The 4km runway at Long Thanh airport will be basically completed before December 19

HÀ ANH CHIẾN |

Dong Nai - The second runway at Long Thanh airport is 4 km long and 75 m wide, basically completing the cement concrete part before December 19.

On November 16, according to information from Vietnam Airports Corporation (ACV), the second runway at the Long Thanh airport project has basically completed the groundbreaking work, and is undergoing the construction of the crushed stone aggregate layer reaching 72.6% and the 150/25 cement concrete structure reaching 60.58%.

ACV is continuing to mobilize personnel, machinery and equipment in the coming time to meet the goal of completing the cement concrete part before December 19, 2025; ensuring completion and putting it into operation in June 2026 according to the required schedule.

Progress according to the contract: the second runway will start construction on May 30, 2025 and be completed in June 2026.

Duong cat ha canh thu nhat tai san bay Long Thanh. Anh: HAC
The first runway at Long Thanh airport. Photo: HAC

The second runway, 4 km long and 75 m wide, is currently under simultaneous construction.

The construction contractor is the joint venture ACC - Truong Son - Vinaconex - Vinadic - ACJC647-Khanh Thien-VTG.

The contract value is VND 2,570.36 billion (of which VND 2,364.73 billion is the construction value, excluding replenishment fees).

ACV has directed the contractor consortium to make the most of the weather to carry out the construction.

To proactively source supply and avoid interruption of progress, more than 100,000 m3 of materials have been gathered at the construction site since the first stage.

Component project 3 - Essential works in the Airport under the Long Thanh International Airport Construction Investment Project Phase 1 invested by ACV include 14 packages.

The scale of phase 1 of the project with 2 runways, 1 passenger terminal and synchronous auxiliary items with a capacity of 25 million passengers/year; 1.2 million tons of cargo/year.

At the same time, implementing the direction of the Prime Minister, ACV has issued Document No. 4219/TTr-TCTCHKVN dated September 24, 2025 reporting to the Government, the Ministry of Finance, and the Ministry of Construction to immediately deploy the third runway and phase 2 of Long Thanh International Airport in accordance with the provisions of law.

HÀ ANH CHIẾN
RELATED NEWS

Resettlement of nearly 1,000 households to expand the road connecting Long Thanh airport

|

Dong Nai - The project to upgrade and expand DT 769 road to reclaim land of 3 communes of Dau Giay, Binh An, Long Thanh connecting to Long Thanh airport.

Expanding a 39 km long road in Dong Nai connecting Long Thanh airport

|

Dong Nai - The project to upgrade and expand DT 773 route, over 39km long, passing through 8 communes of Dong Nai province connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.

Nearly 14,000 construction personnel work day and night to speed up the progress of the Long Thanh Airport Project

|

The connecting traffic routes are sprinting to be put into operation in sync with Long Thanh airport on December 19, towards commercial operation in 2026.

Many roads in Hue are flooded due to heavy rain, water flows like waterfall

|

HUE - Heavy rain caused many roads in A Luoi 3 commune to be flooded, water from the mountains poured down, creating a strong flow, endangering vehicles.

Hue mountainous area turns into river, national highway landslides due to heavy rain

|

HUE - Heavy rain caused many roads in mountainous communes of Hue City to be deeply flooded, water flowing rapidly, and landslides causing traffic jams.

Stock market waiting for explosive session

|

The recovery momentum of the stock market needs to be reinforced by improvements in liquidity in the coming time.

Social housing is deserted because workers complain about the hardship of completing documents

|

HCMC - Workers are Fed up with cumbersome procedures, traveling many times to apply for social housing (NOXH), causing projects to lack customers.

Close-up of the hundred-year-old bridge across the Huong River, 3 times dispatched ships to guard it in the midst of floods

|

HUE - More than 117 years old, the Bach Ho - Da Vien railway bridge has been sent to the harbor by ship carrying rocks 3 times in just one week of floods.

Resettlement of nearly 1,000 households to expand the road connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand DT 769 road to reclaim land of 3 communes of Dau Giay, Binh An, Long Thanh connecting to Long Thanh airport.

Expanding a 39 km long road in Dong Nai connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand DT 773 route, over 39km long, passing through 8 communes of Dong Nai province connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.

Nearly 14,000 construction personnel work day and night to speed up the progress of the Long Thanh Airport Project

HÀ ANH CHIẾN |

The connecting traffic routes are sprinting to be put into operation in sync with Long Thanh airport on December 19, towards commercial operation in 2026.