at the Representative Office in the Mekong Delta, passed away at 2:00 p.m. on November 13, 2024, October 13, Giap Thin year. He was 68 years old.

Proposal to discipline former Minister of Transport Nguyen Van The

|

At the 50th Session, the Central Inspection Committee proposed that competent authorities consider and discipline Mr. Nguyen Van The.

Children whose parents died in storm No. 3 were given savings books by the Union

|

The Vietnam General Confederation of Labor has just issued a Decision on supporting orphaned children of union members and workers who died due to storm No. 3 (Yagi).

Inspect the responsibility of 4 department directors of Ha Nam

|

The inspection focuses on the responsibility of the heads of four departments and branches in Ha Nam in implementing legal regulations.

Xử lý vụ dân bắc thang trèo vào nhà vì đường 1.900 tỉ "ăn" đường liên xã

Tô Công |

Phú Thọ - Chính quyền địa phương, Chủ đầu tư dự án đường liên vùng 1.900 tỉ đồng và người dân xã Văn Khúc, huyện Cẩm Khê đã có buổi làm việc để giải quyết vụ người dân phải bắc thang trèo vào nhà vì mất đường liên xã.

Người dân bắc thang trèo vào nhà vì dự án đường 1.900 tỉ đồng "ăn" mất đường liên xã

Đại Phong |

Dự án Đường giao thông liên vùng kết nối đường Hồ Chí Minh với Quốc lộ 70B, Quốc lộ 32C tỉnh Phú Thọ đi Yên Bái thi công qua địa phận xã Văn Khúc, huyện Cẩm Khê, tỉnh Phú Thọ đã xảy ra những vấn đề khi dự án lấn đường liên xã.

Hàng trăm người dân ở Lâm Đồng bất an vì đường liên xã như "ruộng cày"

Phan Tuấn |

Nhiều năm gần đây, người dân ở thôn 4, xã Lộc Thành, huyện Bảo Lâm (Lâm Đồng) phải khốn khổ đi trên đoạn đường cấp phối, độc đạo chi chít “ổ trâu”, “ổ voi”... Đoạn đường này đã trở thành nỗi ám ảnh, bất an. Nhiều người đã bị té ngã, gãy tay, gãy chân...