National Highway 279 is the main traffic axis connecting Lao Cai and Ha Giang with Noi Bai - Lao Cai Expressway, and will be the access road to Sa Pa airport in the future.
However, the road section through Pho Rang town, Bao Yen district has long been degraded, landslides and many dangerous curves do not ensure safety for people when participating in traffic.
At the end of 2023, the project to upgrade the road connecting National Highway 70 with National Highway 279, Bao Yen district was implemented with a total investment of 25.3 billion VND. The investor is the Bao Yen District Construction Investment Project Management Board, the construction unit is Minh Duc General Construction Company Limited.
The project must be completed by April 2025, but up to now, construction is still sluggish, not reaching 50% of the progress.


In early May, according to the reporter of Lao Dong Newspaper, although the project only lasted about 1km, it was often congested due to no one dividing the two ends. Along the route, rocks, soil, and construction materials are dumped, creating traps for traffic participants, especially at night.
Although this is a unique route, the contractor's construction process lacks warning signs in dangerous areas, posing a potential risk to the safety of people and vehicles passing through.




Mr. Mai Van Nam in Pho Rang town said: "This road is under construction, dusty on sunny days, muddy on rainy days, making it very difficult for people to travel. Not to mention many construction sections are sluggish, without fences, making it easy for traffic accidents to occur.
In particular, through observation at the scene, the pre-cast culvert system that was cracked and broken was still put into construction; the water collection manholes showed signs of being constructed incorrectly, the concrete quality was not guaranteed, peeled, workers used cement to patch them.



Speaking to Lao Dong Newspaper, Mr. Le Quang Trung Hieu - Deputy Director of the Bao Yen District Construction Investment Project Management Board said: Due to problems with site clearance, up to now, the project has only completed half of the road and is carrying out procedures to extend the progress.
Regarding the lack of warning signs and barriers at many construction sites, which pose a potential risk to the safety of people and vehicles, Mr. Le Quang Trung Hieu said that he will request Minh Duc General Construction Company Limited to rectify and overcome the situation.



Minh Duc General Construction Company Limited is located at house number 79B, Quy Hoa Street, Kim Tan Ward, Lao Cai City, Lao Cai Province, with Ms. Nguyen Thi Minh Hien as Director.
Since 2018, this enterprise has participated in the construction of 49 packages with a total winning bid capital of more than 1,655 billion VND; of which the independent role is more than 785 billion VND; the joint venture role is more than 870 billion VND.
Currently, Minh Duc General Construction Company Limited is constructing a series of large packages in Lao Cai province such as: Renovation and upgrading of provincial road 154 from Ta Thang to Coc Ly (Km74-Km88) worth more than 84 billion VND; Renovation and upgrading of provincial road 153 from Km19-Km24 and provincial road 159 from Km34 - Km38 worth more than 107 billion VND; leveling of land and technical infrastructure of Tan Lap urban area, Bac Cuong ward, Lao Cai city worth more than 169 billion VND. The project of the Linh Khau Nhin - Cao Son - La Pan Tan commune road, Muong Khuong district is worth more than 120 billion VND...