The storm has passed, Ca Mau no longer has showers, the weather is dry and sunny, the construction units are working busily.
At the end of the expressway, the section passing through Ho Thi Ky commune, the team of engineers and workers worked hard day and night to complete the remaining work soon. In particular, the asphalt paving process is being urgently implemented, taking advantage of time as well as favorable weather conditions in the situation of erratic sunshine at the end of the year.
The contractors mobilized all their capacity in terms of human resources, vehicles, equipment, and machinery to race against time, speeding up construction day and night on the project, with the goal of completing the progress according to instructions.
The unit has mobilized all human resources, means, and finance to ensure overtime and increase shifts. We divided into 3 shifts, starting from 2am to 10am to carry out the work on schedule, said a construction worker.
Together with the contractor and the construction unit, the supervision consulting units are determined to stay at the construction site so that the coordination work is smooth, according to the overtime schedule of the bidding packages.
The current heavy rain is a major obstacle for construction, but with the spirit of overcoming difficulties, construction units have proactively adjusted the plan to ensure both quick construction and quality of the project.
At this time in Ca Mau area, it often rains heavily in the afternoon, so the construction units avoid rain appropriately to complete the project in time.
Can Tho - Ca Mau Expressway started construction on January 1, 2023, more than 110 km long, passing through 5 provinces and cities (old): Can Tho, Hau Giang, Bac Lieu, Kien Giang, Ca Mau, starting point of the project at IC2 intersection (intersection to National Highway 91 - Nam Song Hau, Can Tho City); end point connecting the Ca Mau City bypass. The expressway has a total investment of more than VND 27,500 billion, divided into 2 component projects: Can Tho - Hau Giang (37 km), Hau Giang - Ca Mau (73 km).
In Ca Mau province alone, the expressway is 21.9 km long (the starting point is adjacent to Kien Giang (old) and the end point is connected to Xuyen A road, Thoi Binh commune, Ca Mau) and 16.6 km connecting to National Highway 1 in Thanh Phu commune, Ca Mau province.
This expressway is expected to be completed by the end of 2025.