Technical opening of Gianh and Quan Hau bridges on National Highway 1 in Quang Tri

CÔNG SÁNG |

Quang Tri - National Highway 1 technically opens to traffic Gianh and Quan Hau bridges to soon complete the package to expand key bridges.

On the afternoon of December 31, representatives of the investor and the construction unit organized the technical opening of the Gianh bridge and Quan Hau bridge expansion package under the project to upgrade and expand some bridges and tunnels on National Highway 1 section passing through Quang Tri province.

The package to expand Gianh bridge and Quan Hau bridge was started in February 2025, with an expected construction time of 18 months. However, due to the urgency of the project, along with the drastic direction of the investor, the Railway Project Management Board (Ministry of Construction) and the efforts of the construction unit, Dat Phuong Group Joint Stock Company, by December 31, the package was completed according to the committed schedule and technically opened to traffic.

Representatives of the investor said that to ensure progress, the contractor has organized "3 shifts, 4 teams" construction, overcome difficulties due to weather conditions, and focused manpower and machinery so that the project reaches the planned target. After completing traffic safety items and auxiliary works, the project is expected to be put into operation in January 2026.

When completed, the project will contribute to reducing the load on the two existing bridges that often experience traffic jams when there are traffic incidents, overcoming bottlenecks on National Highway 1, thereby promoting socio-economic development and ensuring national defense and security of the locality.

CÔNG SÁNG
RELATED NEWS

Prime Minister requests technical opening of Chau Doc-Can Tho-Soc Trang expressway on June 30

|

Can Tho - Inspecting the component project of the Chau Doc-Can Tho-Soc Trang expressway, the Prime Minister requested that the project be technically opened to traffic by June 30.

Deo Ngang tunnel is basically completed, preparing for technical traffic opening

|

Ha Tinh - The Deo Ngang tunnel project has completed the tunnel surface, and construction units are speeding up the drainage phase.

Construction of drainage to open the Deo Ngang tunnel for technical traffic

|

Ha Tinh - These days, contractors are focusing on the construction of the water receding phase to promptly open the Deo Ngang tunnel connecting Ha Tinh with Quang Tri.

Metro Line 1 in Ho Chi Minh City runs all night, free tickets to welcome New Year's Day

|

Ho Chi Minh City - Metro Line 1 increases trips, running overnight on December 31st and free tickets on January 1st, 2026 to serve people celebrating the New Year 2026.

Parking a motorbike for Countdown is quoted as a price of 100,000 VND

|

Hanoi - A sea of people flocking to Hoan Kiem Lake area to welcome Countdown 2026 makes parking areas crowded, in some places asking for prices up to hundreds of thousands of dong.

9th Hour: The price of choice - Part 1

|

9th hour number 183 - A boring marriage suddenly erupts when the husband demands a divorce. Finding clues behind it, how will the wife handle it when the truth is exposed?

Business ecosystem of the director of the program "Come here, four birds of the sky

|

The director of the program "Come here, four birds of the sky" is representing and participating in operating the business ecosystem operating in the entertainment and training fields.

The truth about the school recovering teachers' bonuses in Ninh Binh

|

Ninh Binh - Ha Nam Vocational College admitted to collecting a portion of the bonus money from officials and teachers, but that is a non-compulsory donation campaign.

Prime Minister requests technical opening of Chau Doc-Can Tho-Soc Trang expressway on June 30

TẠ QUANG |

Can Tho - Inspecting the component project of the Chau Doc-Can Tho-Soc Trang expressway, the Prime Minister requested that the project be technically opened to traffic by June 30.

Deo Ngang tunnel is basically completed, preparing for technical traffic opening

TRẦN TUẤN - NGUYỄN LUÂN |

Ha Tinh - The Deo Ngang tunnel project has completed the tunnel surface, and construction units are speeding up the drainage phase.

Construction of drainage to open the Deo Ngang tunnel for technical traffic

TRẦN TUẤN |

Ha Tinh - These days, contractors are focusing on the construction of the water receding phase to promptly open the Deo Ngang tunnel connecting Ha Tinh with Quang Tri.