Urging to accelerate the progress of many slow and oversized projects in Ha Tinh

TRẦN TUẤN |

Ha Tinh - Many projects are facing obstacles and difficulties in site clearance, cost overruns, so the Provincial People's Committee has had to urge and focus on removing obstacles and accelerating progress.

According to reporters of Lao Dong Newspaper, the Thach Ha urban infrastructure improvement sub-project in Thach Ha commune and the Huong Khe urban infrastructure improvement sub-project (Huong Khe commune) are currently under construction, and prolonged construction has caused many consequences.

People want the project to accelerate construction to reduce the impact on travel and living.

The Thach Ha urban infrastructure improvement sub-project was previously invested by Thach Ha District People's Committee (old), now invested by the Provincial Civil and Infrastructure Construction Investment Project Management Board.

Tiểu dự án cải thiện cơ sở hạ tầng đô thị Thạch Hà đang triển khai thi công. Ảnh: Trần Tuấn
Thach Ha urban infrastructure improvement sub-project is under construction. Photo: Tran Tuan

The project was started at the end of December 2023 with a total investment of more than 851 billion VND. According to the initial schedule, by the end of 2024, the project had to complete construction and installation, but was later delayed.

Currently, the project has been approved by the Ha Tinh Provincial People's Committee for adjustment, extending the time to December 2026.

Along with the slow progress, the project has adjusted capital increases twice. On December 13, 2024, the Ha Tinh Provincial People's Council issued Resolution No. 209 adjusting the investment policy of the Thach Ha urban infrastructure improvement sub-project from more than 851 billion VND to more than 911 billion VND.

The above-mentioned Resolution also adjusted the Huong Khe Urban Infrastructure Improvement Sub-project (former Huong Khe district) from more than 709 billion VND to more than 781 billion VND.

Most recently, on May 8, 2025, Ha Tinh Provincial People's Committee issued Decision No. 1164 adjusting the capital increase for the Thach Ha Urban Infrastructure Improvement Sub-project from more than VND 911 billion to more than VND 986 billion (an increase of VND 75 billion).

This decision also adjusted the capital increase for the Huong Khe Urban Infrastructure Improvement Sub-project from more than 781 billion VND to more than 828 billion VND (an increase of more than 47 billion VND).

Tiểu dự án cải thiện cơ sở hạ tầng đô thị Hương Khê đang thi công. Ảnh: Trần Tuấn
The Huong Khe urban infrastructure improvement sub-project is under construction. Photo: Tran Tuan

According to Mr. Nguyen Quang Linh - Director of the Project Management Board for Investment in Construction of Civil Works and Infrastructure in Ha Tinh province, the fact that the locality has not completed the handover of land to the Thach Ha Urban Infrastructure Improvement Sub-project and the Huong Khe Urban Infrastructure Improvement Sub-project makes the project completion progress more pressured, because the entire project must be completed by December 2026.

The Ham Nghi road project is extended with a total investment of 575 billion VND, with a length of 3.3 km with the starting point connecting National Highway 1 bypass through Thach Dai commune (now Ha Huy Tap ward), the ending point connecting to the National Highway 8C branch through Thach Xuan commune.

According to the previous approval, the project must be completed and handed over in 2024. However, due to site clearance problems and slow progress, Ha Tinh Provincial People's Committee has extended the deadline to December 31, 2026.

Recently, the Provincial People's Committee issued Decision No. 1422 approving the adjustment of capital sources, increasing the total investment of the project from more than 575 billion VND to more than 630 billion VND (an increase of 55 billion VND).

Dự án đường Hàm Nghi kéo dài chậm tiện độ, đội vốn. Ảnh: Trần Tuấn
Ham Nghi extended road project is behind schedule, over budget. Photo: Tran Tuan

The eastern ring road project of Ha Tinh city (old) has a total investment of nearly 1,000 billion VND, passing through Thanh Sen and Tran Phu wards. The project is invested by the Ha Tinh Provincial Traffic Construction and Urban Development Investment Project Management Board. Also due to problems in site clearance, this project is behind schedule.

Mr. Nguyen Danh Phong - Deputy Director of the Project Management Board for Investment in Construction of Transport Works and Urban Development of Ha Tinh province said that the eastern ring road project of Ha Tinh city (old) was started in 2022. Previously, the project was assigned to be completed by the end of 2025, but due to many difficulties and obstacles in site clearance, it has now been extended to 2027.

Dự án đường vành đai phía Đông thành phố Hà Tĩnh (cũ) vướng mắc mặt bằng nên phải gia hạn tiến độ. Ảnh: Trần Tuấn
The eastern ring road project of Ha Tinh city (old) is facing site clearance problems, so the progress must be extended. Photo: Tran Tuan

Faced with the situation that many projects are behind schedule, Ha Tinh Provincial People's Committee has just issued a document urging to departments, agencies, and branches at the provincial level; People's Committees of communes and wards; project management boards, investors, and investors with the requirement to strengthen management and accelerate the progress of projects, especially large and key projects.

The Provincial People's Committee directed that, for projects with prolonged delays, agencies and units assigned to monitor and manage should proactively review and clarify the causes and responsibilities of relevant organizations and individuals.

Heads of agencies, units, and localities are responsible to the Provincial People's Committee and the Chairman of the Provincial People's Committee if delays occur due to subjective reasons, irresponsibility, avoidance, shirking, or failure to promptly advise on handling contents under their authority.

TRẦN TUẤN
RELATED NEWS

Urging to accelerate the progress of social housing projects in Nghe An

|

Nghe An - The province urges departments and sectors to remove obstacles and accelerate the progress of social housing projects in order to complete the targets assigned by the Government in 2026.

Ha Tinh urges progress of 2 inter-level boarding schools to start construction from 2025

|

Ha Tinh - The Provincial People's Committee has just urged to accelerate the construction progress of the inter-level boarding primary and secondary school in Son Kim 1 and Huong Khe communes.

Urging flood control projects in the central ward of Bac Ninh

|

Bac Ninh - Chairman of the Provincial People's Committee Pham Hoang Son has urged the implementation of a project to overcome flooding and waterlogging in Bac Giang ward.

A gold shop in Thu Dau Mot temporarily suspends operations, buyers worried

|

Ho Chi Minh City - Gold shop in Kim Hong (on Cach Mang Thang Tam street, Thu Dau Mot ward) closed and temporarily suspended operations.

Building a Visionary Press System Development and Management Strategy to 2045

|

On June 15, in Hanoi, the Ministry of Culture, Sports and Tourism organized a workshop to contribute opinions on building a dossier on the Strategy for development and management of the press system to 2030, with a vision to 2045.

Localities are allowed to sign contracts to support commune-level civil servants, not included in the payroll

|

The Ministry of Home Affairs requests localities to sign contracts to support commune-level civil servants, and people working under contracts are not included in the payroll.

Trade unions get involved, seafood processing workers receive late-paying salaries

|

Lam Dong - After the trade union and police worked with businesses, workers at a seafood processing company were paid the delayed salary.

Urging to accelerate the progress of social housing projects in Nghe An

QUANG ĐẠI |

Nghe An - The province urges departments and sectors to remove obstacles and accelerate the progress of social housing projects in order to complete the targets assigned by the Government in 2026.

Ha Tinh urges progress of 2 inter-level boarding schools to start construction from 2025

TRẦN TUẤN |

Ha Tinh - The Provincial People's Committee has just urged to accelerate the construction progress of the inter-level boarding primary and secondary school in Son Kim 1 and Huong Khe communes.

Urging flood control projects in the central ward of Bac Ninh

Vân Trường |

Bac Ninh - Chairman of the Provincial People's Committee Pham Hoang Son has urged the implementation of a project to overcome flooding and waterlogging in Bac Giang ward.