Hundreds of workers urgently accelerate the progress of the Cao Bo - Mai Son expressway

NGUYỄN TRƯỜNG |

Ninh Binh - Despite the cold weather, hundreds of workers are still working urgently at the construction site of the Cao Bo - Mai Son expressway expansion project.

The North-South Expressway expansion project in the East, Cao Bo - Mai Son section, is invested by the Ninh Binh Provincial Department of Construction. The project started in March 2025, and so far the contractors have completed excavation, paving and paving the roadbed, basically closing piles for the entire 9,800m. Of which, 640m has been paved with BR25 asphalt concrete and 120m paved with C19 asphalt concrete.

Cong nhan do betong mat cau vuot Khanh Hoa. Anh: Dieu Anh
Workers pouring concrete on the surface of Khanh Hoa overpass. Photo: Dieu Anh

For 5 bridges on the entire route, to date, the construction unit has basically completed the installation of beams, concreted the bridge surface, bridge railings and C19 asphalt concrete paving the bridge surface. The estimated implementation value is about 525/1,029 billion VND (reaching 51.0%).

Present at the construction site for the expansion of the Cao Bo - Mai Son Expressway Project on January 10, according to Lao Dong Newspaper reporters' records, despite the cold weather, hundreds of workers and machinery are working urgently to speed up the project progress.

May moc thiet bi thi cong phan nen duong, doan qua dia ban phuong Dong Hoa Lu. Anh: Dieu Anh
Machinery and equipment for constructing the roadbed section, passing through Dong Hoa Lu ward. Photo: Dieu Anh

Talking to Lao Dong Newspaper reporters, Mr. Do Huy Tuan - Deputy Director of the Construction Investment Project Management Board (under Ninh Binh Provincial Department of Construction) - said that contractors are currently mobilizing more than 300 workers and nearly 100 equipment and machinery to deploy 11 construction bridges on the entire route. It is expected that the project will be completed and put into operation in 2026.

Currently, construction teams are working overtime until 9 pm daily to speed up progress and shorten the project completion time. We are striving to complete the main route in June 2026" - Mr. Tuan said.

Cac cong nhan dang thi cong phan cong ngam. Anh: Dieu Anh
Workers are constructing and installing the underground sewer section. Photo: Dieu Anh

The Cao Bo - Mai Son expressway expansion project is invested in expanding 2 more lanes on the left side of the existing road, with a scale of 6 lanes, roadbed width of 32.25m; road surface width for vehicles is 22.5m; in addition, there is a median strip, emergency stopping strip and sidewalk. Design speed from 100 to 120km/h, according to expressway standard TCVN 5729-2012. The total investment of the Project is nearly 1,900 billion VND from the central budget. Up to now, the total capital allocated to the project is 1,200 billion VND.

Cac nha thau hien dang trien khai 11 mui thi cong tren toan tuyen cua Du an mo rong cao toc Cao Bo - Mai Son. Anh: Dieu Anh
Contractors are currently deploying 11 construction teams on the entire route of the Cao Bo - Mai Son expressway expansion project. Photo: Dieu Anh

After completion and commissioning, this road will contribute to improving exploitation capacity, meeting increasing transportation needs, reducing traffic accidents, and supporting the socio-economic development of Ninh Binh province.

At the same time, gradually complete the road network planning for the period 2021 - 2030, with a vision to 2050. Contributing to the implementation of the goals of Resolution 30-NQ/TW of the Politburo on socio-economic development, ensuring national defense and security in the Red River Delta region.

NGUYỄN TRƯỜNG
RELATED NEWS

Da Nang urgently builds houses for people in time for Tet

|

Da Nang - In the flood center commune of Ha Nha, the "Quang Trung Campaign" is entering the final sprint stage.

Rushing at the large construction site in the southernmost sea area of the Fatherland, Ca Mau Cape

|

Ca Mau - In the middle of the southern ocean of the Fatherland, the road connecting the mainland to Hon Khoai Island and the dual-use port project are being constructed at an urgent pace.

Preparing land to start construction of Ninh Binh - Hai Phong expressway

|

Ninh Binh - The province is focusing on directing the acceleration of site clearance progress to start the Ninh Binh - Hai Phong expressway project, the section passing through the province.

U23 Vietnam vs U23 Korea Preview in the 3rd place match of the AFC U23 Championship

|

Football prediction U23 Vietnam vs U23 Korea in the 3rd place match of the 2026 AFC U23 Championship taking place at 10:00 PM tonight (January 23).

U23 Vietnam players and the opportunity to join the national team

|

Some U23 Vietnam players have enough capacity and desire to try their hand at the national team after the 2026 AFC U23 Championship.

Focus on implementing three strategic breakthroughs, bringing Vinh Long to rapid and sustainable development

|

The 14th National Party Congress is a major political event of the country, deciding strategic issues for the future and destiny of the nation, unleashing all resources and development motivation. To help readers have a comprehensive and objective view of the contributions of the Vinh Long Provincial Party Committee Delegation at the Congress, as well as the solutions of the Provincial Party Committee in thoroughly grasping and effectively implementing the Resolution of the 14th Party Congress, reporters of Vinh Long Newspaper and Radio, Television interviewed comrade Tran Tri Quang - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee about the above content.

Comrade Ha Quoc Tri: shifting from "passive to proactive" inspection and supervision, not allowing serious violations to occur

|

Ladies and gentlemen! In the term of the 13th Party Congress, the work of inspection, supervision, and Party discipline has achieved many important results; focusing on inspecting party members and Party organizations when there are signs of violations, thereby detecting, rectifying and handling them promptly. However, according to assessments, inspection and supervision work is still passive (i.e., inspection and supervision are only carried out when there are signs of violations).

Ha Long canned food explains the destruction of more than 130 tons of diseased meat and temporary suspension of production

|

Ha Long canned goods said they have destroyed more than 130 tons of raw materials positive for the virus, not put into production, not supplied to the market.

Da Nang urgently builds houses for people in time for Tet

Nguyễn Linh - Trần Thi |

Da Nang - In the flood center commune of Ha Nha, the "Quang Trung Campaign" is entering the final sprint stage.

Rushing at the large construction site in the southernmost sea area of the Fatherland, Ca Mau Cape

NHẬT HỒ - VĂN ĐÔNG |

Ca Mau - In the middle of the southern ocean of the Fatherland, the road connecting the mainland to Hon Khoai Island and the dual-use port project are being constructed at an urgent pace.

Preparing land to start construction of Ninh Binh - Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - The province is focusing on directing the acceleration of site clearance progress to start the Ninh Binh - Hai Phong expressway project, the section passing through the province.