Hanoi expands arterial roads, many households do not cooperate in land counting

HỮU CHÁNH - BẢO HÂN |

Hanoi - Many households subject to site clearance for the National Highway 6 expansion project have proposed the red line planning boundary, so they have not cooperated in investigating and counting land.

In December 2022, the Hanoi People's Committee started the project to expand National Highway 6 by 21.7km through Ha Dong district (old) and Chuong My district (old), of which the section through Chuong My district is 15.8km long and Ha Dong is 5.9km long.

The starting point of the project is located at km14 in Ba La, Ha Dong district (now Yen Nghia ward); the end point is km38, Xuan Mai town, Chuong My district (now Xuan Mai commune).

The project has 5 construction packages, including items: Synchronous construction of roadbed, water supply and drainage, technical cable cars, lighting, trees, 8 road bridges, 1 newly built box culvert.

The project has a total investment of over VND9,590 billion, invested by the Hanoi Traffic Construction Investment Project Management Board, implemented in the period of 2022-2027.

Quoc lo 6 doan qua Ha Noi chat hep, thuong xuyen un tac, dac biet vao gio cao diem. Anh: Tat Thao
National Highway 6 is a vital route connecting Hanoi with Phu Tho and the Northwestern provinces, but the road surface is narrow and often congested. Photo: Bao Han

According to Lao Dong's records in early December, in Ha Dong district (old), the site has not been handed over, currently only a small part is being constructed on public land and the intersection with Ring Road 4.

The section through Chuong My ward, Phu Nghia commune, Xuan Mai commune, the contractor is implementing construction at some locations with cleared land. However, the handover of " sticky rice and bean" land has significantly affected the construction work as well as the travel of people.

Information on the progress of the National Highway 6 expansion project, a representative of the Hanoi Traffic Construction Investment Project Management Board said that regarding the bridge and culvert section, contractors are basically implementing construction, but the completed volume is still low.

As for the road (the expanded construction part), only about 1,955m of asphalt concrete has been paved with the sections and the technical infrastructure is synchronized. The sections have other land that is being paved with, embankments...

dD
National Highway 6 through Phu Nghia Industrial Park is being expanded. Photo: Bao Han

According to statistics, in Chuong My district (old), about 51.46ha/85.4ha has been handed over, reaching a rate of 60% (the area of public land and agricultural land on the entire route), however, the handover site is sticky rice and bean sprouts, not connected to the route, and there are technical infrastructure works and architectural works that have not been moved. The residential land has not been cleared.

Site clearance in the wards of Yen Nghia, Kien Hung, Phu Luong, Duong Noi (in the old Ha Dong district) is all behind schedule and faces many difficulties, such as: Land records in the wards are not synchronous, many cases of border encroachment, land use rights disputes; old data has not been updated on the situation of separation...

In addition, there are households subject to site clearance that have petitioned about the red line planning boundary, so they have not cooperated in investigating and declaring the counting.

Quoc lo 6 doan qua dia ban quan Ha Dong (cu). Anh: Tat Thao
National Highway 6 through Ha Dong District (old) is stuck in site clearance. Photo: Bao Han

To resolve the above difficulties, the City Traffic Construction Investment Project Management Board has issued a document requesting the City People's Committee to allow investors and measurement consultants to coordinate with the People's Committees of communes and wards to conduct map surveys and make statements on the current status of plots as a basis for compensation and support for households and individuals with land within the site clearance boundary.

At the same time, coordinate with the People's Committees of communes and wards to speed up site clearance, especially focusing on determining the origin of land, confirming the population... For households that have investigated and counted, request the People's Committees of communes and wards to sign confirmation according to regulations as a basis for implementing the next steps.

The investor strives to complete the land acquisition and site clearance work by the second quarter of 2026 to hand over to contractors to complete the project in 2027.

HỮU CHÁNH - BẢO HÂN
RELATED NEWS

People simultaneously move assets, hand over land for the Ring Road 1 project

|

Hanoi - Many households are moving their assets to hand over the site for the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Some households deliberately encroach, do not hand over land for the construction of the 2.5 belt road in Hanoi

|

Hanoi - Some households deliberately re-encroach on the site and refuse to hand over the site to the contractor for the Ring Road 2.5 project.

Power, water and corrugated iron fences cut off for 138 households that do not hand over the land for Ring Road 1

|

Hanoi - Giang Vo Ward has cut off electricity, water and corrugated iron fences for 138/144 households that do not hand over the site for the Ring Road 1 project, Hoang Cau - Voi Phuc section.

2 big goals of Miss Le Nguyen Bao Ngoc at Miss World 2026

|

Le Nguyen Bao Ngoc sets two goals at Miss World 2026: high achievements and a meaningful journey.

New developments in the case of Yen Bai Transport Hospital being late in paying staff for 4 years

|

Lao Cai - The Department of Health has just held a meeting with staff of Yen Bai Transport Hospital to discuss employment.

Gia Bac Pass in Lam Dong suffered a serious landslide, 20 cars were stuck on National Highway 28

|

Lam Dong - Initially, the authorities recorded a landslide and a fall of forest trees on National Highway 28, causing about 20 cars to be stuck at Gia Bac Pass.

Thailand apologizes for the incident of not playing the national anthem in the match between U22 Vietnam and U22 Laos

|

A rare incident occurred in the opening match of the 33rd SEA Games men's football event between U22 Vietnam and U22 Laos when players of both teams had to "sing" the National Anthem.

Hanoi Police warn of the "diplomatic" scam of social housing spreading online

|

Hanoi - At the Social Housing Dialogue Conference, representatives of Hanoi City Police warned about the "diplomatic" trick of buying social housing

People simultaneously move assets, hand over land for the Ring Road 1 project

HỮU CHÁNH |

Hanoi - Many households are moving their assets to hand over the site for the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Some households deliberately encroach, do not hand over land for the construction of the 2.5 belt road in Hanoi

HỮU CHÁNH |

Hanoi - Some households deliberately re-encroach on the site and refuse to hand over the site to the contractor for the Ring Road 2.5 project.

Power, water and corrugated iron fences cut off for 138 households that do not hand over the land for Ring Road 1

HỮU CHÁNH |

Hanoi - Giang Vo Ward has cut off electricity, water and corrugated iron fences for 138/144 households that do not hand over the site for the Ring Road 1 project, Hoang Cau - Voi Phuc section.