The An Phu and My Thuy intersections will be completed in 2026, and the East of Ho Chi Minh City will soon reduce traffic congestion

MINH QUÂN |

HCMC - The An Phu and My Thuy intersection projects are preparing to complete many important items before reaching the finish line in 2026.

On December 11, the Ho Chi Minh City Department of Construction said it was focusing on coordinating with relevant units to speed up the progress of two major transport projects, the An Phu intersection and the My Thuy intersection.

The An Phu intersection started construction at the end of 2022, located at the eastern gateway of Ho Chi Minh City with a total investment of more than VND 3,400 billion. According to the plan, the project must be completed in December 2025 but is currently behind schedule compared to the set target.

The leaders of the Ho Chi Minh City People's Committee and the Department of Construction have held many meetings to inspect the site, direct the investor to handle problems and speed up construction.

To date, some important items such as Ba Dat Bridge, Giong Ong To Bridge and HC1-01 underpass (through Mai Chi Tho - Dong Van Cong intersection) have been basically completed and put into use.

Nhanh cau N2 du kien hoan thanh truoc 31.12.2025. Anh: Anh Tu
The N2 bridge branch is expected to be completed before December 31, 2025. Photo: Anh Tu

The N2 bridge branch (right from the Ho Chi Minh City - Long Thanh expressway to Mai Chi Tho street) is expected to be completed before December 31, 2025.

The HC1-02 underpass connecting directly to the expressway with Mai Chi Tho Street (towards the Saigon River tunnel) will be completed before February 17, 2026.

Branches N3, N4 and bridges N1.1, N1.3 (left from Mai Chi Tho Street to the expressway) are expected to be completed before April 30, 2026.

The entire An Phu intersection is expected to be completed in 2026.

Toan canh du an nut giao My Thuy.  Anh: Anh Tu
Overview of the My Thuy intersection project. Photo: Anh Tu

With My Thuy intersection, the Ho Chi Minh City Department of Construction said that the investor is also mobilizing maximum human resources and equipment to keep up with the progress after many years of construction.

The right turn from Dong Van Cong Street to Vo Chi Cong and from Dong Van Cong Street to Nguyen Thi Dinh Street are expected to be completed before January 31, 2026.

The remaining branches and Ky Ha 4 bridge will be completed in February 2026. The entire project will be completed in 2026.

The My Thuy intersection project started in 2016, including two component projects: construction and installation with a cost of VND 1,826 billion and compensation and site clearance of more than VND 1,623 billion.

After nearly 10 years of implementation, the project has just completed some items such as Ky Ha 3 bridge, Ring Road 2 overpass, left underpass from Ring Road 2 to Cat Lai and My Thuy 3 bridge.

MINH QUÂN
RELATED NEWS

The largest complex intersection in the east of Ho Chi Minh City is gradually taking shape after more than 9 months of construction

|

HCMC - After more than 9 months of construction in phase 3, My Thuy intersection is gradually taking shape, aiming to be put into operation in 2026.

The An Phu intersection must be completed immediately, it is already too congested!

|

After the press's reflection on the delay of the An Phu intersection project (HCMC), in mid-November, the construction site became bustling again.

The overpass and underpass at An Phu intersection are sprinting to complete by the end of the year

|

HCMC - In mid-November, the An Phu intersection construction site was bustling, the overpass and underpass items simultaneously accelerated, gradually taking shape.

U23 Vietnam vs U23 Korea Preview in the 3rd place match of the AFC U23 Championship

|

Football prediction U23 Vietnam vs U23 Korea in the 3rd place match of the 2026 AFC U23 Championship taking place at 10:00 PM tonight (January 23).

U23 Vietnam players and the opportunity to join the national team

|

Some U23 Vietnam players have enough capacity and desire to try their hand at the national team after the 2026 AFC U23 Championship.

Focus on implementing three strategic breakthroughs, bringing Vinh Long to rapid and sustainable development

|

The 14th National Party Congress is a major political event of the country, deciding strategic issues for the future and destiny of the nation, unleashing all resources and development motivation. To help readers have a comprehensive and objective view of the contributions of the Vinh Long Provincial Party Committee Delegation at the Congress, as well as the solutions of the Provincial Party Committee in thoroughly grasping and effectively implementing the Resolution of the 14th Party Congress, reporters of Vinh Long Newspaper and Radio, Television interviewed comrade Tran Tri Quang - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee about the above content.

Comrade Ha Quoc Tri: shifting from "passive to proactive" inspection and supervision, not allowing serious violations to occur

|

Ladies and gentlemen! In the term of the 13th Party Congress, the work of inspection, supervision, and Party discipline has achieved many important results; focusing on inspecting party members and Party organizations when there are signs of violations, thereby detecting, rectifying and handling them promptly. However, according to assessments, inspection and supervision work is still passive (i.e., inspection and supervision are only carried out when there are signs of violations).

Ha Long canned food explains the destruction of more than 130 tons of diseased meat and temporary suspension of production

|

Ha Long canned goods said they have destroyed more than 130 tons of raw materials positive for the virus, not put into production, not supplied to the market.

The largest complex intersection in the east of Ho Chi Minh City is gradually taking shape after more than 9 months of construction

Tâm Tú |

HCMC - After more than 9 months of construction in phase 3, My Thuy intersection is gradually taking shape, aiming to be put into operation in 2026.

The An Phu intersection must be completed immediately, it is already too congested!

Lê Thanh Phong |

After the press's reflection on the delay of the An Phu intersection project (HCMC), in mid-November, the construction site became bustling again.

The overpass and underpass at An Phu intersection are sprinting to complete by the end of the year

Anh Tú |

HCMC - In mid-November, the An Phu intersection construction site was bustling, the overpass and underpass items simultaneously accelerated, gradually taking shape.