Hopefully, the site clearance milestone for the high-speed railway project will be handed over soon

TRẦN TUẤN |

The investor has not yet handed over the site clearance markers for the high-speed railway project, so the Ha Tinh functional sector is concerned about great pressure as time is getting faster.

On the afternoon of October 29, Mr. Le Anh Son - Deputy Director of the Ha Tinh Department of Construction - said that up to now, the investor has not yet handed over the site clearance (GPMB) markers for the North-South high-speed railway project through Ha Tinh, so the measurement, counting, price appraisal, and approval of compensation plans for the GPMB scope are not eligible for implementation.

Currently, localities are implementing site clearance tasks according to the preliminary boundary of the project's pre-feasibility study step.

"We hope that the investor will soon hand over the landmark on site to have a basis and basis to focus on implementing site clearance. Because late handover will be very stressful when the volume of site clearance is very large," said Mr. Son.

According to Mr. Son, with the proposal of Ha Tinh province to request the Ministry of Construction to adjust the route at some locations due to the relic site, spiritual works and a section overlapping with the North - South expressway, it has not yet received a response.

Mr. Son said that implementing site clearance when the route plan may still have many adjustments will pose a risk of having to adjust, causing waste of resources and affecting progress.

Therefore, it is necessary to have a decision as soon as possible from the competent authority to facilitate site clearance, so that the locality can feel secure and determined with this work.

According to the Ha Tinh Department of Construction, the high-speed railway project on the North-South axis passes through 18 communes and 5 wards of Ha Tinh province with a total length of about 103.42km.

According to the preliminary review results, up to now, the project is expected to reclaim about 764.12 hectares of land, affecting about 1,800 households with residential land. Of which, nearly 1,300 households had to be relocated and resettled.

The project also affects the power grid infrastructure along with many other works and technical infrastructure. The estimated cost of site clearance is about VND 8,462 billion.

It is expected that the whole province will have to build 35 resettlement areas in 18 communes and wards.

Up to now, only one resettlement area has been constructed, which is a resettlement area in Lien Vinh residential group, Ha Huy Tap ward.

Khu tai dinh cu dau tien dang thi cong o phuong Ha Huy Tap. Anh: Tran Tuan.
The first resettlement area is under construction in Ha Huy Tap ward. Photo: Tran Tuan.

With the remaining 34 resettlement areas, 30 areas have approved detailed planning/approved master plan, 4 areas are completing documents, and are about to approve planning.

TRẦN TUẤN
RELATED NEWS

Khanh Hoa needs VND 8,626 billion for site clearance for high-speed railway

|

Khanh Hoa needs to allocate VND 8,626 billion from the central budget to implement compensation and site clearance for the high-speed railway project

The North-South high-speed railway project through 2 communes in Dong Nai coincides with the heart of route 769E

|

Dong Nai - The People's Committees of wards and communes determined the number of households that had to be relocated and resettled for the high-speed railway project on the North-South axis.

Prioritize the maximum application of international standards for the North-South high-speed railway

|

It is expected that before October 30, the Ministry of Construction will issue 37 sets of ISO equivalent TCVN for the North-South high-speed railway project.

A thousand-ton train convoy withdraws from Bach Ho bridge as floods in Hue gradually recede

|

HUE - At 9:20 a.m. on October 30, the railway industry allowed the locomotive to withdraw from Bach Ho bridge after many days of "guarding" the water flow as the floodwaters of the Huong River were gradually receding.

Russian plane carries 29 tons of emergency relief goods for people in flooded areas of Hue

|

On the morning of October 30, at Noi Bai airport (Hanoi), a Russian private plane landed, carrying 29 tons of emergency aid to the people of Hue city

Accelerate waste-to-energy projects to end the situation of waste being left behind

|

Ninh Binh - With a large amount of waste remaining, causing environmental pollution, Ninh Binh province is directing to speed up the progress of waste treatment projects to end the above situation.

Forecast of the risk of 2-3 typhoons near the East Sea in November

|

The low pressure is forecast to strengthen into a storm in early November, and there may be 2-3 storms near the East Sea throughout the month.

Floodwaters have flooded, farmer's tractor has turned into a special rescue vehicle

|

Quang Tri - The whole commune was flooded with immense floodwaters, some families were flooded, some went to the hospital to need support, Mr. Phung was there. The tractor is often a means of livelihood, now becoming a special rescue vehicle when floods come.

Khanh Hoa needs VND 8,626 billion for site clearance for high-speed railway

Hữu Long |

Khanh Hoa needs to allocate VND 8,626 billion from the central budget to implement compensation and site clearance for the high-speed railway project

The North-South high-speed railway project through 2 communes in Dong Nai coincides with the heart of route 769E

HÀ ANH CHIẾN |

Dong Nai - The People's Committees of wards and communes determined the number of households that had to be relocated and resettled for the high-speed railway project on the North-South axis.

Prioritize the maximum application of international standards for the North-South high-speed railway

PHẠM ĐÔNG |

It is expected that before October 30, the Ministry of Construction will issue 37 sets of ISO equivalent TCVN for the North-South high-speed railway project.