Hundreds of billions of VND road stalled due to an unconstructed bridge span

QUÁCH DU |

Thanh Hoa - The traffic route with a total investment of more than 440 billion VND has stalled due to a bridge span that has not been able to be constructed for many months.

In March 2023, the road project connecting provincial road 504 to Tho Xuan - Nghi Son road, Thanh Hoa province was approved by Thanh Hoa Provincial People's Committee, with a total investment of more than 440 billion VND. The project is expected to be completed by the end of 2026.

Cầu vượt đường sắt Bắc - Nam (ở xã Thắng Lợi) thuộc dự án tuyến đường nối từ đường tỉnh 504 đến đường Thọ Xuân - Nghi Sơn, tỉnh Thanh Hóa còn thiếu 1 nhịp chính. Ảnh: Quách Du
The North-South railway overpass (in Thang Loi commune) belonging to the project of the road connecting provincial road 504 to Tho Xuan - Nghi Son road, Thanh Hoa province still lacks 1 main span. Photo: Quach Du

The project has a total length of nearly 6km, meeting the standard of a level III delta road, with a design speed of 80km/h. According to the design documents, the entire route has 2 bridges including the Yen River overpass and the railway overpass in Thang Loi commune.

After completion, the project is expected to form a traffic axis connecting the two old Nong Cong and Quang Xuong districts with National Highway 1A, creating motivation to promote local socio-economic development.

Representatives of the Thanh Hoa Civil and Industrial Construction Investment Project Management Board said that after 3 years of construction, the project has completed about 75% of the volume.

Real-world records at the project show that the road has basically completed the foundation and road surface. However, the 2 bridges on the route are still under slow construction, and some items are interrupted.

Do vướng hệ thống thông tin tín hiệu đường sắt, chưa được giải phóng mặt bằng khiến một nhịp cầu chưa thể thi công trong nhiều tháng. Ảnh: Quách Du
Due to problems with the railway signal information system, the site has not been cleared, causing one bridge span to be unable to be constructed for many months. Photo: Quach Du

In particular, the North-South railway overpass in Thang Loi commune has a total of 10 spans, with a length of more than 330m. Currently, the bridge only lacks one main span across the railway line, but this item has been suspended for many months.

According to a representative of the Thanh Hoa Civil and Industrial Construction Investment Project Management Board, the reason why the main span of the bridge had to stop construction is due to railway signal information system problems, which has not been cleared.

Recorded at the scene, due to prolonged construction suspension, the steel system in the bridge area has appeared rusty.

Representatives of the investor said that the unit is coordinating with the Vietnam Railways Authority, People's Committees of Thang Loi and Quang Ngoc communes to complete site clearance and soon deploy the construction of the remaining bridge span. It is expected that by the end of this year, the project will be completed, handed over and put into use.

QUÁCH DU
RELATED NEWS

Building a hundred-billion-VND road connecting the expressway to the central ward of Northern Thai Nguyen

|

Thai Nguyen - The road connecting the CT. 07 expressway to Bac Kan ward has a total investment of 775 billion VND.

Many roads in Ha Long are dug up in disarray

|

15 renovation projects in the old Ha Long City, Quang Ninh province are being constructed scattered, delayed, causing roads to be messy, affecting people's lives.

Nearly 1,500 billion VND road connecting Ho Chi Minh City - Tay Ninh is about to reach the finish line

|

Ho Chi Minh City - The National Highway 50 expansion project connecting Ho Chi Minh City with Tay Ninh is entering the completion phase, reaching more than 90% of the progress, and is expected to complete the entire route in the third quarter.

Accident between 2 trucks on highway through Ha Tinh, 2 people died

|

Ha Tinh - On the Bai Vot - Ham Nghi expressway, a traffic accident occurred between 2 trucks, killing 2 people, injuring 1 person and trapping them in the cabin.

8.2 magnitude strong earthquake in the Philippines, tsunami risk

|

A magnitude 8.2 earthquake occurred in Mindanao, Philippines on the morning of June 8.

EVN speaks out about sudden profits and 152.443 billion VND deposited in banks

|

Although the parent company - EVN recorded after-tax profit of nearly 39. 762 billion VND in 2025, Vietnam Electricity Group (EVN) still had accumulated losses of 5.611 billion VND.

Government requests absolutely no shortage of electricity and gasoline in all situations

|

The Government requests to effectively organize the implementation of solutions to ensure sufficient electricity and gasoline supply, especially during peak hot and dry season months.

Goal video Song Lam Nghe An - PVF-CAND (1-3)

|

PVF-CAND Club beat Song Lam Nghe An 3-1. Watch LPBank V.League 1-2025/26 live & watch on FPT Play, at https://fptplay.vn.

Building a hundred-billion-VND road connecting the expressway to the central ward of Northern Thai Nguyen

Việt Bắc |

Thai Nguyen - The road connecting the CT. 07 expressway to Bac Kan ward has a total investment of 775 billion VND.

Many roads in Ha Long are dug up in disarray

Nguyễn Hùng |

15 renovation projects in the old Ha Long City, Quang Ninh province are being constructed scattered, delayed, causing roads to be messy, affecting people's lives.

Nearly 1,500 billion VND road connecting Ho Chi Minh City - Tay Ninh is about to reach the finish line

Minh Tâm |

Ho Chi Minh City - The National Highway 50 expansion project connecting Ho Chi Minh City with Tay Ninh is entering the completion phase, reaching more than 90% of the progress, and is expected to complete the entire route in the third quarter.