On November 6, information from the People's Committee of Bac Ninh province said that according to the plan, the organization of the first phase of advance payment for compensation and site clearance support (GPMB) to implement the Gia Binh International Airport project and related projects in Luong Tai commune will be implemented from November 4 to 12 in 20 villages, with an area of 313.54 hectares of 2,425 households with a total amount of VND 1,383 billion.
Payment location at the village cultural house, from 8:00 to 11:30 and from 13:30 until all households come to receive money.
The force participating in the advance payment includes representatives of the Commune People's Committee, investors; officers and employees of the Provincial Land Fund Development Center and branches...
At payment points, people are guided by the relevant authorities to carry out procedures and processes for receiving money; payment activities take place conveniently, quickly and safely.
Yesterday (November 5), Luong Tai commune organized an advance payment for compensation and support for site clearance in 3 villages of Phuong Moi, Phu Tren, Tam Son, with an area of over 48 hectares of 376 households, with a total cost of about 214 billion VND.
Previously, on November 4, Luong Tai commune also paid an advance payment for compensation and support for site clearance in 3 villages of Van Trong, Bai Giang, Lang Khe with 251 households, area of nearly 30 hectares, costing more than 128 billion VND.
The Gia Binh International Airport project has a total area of about 1,959.9 hectares (including 124.7 hectares of phase 1), of which Gia Binh commune has about 888.7 hectares; Nhan Thang has about 17.2 hectares; Luong Tai has about 1,012.7 hectares; Lam Thao has about 41.3 hectares.
According to Plan No. 57 issued by the People's Committee of Bac Ninh province on September 5, 2025, units and localities must complete site clearance for the entire agricultural land area (1,2655.1 ha) of the project before October 30, 2025.
About 40 km from Hanoi, the Gia Binh International Airport project (Bac Ninh) started construction in December 2024.
According to the plan, the airport will be basically completed and initially put into operation from the end of 2026 to serve the 2027 APEC Summit.
By 2050, the airport's capacity will reach about 50 million passengers/year and 2.5 million tons of cargo/year.