Encountering site clearance, nearly 200 billion VND railway overpass project faces progress pressure

NGUYỄN LUÂN |

Quang Tri - Many locations are still facing site clearance issues, causing the Dong Hoi City Central Railway Road and Overpass project to face pressure to accelerate to be completed in time.

Slow site clearance

The Dong Hoi City Central Railway Road and Overpass project is located in the old Bac Ly and Nam Ly wards, now Dong Hoi and Dong Thuan wards (Quang Tri province). The project is invested by the Provincial Department of Construction and assigned to the Traffic Construction Investment Project Management Board under the Department of Construction for management.

The project includes 2 bidding packages for road and bridge construction with a total length of 2.2km, with an initial total investment of 160 billion VND, expected to be completed in 2025. However, site clearance work faces many difficulties and obstacles. In November 2025, the project was adjusted to increase capital to 193.5 billion VND, extending the completion deadline to the third quarter of 2026.

The project is expected to solve traffic congestion in the urban center area, and at the same time create motivation for the development of urban space in the East and West of the North-South railway line. However, after more than 3 years of implementation, the project has not yet been completed according to the initial plan due to prolonged problems in compensation, support and site clearance.

Đoạn phía phường Đồng Thuận chưa thể thi công đường dẫn lên cầu do chậm giải phóng mặt bằng. Ảnh: Nguyễn Luân
The section in Dong Thuan ward cannot construct the access road to the bridge due to slow site clearance. Photo: Nguyen Luan

According to the Traffic Construction Investment Project Management Board, the bridge section is basically completed, and the contractor is deploying the construction of access roads to the bridge. For the road section package, the longitudinal and horizontal drainage culvert systems have been basically completed, and construction units are focusing on treating the roadbed and foundation at locations where the site has been handed over.

The total value of construction and installation carried out to date reached more than 70 billion VND out of a total contract value of about 94.5 billion VND, equivalent to 74% of the volume.

Phần cầu vượt đường sắt đã cơ bản hoàn thiện, chờ đường dẫn. Ảnh: Nguyễn Luân
The railway overpass has been basically completed, waiting for the access road. Photo: Nguyen Luan

Talking to Lao Dong Newspaper, Mr. Luong Son Bao - Head of Project Management Department 2, Traffic Construction Investment Project Management Board under Quang Tri Provincial Department of Construction said that thanks to the close coordination between departments, branches and localities, many site bottlenecks on the route have been removed.

At the handed-over locations, the investor is requesting contractors to mobilize maximum manpower and equipment to accelerate construction. However, on the entire route, there are still some locations facing local site clearance issues.

It is proposed that localities and relevant units continue to focus on thoroughly removing existing problems in June so that investors can complete the project in September" - Mr. Bao said.

Resolutely hold responsible units for delays

Faced with the risk of affecting the project progress, the People's Committee of Quang Tri province has repeatedly requested localities and relevant units to mobilize the entire political system to get involved to thoroughly handle the obstacles.

According to the latest report of the Provincial Land Fund Development Center, compensation, support and site clearance are being accelerated throughout the route. In Dong Hoi ward, the auxiliary fence area of the Provincial General Hospital is completing the compensation plan according to the appraisal opinions of specialized agencies. In the hospital collective housing area alone, there are 8 affected households, so far 4 households have been approved for compensation plans, and the remaining 4 households are being reviewed and handled for recommendations to complete dossiers.

Máy móc, công nhân được huy động tối đa để tăng tốc thi công dự án. Ảnh: Nguyễn Luân
Machinery and workers are mobilized to the maximum to accelerate the project construction. Photo: Nguyen Luan

In Dong Thuan ward, the locality has approved compensation plans for 21 cases of consensus. For cases where plans have not been agreed upon, the local government continues to organize dialogues, mobilize and coordinate with specialized agencies to resolve people's petitions.

According to Dong Thuan Ward People's Committee, some cases that have been stuck for many years have had positive changes. However, there are still shortcomings that have not been resolved. Up to now, the locality is still waiting for land price plans from specialized units to serve as a basis for preparing compensation plans according to regulations.

In order to ensure the project is completed on time as extended, the People's Committee of Quang Tri province has requested localities, land clearance consulting units and relevant agencies to absolutely not delay land clearance work.

Công tác xây lắp cống thoát nước dưới chân cầu đang được triển khai. Ảnh: Nguyễn Luân
Construction of drainage culverts under the bridge is being implemented. Photo: Nguyen Luan

The Provincial People's Committee also requested the Chairmen of the People's Committees of Dong Hoi and Dong Thuan wards, the Director of the Provincial Land Fund Development Center, and related organizations and individuals to be responsible to the Provincial People's Committee if there is a situation of slow site clearance, leading to projects not being completed on schedule, causing waste of public investment capital.

With not much time left, definitively handling the final bottlenecks in land is being considered a decisive factor for the Dong Hoi central railway overpass project to reach the finish line in the third quarter of 2026 as targeted.

NGUYỄN LUÂN
RELATED NEWS

3,500 billion VND transportation project in Quang Ngai entangled with site clearance

|

Quang Ngai - The Hoang Sa - Doc Soi road project worth 3,500 billion VND is accelerating construction, but is still facing site clearance issues, affecting progress.

Approaching completion deadline, 3 transportation projects worth more than 2 trillion VND are still facing site clearance issues

|

Can Tho - There are only about 6 months left to reach the target according to the plan, but 3 key transport projects have not yet been able to open the route due to site clearance obstacles.

2 projects worth more than 16,000 billion VND in Ho Chi Minh City entangled with land for 132 households

|

Ho Chi Minh City - 2 canal and ditch renovation projects with a total investment of more than 16,000 billion VND are facing difficulties due to site clearance issues for 132 households, affecting construction progress.

Assoc. Prof. Dr. Bui Hoai Son talks about the controversy surrounding Son Tung M-TP standing on a Lac bird

|

Images of Son Tung M-TP standing on a model of a Lac bird in the MV "Come My Way" are creating many mixed opinions.

Knowing how to swim alone is not enough to protect children from summer drowning

|

Many tragic drowning cases in children recently show that just knowing how to swim is not enough to protect children from the risk of water accidents, especially during the summer.

Literature exam for 10th grade in Hanoi: Good and excellent students can get 8 points

|

The Literature exam for the 10th grade entrance exam in Hanoi in the 2026-2027 school year is assessed to maintain stability in structure, while enhancing topicality and differentiation ability.

Will soon decide on an agreement with Iran

|

Mr. Trump said he would soon make a decision on the proposal for an agreement to extend the ceasefire with Iran.

3,500 billion VND transportation project in Quang Ngai entangled with site clearance

ĐÔNG GIANG |

Quang Ngai - The Hoang Sa - Doc Soi road project worth 3,500 billion VND is accelerating construction, but is still facing site clearance issues, affecting progress.

Approaching completion deadline, 3 transportation projects worth more than 2 trillion VND are still facing site clearance issues

Tạ Quang |

Can Tho - There are only about 6 months left to reach the target according to the plan, but 3 key transport projects have not yet been able to open the route due to site clearance obstacles.

2 projects worth more than 16,000 billion VND in Ho Chi Minh City entangled with land for 132 households

MINH QUÂN |

Ho Chi Minh City - 2 canal and ditch renovation projects with a total investment of more than 16,000 billion VND are facing difficulties due to site clearance issues for 132 households, affecting construction progress.