Timelines for the implementation of Gia Binh International Airport

Vân Trường |

Bac Ninh - The Provincial People's Committee issued an official dispatch on the implementation of the Gia Binh International Airport Construction Investment Project and related projects.

According to the People's Committee of Bac Ninh province, the development and promulgation of the Plan is necessary to strictly implement the instructions of the Central Government and the Government and specify Resolution No. 28-NQ/TU dated August 19, 2025 of the Executive Committee of the Bac Ninh Provincial Party Committee.

The plan will specify tasks, clearly assign responsibilities and progress for each work item, ensuring timely, synchronous, public, transparent and effective project implementation...

The plan clearly states the progress of BT projects:

1. Appraisal and approval of the urban subdivision planning south of Duong River, Urban Subdivision 1, 2: Complete before September 20, 2025.

2. Appraisal and approval of detailed planning for resettlement areas and cemeteries: Complete before September 25, 2025.

3. Approving environmental impact assessment: Complete before September 25, 2025.

4. approve the project and approve the investor: Complete before September 30, 2025.

5. Signing a BT project contract: Complete before October 5, 2025.

6. Organize the preparation, appraisal, and approval of construction drawing designs and estimates (can approve each part to ensure construction progress of projects): Complete before November 1, 2025.

7. The resettlement project to serve Gia Binh International Airport and the Investment and Construction Project to serve the site clearance of Gia Binh International Airport will be completed before June 30, 2026.

Investment project to build a road directly connecting Gia Binh International Airport: Complete before December 31, 2026.

Regarding the progress of compensation and site clearance for the Gia Binh International Airport Construction Investment Project and BT projects, the plan also clearly states that the site clearance for the entire agricultural land area of the projects will be completed within 2 months: Completed before October 30, 2025.

Complete site clearance for the entire non-agricultural land area of the projects: Complete before February 20, 2026.

Bac Ninh province aims to put Gia Binh International Airport and related routes into operation in 2026.

Phoi canh san bay Gia Binh (Bac Ninh). Anh: VGP
Perspective of Gia Binh airport (Bac Ninh). Photo: VGP

About 40 km from Hanoi, Gia Binh International Airport (Bac Ninh) started construction in December 2024 with a total area of nearly 1,900 hectares.

According to the plan, the airport will be basically completed and initially put into operation from the end of 2026 to serve the 2027 APEC Summit.

By 2050, the airport's capacity will reach about 50 million passengers/year and 2.5 million tons of cargo/year.

Vân Trường
RELATED NEWS

Peak of site clearance for Gia Binh International Airport project

|

Bac Ninh - The peak period in the next 1.5 months will be to pay compensation to people subject to land acquisition to serve the Gia Binh International Airport project.

Standing team 24/24 deploys Gia Binh International Airport project

|

Bac Ninh - The locality established a 24/7 Standing Group to implement the Gia Binh International Airport Project and related projects.

Planning the airport urban area near Gia Binh International Airport

|

Bac Ninh - Nam Song Duong is positioned as a multi-functional airport urban area of international stature.

Accident on Phap Van - Cau Gie Expressway, limousine overturned, deformed

|

Ninh Binh - The accident on the Phap Van - Cau Gie Expressway caused the limousine to overturn and deform.

Viet Long Company announces will continue to exploit stone, despite objections

|

Lao Cai - Viet Long Company has just issued a document announcing that it will continue to exploit stone at Lieu Do 2 mine, although it has not reached an agreement with the people.

The Ministry of Education and Training proposes to teach Cambodian, Thai, and Indonesian languages to high school students

|

The Ministry of Education and Training proposes that from 2026, Vietnam will start teaching Lao, Cambodian, Thai, and Indonesian in schools in need.

Russian Minister of Health directly rescues passengers on a flight to Vietnam

|

Russian Health Minister Mikhail Murashko was praised for his timely actions to rescue a passenger while the plane was flying from Moscow to Hanoi.

Ms. Van Thi Bach Tuyet appointed as Deputy Secretary of the Ho Chi Minh City Party Committee

|

Ho Chi Minh City - Ms. Van Thi Bach Tuyet - Head of the Ho Chi Minh City Party Committee's Organization Committee was appointed by the Politburo as Deputy Secretary of the Ho Chi Minh City Party Committee.

Peak of site clearance for Gia Binh International Airport project

Vân Trường |

Bac Ninh - The peak period in the next 1.5 months will be to pay compensation to people subject to land acquisition to serve the Gia Binh International Airport project.

Standing team 24/24 deploys Gia Binh International Airport project

Vân Trường |

Bac Ninh - The locality established a 24/7 Standing Group to implement the Gia Binh International Airport Project and related projects.

Planning the airport urban area near Gia Binh International Airport

Trần Tuấn |

Bac Ninh - Nam Song Duong is positioned as a multi-functional airport urban area of international stature.