Many expressway projects must be completed in 2025

Xuyên Đông |

The Government has just issued instructions on key transport projects, including expressway projects.

The completion of expressway projects is something that people are looking forward to. Recently, the Government Office issued Document No. 235/TB-VPCP dated May 17, 2025, announcing the conclusion of Prime Minister Pham Minh Chinh, Head of the Steering Committee at the 17th Session of the State Steering Committee for important national projects and works, key to the transport sector (Steering Committee).

In which, the Prime Minister directed that the task of the whole country having 3,000 km of expressway in 2025 is not to change.

Units must mobilize all resources, equipment, machinery, and apply modern technical solutions to complete expressway projects such as An Huu - Cao Lanh, Ho Chi Minh City Ring Road 3, Tuyen Quang - Ha Giang, Bien Hoa - Vung Tau, Dong Dang - Tra Linh, Huu Nghi - Chi Lang... in December 2025.

Regarding the procedures for preparing a number of projects, the Prime Minister requested that arising issues must be proactively handled by agencies and units according to their authority, promptly reported if they exceed their authority; resolutely not push them away to avoid them.

Public-private partnership projects must implement procedures to start construction in May 2025.

Investors continue to proactively mobilize all resources, equipment, and human resources to speed up the construction progress of projects... Assign the Ministry of Finance to continue studying and proposing amendments to the PPP Law and the Investment Law in the direction of simplifying/reducing procedures (including appraisal procedures of the State Appraisal Council/ Interdisciplinary Appraisal Council), attracting resources outside the state budget, attracting investors.

The Prime Minister assigned the State Bank of Vietnam to urgently deploy solutions to mobilize VND500,000 billion to invest in strategic infrastructure projects and science and technology, innovation and digital transformation.

Assign Deputy Prime Minister Ho Duc Phoc to direct the Ministry of Finance to allocate sufficient resources to implement investment in important infrastructure projects.

Regarding site clearance, the Prime Minister requested the provinces of Dong Nai, Khanh Hoa, Binh Duong, and Lang Son to seriously implement the Prime Minister's instructions, make further efforts and determination to hand over the entire remaining site of projects planned to be completed in 2025, in May 2025.

The provinces of Quang Tri, Quang Ngai, Binh Dinh, Khanh Hoa, Ninh Thuan, Binh Thuan, Dong Nai, Kien Giang urgently speed up the handover of land for rest stop projects on the North - South expressway in the East, to be completed no later than May 20, 2025.

The provinces of An Giang, Soc Trang, Hanoi, Hung Yen, Bac Ninh, Kien Giang, Bac Lieu, Thai Nguyen, Tuyen Quang, Tien Giang are determined to deploy site clearance and relocation of technical infrastructure to meet the progress of the Chau Doc - Can Tho - Soc Trang project, Ring Road 4 of Hanoi Capital Region, Ho Chi Minh Road.

The Prime Minister requested Tien Giang, Ben Tre, An Giang, and Soc Trang provinces to complete the remaining mine licensing procedures in May 2025 in accordance with the direction in Notice No. 203/TB-VPCP dated April 25, 2025.

An Giang reviews and urgently assigns direct contractors to the mines to proactively source materials to meet the project completion schedule.

Vinh Long, Tien Giang, and Ben Tre provinces consider increasing mine capacity to meet the 2025 demand of the Ho Chi Minh City Ring Road 3 project.

Dak Lak province completes procedures for approving the lease of Ea Kenh mine land and procedures for returning temporary waste dumps according to the instructions of the Ministry of Agriculture and Environment at the Khanh Hoa - Buon Ma Thuot project in May 2025.

The Ministry of Public Security investigates the supply of filling materials for key projects in the Southern region.

Xuyên Đông
TIN LIÊN QUAN

Mobilizing people to hand over the site of the expressway project through Dong Nai before enforcement

|

Dong Nai - On May 20, the authorities will enforce 12 households in Long Duc commune, Long Thanh district, and clear the land for the Bien Hoa - Vung Tau expressway.

Son La people eagerly wait for the start of construction of the Hoa Binh - Moc Chau expressway

|

The groundbreaking ceremony for the Hoa Binh - Moc Chau expressway section through Son La province took place on May 18, 2025, opening up new expectations for the development of the Northwest region.

Speeding up the construction progress of the Cao Lanh - An Huu Expressway

|

Dong Thap - Chairman of the Provincial People's Committee (PPC) Tran Tri Quang requested to speed up the construction progress of the Cao Lanh - An Huu expressway.

An Giang Provincial Party Secretary holds the position of Deputy Head of the Central Internal Affairs Commission

|

The Politburo transferred, assigned and appointed Mr. Le Hong Quang to hold the position of Deputy Head of the Central Internal Affairs Commission.

Heavy rain causes local congestion on many streets in Hanoi

|

Hanoi - Due to heavy rain on the evening of June 30, some streets in Hanoi experienced local congestion.

Mr. Tran Thanh Lam holds the position of Deputy Head of the Central Propaganda and Mass Mobilization Department

|

The Secretariat decided to transfer and appoint Mr. Tran Thanh Lam to the position of Deputy Head of the Central Propaganda and Mass Mobilization Department.

20h News: Ministry of Education and Training talks about marking high school graduation exams when merging provinces and cities

|

20h News on September 30: The marking of high school graduation exams is not affected by the merger of provinces and cities; Forecast of very heavy rain in the next 3 days...

Vietnam General Confederation of Labor offers incense to commemorate the late General Secretary Nguyen Van Linh

|

Hung Yen - On the afternoon of June 30, a working delegation of the Vietnam General Confederation of Labor led by Comrade Nguyen Dinh Khang - Member of the Party Central Committee, President of the Vietnam General Confederation of Labor offered incense to commemorate the late General Secretary Nguyen Van Linh at the memorial house in Nguyen Van Linh commune, Yen My district (Hung Yen).

Mobilizing people to hand over the site of the expressway project through Dong Nai before enforcement

HÀ ANH CHIẾN |

Dong Nai - On May 20, the authorities will enforce 12 households in Long Duc commune, Long Thanh district, and clear the land for the Bien Hoa - Vung Tau expressway.

Son La people eagerly wait for the start of construction of the Hoa Binh - Moc Chau expressway

Minh Nguyễn |

The groundbreaking ceremony for the Hoa Binh - Moc Chau expressway section through Son La province took place on May 18, 2025, opening up new expectations for the development of the Northwest region.

Speeding up the construction progress of the Cao Lanh - An Huu Expressway

Phong Linh |

Dong Thap - Chairman of the Provincial People's Committee (PPC) Tran Tri Quang requested to speed up the construction progress of the Cao Lanh - An Huu expressway.