Two key traffic routes in Phu Tho will be completed in June

Tô Công |

Phu Tho - There are two key transport projects, the inter-regional road and the road connecting 2 expressways, both of which have set a target to be completed before June 30, 2026.

Multi-billion VND inter-regional road connecting Phu Tho - Lao Cai

The inter-regional traffic road project connecting Ho Chi Minh Road with National Highway 70B, National Highway 32C Phu Tho province to Yen Bai province (now Lao Cai province) is one of the key traffic projects of Phu Tho province, started at the end of 2021 to date.

The project has a total investment of up to 2,120 billion VND invested by the Phu Tho Regional Project Management Board. Since 2024, more than 50km of the main route has been handed over and put into operation.

Hơn 2km đầu tuyến chính đã thi công xong. Ảnh: Tô Công
More than 2km of the main route has been completed. Photo: To Cong

To date, the additional section of more than 2km at the beginning of the main route (Km0 - Km2+452) through Van Xuan commune has also been completed. Vehicles can easily travel.

According to a representative of the Phu Tho Regional Project Management Board, the above-mentioned route section is currently in the process of completing procedures for handover and putting into operation.

Tuyến đường liên vùng kéo dài cũng đang trong quá trình hoàn thiện. Ảnh: Tô Công
The extended inter-regional road is also in the process of completion. Photo: To Cong

For the extended inter-regional road section (more than 3.7km) connecting Km0 of the inter-regional road with National Highway 32 in Tam Nong commune, the Ho Chi Minh road overpass and many other items have been completed. The contractor is currently completing the asphalt paving of the road surface.

With a branch line of more than 3km connecting the main inter-regional road with Cam Khe industrial park, the asphalt paving of the road surface, the traffic safety system section from Km0 - Km2+300 and the Dong Men bridge item have been basically completed.

Tuyến nhánh đường liên vùng thẳng tắp đi qua những cánh đồng, đồi cao tại xã Cẩm Khê. Ảnh: Tô Công
The inter-regional branch road is straight through fields and high hills in Cam Khe commune. Photo: To Cong

The construction sites of the above-mentioned 3 sections of the inter-regional road project are maintaining an urgent and continuous pace of work.

The goal is to complete it all before June 30, 2026.

Nearly 700 billion VND project to build road connecting two key expressways

Another traffic infrastructure project is also racing against time. That is the project to invest in connecting the Noi Bai - Lao Cai expressway with the Tuyen Quang - Phu Tho expressway. The project plays an important role in helping to close the expressway network.

Toàn cảnh tuyến đường nối 2 cao tốc sắp hoàn thành ở Phú Thọ. Ảnh: Tô Công
Overview of the road connecting 2 expressways to be completed in Phu Tho. Photo: To Cong

The above project has a total investment of more than 692 billion VND, construction starts from mid-February 2025. The project to build the road has a total length of more than 2.7km, connecting the IC9 intersection of the Noi Bai - Lao Cai expressway and the ending point of the Tuyen Quang - Phu Tho expressway. The rest is the service road system.

According to the report of the Phu Tho Regional Project Management Board (the project investor), up to now, construction deployment has reached over 85% of the volume, with many important items completed.

Các hạng mục phức tạp nhất của tuyến đường nối 2 cao tốc đã hoàn thành. Ảnh: Tô Công
The most complex items of the road connecting the 2 expressways have been completed. Photo: To Cong

Specifically, the entire length of the main route has been asphalted; the overpass item at the provincial road intersection 315B (connecting directly to the end point of the Tuyen Quang - Phu Tho expressway) has been completed.

The contractor has constructed 5/5 underpasses, 10/10 box culverts, 14/14 round culverts, 100% precast components, 100% retaining walls...

Các hạng mục cuối cùng đang được khẩn trương hoàn thiện. Ảnh: Tô Công
The final items are being urgently completed. Photo: To Cong

Items such as: IC9 intersection branch line, service road, restored road... are in the process of completion; traffic safety and smart traffic systems are also being installed.

The goal is to complete construction before June 30, 2026.

Tô Công
RELATED NEWS

A wake-up call for parents from the case of 18 teenagers causing trouble in Phu Tho

|

The case of 18 teenagers carrying weapons causing trouble at night in Phu Tho being handled is a warning to parents in managing their children during the summer vacation.

Phu Tho mountainous commune invests 19.5 billion VND to renovate traffic roads

|

Phu Tho - Trung Son mountainous commune invests 19.5 billion VND to renovate and upgrade the road from Dong Mang area to Bop area.

Transport infrastructure accelerates, unlocking growth momentum in Lao Cai

|

Lao Cai - The completion of infrastructure not only helps connect areas, creates convenience for people to travel but also contributes to promoting economic development.

Building a Visionary Press System Development and Management Strategy to 2045

|

On June 15, in Hanoi, the Ministry of Culture, Sports and Tourism organized a workshop to contribute opinions on building a dossier on the Strategy for development and management of the press system to 2030, with a vision to 2045.

Localities are allowed to sign contracts to support commune-level civil servants, not included in the payroll

|

The Ministry of Home Affairs requests localities to sign contracts to support commune-level civil servants, and people working under contracts are not included in the payroll.

Trade unions get involved, seafood processing workers receive late-paying salaries

|

Lam Dong - After the trade union and police worked with businesses, workers at a seafood processing company were paid the delayed salary.

Large amount of soil and dust arises when dismantling Chi Lang stadium in Da Nang

|

Da Nang - Dust arising during the dismantling of Chi Lang stadium is affecting the daily life and business of people in the surrounding area.

18 million phone numbers will be locked for calls on the afternoon of June 15

|

According to information from the Telecommunications Authority (Ministry of Science and Technology), more than 93 million phone numbers have been authenticated by users.

A wake-up call for parents from the case of 18 teenagers causing trouble in Phu Tho

Tô Công |

The case of 18 teenagers carrying weapons causing trouble at night in Phu Tho being handled is a warning to parents in managing their children during the summer vacation.

Phu Tho mountainous commune invests 19.5 billion VND to renovate traffic roads

Tô Công |

Phu Tho - Trung Son mountainous commune invests 19.5 billion VND to renovate and upgrade the road from Dong Mang area to Bop area.

Transport infrastructure accelerates, unlocking growth momentum in Lao Cai

Đinh Đại |

Lao Cai - The completion of infrastructure not only helps connect areas, creates convenience for people to travel but also contributes to promoting economic development.