Key road in the East of Ho Chi Minh City not completed after 16 years due to 226 households

MINH QUÂN |

Ho Chi Minh City - After 16 years of construction, the project to expand Hanoi Highway and National Highway 1 has not been completed due to site clearance issues for 226 households.

The project to expand Hanoi Highway and National Highway 1 has a total length of 15.7km, from Saigon Bridge to Tan Van intersection, started in 2010 in the form of BOT (build - operate - transfer).

Initially, the project was approved by the Ho Chi Minh City People's Committee with a total investment of 2,516 billion VND and in 2016 it was adjusted to increase to more than 4,900 billion VND.

According to the design, the road is expanded to 12 - 16 lanes and divided into three sections. In which, the section from Saigon Bridge to Binh Thai intersection is 6.2km long; the section from Binh Thai to Tram 2 intersection is 5.3km long; the section from Tram 2 intersection to Tan Van is 4.2km long.

The project is expected to be completed after 36 months from the date of site handover. However, so far only the first two sections have been basically completed, while the final section is still unfinished due to problems with compensation and site clearance.

Hầm chui song hành phải Xa lộ Hà Nội dừng thi công từ tháng 6.2023. Ảnh: Minh Quân
The parallel underpass must have stopped construction on Hanoi Highway (HCMC) from June 2023. Photo: Minh Quan

One of the items that cannot be put into operation is the underpass on the right parallel line of Hanoi Highway, the Tram 2 intersection area in the direction from Saigon Bridge to Dong Nai. The project is about 400m long and is currently facing land issues for 21 households in Tang Nhon Phu ward.

According to Ho Chi Minh City Infrastructure Investment Joint Stock Company (CII) - the project investor, if the full site is handed over, this item will only take about 3 months to complete and put into use.

Quốc lộ 1 (từ bến xe Miền Đông mới đến nút giao Tân Vạn) chưa mở rộng xong, tạo nút thắt cổ chai. Ảnh: Anh Tú
National Highway 1 (from the new Mien Dong bus station to Tan Van intersection) has not been completed, creating a bottleneck. Photo: Anh Tu

Meanwhile, the section from the main gate intersection of Ho Chi Minh City National University to Tan Van intersection still has about 11.5ha of land that cannot be recovered, affecting the construction of the left parallel line. For the right parallel line, only about 500m in front of the Mien Dong Bus Station area has been deployed.

Statistics show that this area still has 205 cases, including 203 cases in Dong Hoa ward, one case in Linh Xuan ward and one case in Phuoc Long ward.

Leaders of Dong Hoa ward said that the above cases belong to Binh Thang ward, Di An city (Binh Duong province before). Due to the project being stalled for a long time, this area has lost 71 out of a total of 80 land clearance milestones, forcing functional agencies to restore the milestones to continue implementing land acquisition procedures.

Đoạn qua bến xe Miền Đông mới còn vướng mặt bằng. Ảnh: Anh Tú
The section passing through the new Mien Dong bus station is still facing site clearance issues. Photo: Anh Tu

Recently, the Office of the Ho Chi Minh City People's Committee issued a notice of the conclusion of Vice Chairman of the Ho Chi Minh City People's Committee Hoang Nguyen Dinh at the meeting to review the progress of compensation and site clearance for the project.

Accordingly, the People's Committee of Tang Nhon Phu ward is assigned to continue to mobilize and persuade the remaining 21 households to hand over the land before July 25, 2026.

Phuoc Long and Linh Xuan Ward People's Committees are requested to urgently review legal documents and complete the mobilization of the remaining households to hand over the land according to the assigned deadline.

Ho Chi Minh City leaders also requested Ho Chi Minh City National University to coordinate with Dong Hoa Ward People's Committee to urgently hand over the boundary, organize marker planting on the ground to serve inventory, compensation, site clearance and deploy the next steps of the project.

For 71 cases requiring resettlement by land plots, the Ho Chi Minh City People's Committee assigned the Department of Construction to preside over and coordinate with relevant units to review appropriate resettlement arrangement plans.

This is the basis for the Ho Chi Minh City Traffic Construction Investment Project Management Board to soon complete the project adjustment dossier and submit it to competent authorities for consideration according to regulations.

MINH QUÂN
RELATED NEWS

Ho Chi Minh City extends the metro line connecting Binh Duong by an additional 15.6km to the center

|

Ho Chi Minh City - Thu Dau Mot - Ho Chi Minh City Metro line will be extended by 15.6km, bringing the ending point from the Hiep Binh Phuoc depot area to Tao Dan station (District 1 previously).

Ho Chi Minh City recovers land from 853 households to build a project worth more than 145.6 trillion VND

|

Ho Chi Minh City will complete land acquisition from 853 households in October 2026 to build Rach Chiec National Sports Complex with a total capital of more than 145.600 billion VND.

Solving the problem of traffic jams and flooding in the overall plan of Ho Chi Minh City

|

Ho Chi Minh City - The overall plan of Ho Chi Minh City is not only to expand the city but also to find fundamental solutions to the two biggest challenges today: traffic jams and flooding.

Prime Minister Le Minh Hung presents flowers to congratulate the Executive Committee of the 14th Vietnam General Confederation of Labour

|

At the 14th Vietnam Trade Union Congress, Prime Minister Le Minh Hung presented flowers to congratulate the Executive Committee of the 14th Vietnam General Confederation of Labor, term 2026-2031.

From "Trade Union Shelter" to housing policies for workers

|

Khanh Hoa - At the 14th Congress of the Vietnam Trade Union, the delegation of the Provincial Trade Union brought many recommendations to improve the lives of union members and workers.

Forming a "Trade Union Ecosystem" in Dong Thap Industrial Parks

|

Dong Thap - Mr. Nguyen Thanh Nhan - Member of the Standing Committee of the Dong Thap Provincial Labor Federation, Chairman of the Trade Union of Industrial Zones and Economic Zones - wrote an article in response to the direction of General Secretary and President To Lam at the 14th Congress of the Vietnam Trade Union, which became a direction for deploying work at his unit.

Master digital space to be closer to workers

|

At the 14th Congress of the Vietnam General Confederation of Labour, term 2026 - 2031, Mr. Nguyen Van Thang - Member of the Presidium of the Vietnam General Confederation of Labour, City Party Committee Member, Vice Chairman of the Vietnam Fatherland Front Committee of Hanoi City, Chairman of the Hanoi Labor Federation - presented a paper on propaganda, political, ideological, and legal education for union members and workers...

Early dialogue, solution from the root to limit collective work stoppages

|

Ms. Nguyen Thi Huong - Chairwoman of the Tien Lang Commune Trade Union, Hai Phong City - said, as a trade union official of Tien Lang commune, Hai Phong City, I am very impressed with the direction of General Secretary, President To Lam at the 14th Congress of the Vietnam Trade Union, including the direction on building harmonious, stable, progressive labor relations, contributing to maintaining social stability and the country's development environment.

Ho Chi Minh City extends the metro line connecting Binh Duong by an additional 15.6km to the center

MINH QUÂN |

Ho Chi Minh City - Thu Dau Mot - Ho Chi Minh City Metro line will be extended by 15.6km, bringing the ending point from the Hiep Binh Phuoc depot area to Tao Dan station (District 1 previously).

Ho Chi Minh City recovers land from 853 households to build a project worth more than 145.6 trillion VND

MINH QUÂN |

Ho Chi Minh City will complete land acquisition from 853 households in October 2026 to build Rach Chiec National Sports Complex with a total capital of more than 145.600 billion VND.

Solving the problem of traffic jams and flooding in the overall plan of Ho Chi Minh City

MINH QUÂN |

Ho Chi Minh City - The overall plan of Ho Chi Minh City is not only to expand the city but also to find fundamental solutions to the two biggest challenges today: traffic jams and flooding.