The Binh Goi bridge project across the Saigon River belongs to the construction package of 4 Ho Chi Minh City Ring Road 3 projects, previously through Binh Duong.
This project has a total investment of nearly 600 billion VND, and construction started in October 2023. Binh Goi Bridge is 1km long, with a scale of 4 lanes, and the speed limit is designed according to the highway standards of 100km/h. At the end of June 2025, the investor and the units organized the bridge closure.
According to the report of the Binh Duong Traffic Construction Investment Project Management Board, the construction progress has reached over 74.4% of the contract volume (423.9/569.3 billion VND).
Currently, 210/218 bored piles have been built (reaching 96.3%), the piers have reached 20/22 pillars, 14/22 bridge spans have been assembled, and 8/20 spans have been built.
Currently, the contractor is sandblasting the M1 abutment road and the service road. For the M2 abutment approach road, CDM deposit drilling is being conducted.
According to the assessment, this is one of the projects with the fastest progress in the Ho Chi Minh City Ring Road 3 project, through Binh Duong before. The project is striving to speed up the progress to be able to open to technical traffic on December 31, 2025.