According to the People's Committee of Bac Ninh province, the development and promulgation of the Plan is necessary to strictly implement the instructions of the Central Government and the Government and specify Resolution No. 28-NQ/TU dated August 19, 2025 of the Executive Committee of the Bac Ninh Provincial Party Committee.
The plan will specify tasks, clearly assign responsibilities and progress for each work item, ensuring timely, synchronous, public, transparent and effective project implementation...
The plan clearly states the progress of BT projects:
1. Appraisal and approval of the urban subdivision planning south of Duong River, Urban Subdivision 1, 2: Complete before September 20, 2025.
2. Appraisal and approval of detailed planning for resettlement areas and cemeteries: Complete before September 25, 2025.
3. Approving environmental impact assessment: Complete before September 25, 2025.
4. approve the project and approve the investor: Complete before September 30, 2025.
5. Signing a BT project contract: Complete before October 5, 2025.
6. Organize the preparation, appraisal, and approval of construction drawing designs and estimates (can approve each part to ensure construction progress of projects): Complete before November 1, 2025.
7. The resettlement project to serve Gia Binh International Airport and the Investment and Construction Project to serve the site clearance of Gia Binh International Airport will be completed before June 30, 2026.
Investment project to build a road directly connecting Gia Binh International Airport: Complete before December 31, 2026.
Regarding the progress of compensation and site clearance for the Gia Binh International Airport Construction Investment Project and BT projects, the plan also clearly states that the site clearance for the entire agricultural land area of the projects will be completed within 2 months: Completed before October 30, 2025.
Complete site clearance for the entire non-agricultural land area of the projects: Complete before February 20, 2026.
Bac Ninh province aims to put Gia Binh International Airport and related routes into operation in 2026.

About 40 km from Hanoi, Gia Binh International Airport (Bac Ninh) started construction in December 2024 with a total area of nearly 1,900 hectares.
According to the plan, the airport will be basically completed and initially put into operation from the end of 2026 to serve the 2027 APEC Summit.
By 2050, the airport's capacity will reach about 50 million passengers/year and 2.5 million tons of cargo/year.