Construction in 3 shifts to open the billion-dollar expressway in Tuyen Quang on December 19

Việt Bắc |

Tuyen Quang - Contractors are speeding up construction, striving to open the Tuyen Quang - Ha Giang expressway to traffic on December 19.

On December 3, Permanent Vice Chairman of Tuyen Quang Provincial People's Committee Nguyen Manh Tuan chaired a meeting to assess the situation and progress of the Tuyen Quang - Ha Giang Expressway Project (phase 1) through Tuyen Quang province.

Accordingly, the project through Tuyen Quang province, 77 km long, is worth VND 8,800 billion. Up to now, the site clearance work has been completed and handed over to the construction unit 100%. Currently, 6/7 construction packages for the road and bridge sections on the route are being implemented. All 6 construction packages have deployed more than 114 construction teams with 1,058 equipment and 1,100 human resources.

Reporting at the meeting, contractors and construction units affirmed that up to now, problems with site clearance and construction materials have been basically resolved. However, the overall progress has not met the set plan due to many objective factors. The units are urging the organization of 3 shifts and 4 teams, striving to open to traffic before December 19.

At the meeting, Permanent Vice Chairman of the Provincial People's Committee Nguyen Manh Tuan requested departments, branches, investors, and contractors to continue to make the highest efforts for the set goals. At the same time, carefully prepare for the expressway opening ceremony on December 19 according to the direction of the Prime Minister.

Việt Bắc
RELATED NEWS

Proposal to spend VND23,940 billion to build Vinh - Thanh Thuy expressway, 60km long

|

The Government proposes three specific mechanisms to invest in the construction of the Vinh - Thanh Thuy expressway, 60km long, with a total investment of VND 23,940.34 billion, with a scale of 4 lanes.

Son Hai Group wins bid for Tan Phu - Bao Loc Expressway Project worth VND14,475 billion

|

Bao Loc - Son Hai Group Company Limited is the winning bidder for the Tan Phu (Dong Nai) - Bao Loc (Lam Dong) expressway construction project.

More than 2,000 workers race overnight on the Can Tho - Ca Mau expressway project

|

Can Tho - 2,100 workers and 1,150 machines are racing to complete the 110 km expressway before the opening date of December 19, 2025

Hanoi is seriously polluted this morning, AQI is simultaneously at the purple threshold

|

Hanoi - This morning (December 10), air quality in Hanoi is at the purple threshold - very poor. AQI at 7:30 is 225.

Assets increase sharply, billionaire Pham Nhat Vuong firmly holds the second richest position in Southeast Asia

|

With assets increasing by 2.8 billion USD, Mr. Pham Nhat Vuong, Chairman of Vingroup Corporation, rose to 2nd place in the list of the richest people in Southeast Asia.

Bai Vot - Ham Nghi Expressway has been opened to traffic, the connecting road in Ha Tinh is still not completed

|

Ha Tinh - The connecting road and the parallel road with the Bai Vot - Ham Nghi expressway section have not been handed over, affecting traffic.

Young people in the cancer spinout

|

Increasingly young cancer causes many young people to face the same worries about illness, treatment costs and disruptions in studying, work, and the future.

Three scenarios that can change world gold prices in 2026

|

Gold prices still have room to increase next year, according to many experts.

Proposal to spend VND23,940 billion to build Vinh - Thanh Thuy expressway, 60km long

PHẠM ĐÔNG |

The Government proposes three specific mechanisms to invest in the construction of the Vinh - Thanh Thuy expressway, 60km long, with a total investment of VND 23,940.34 billion, with a scale of 4 lanes.

Son Hai Group wins bid for Tan Phu - Bao Loc Expressway Project worth VND14,475 billion

Phúc Khánh - Phan Tuấn |

Bao Loc - Son Hai Group Company Limited is the winning bidder for the Tan Phu (Dong Nai) - Bao Loc (Lam Dong) expressway construction project.

More than 2,000 workers race overnight on the Can Tho - Ca Mau expressway project

Tạ Quang |

Can Tho - 2,100 workers and 1,150 machines are racing to complete the 110 km expressway before the opening date of December 19, 2025