Land clearance problems, a series of trillion-dong projects in Thai Nguyen are behind schedule

Việt Bắc |

Thai Nguyen - The inability to clear land and resettle people has affected the construction process and progress of the projects.

The Quang Vinh 1 and Quang Vinh 2 bridge projects across the Cau River in the center of Thai Nguyen province have a total investment of more than 1,500 billion VND. The project will start construction in early 2025, of which the length of Quang Vinh 1 (3.45km) and Quang Vinh 2 bridge (2.38km). The total area of land recovered to serve the project is more than 17 hectares.

Recorded by PV on December 21 at the Quang Vinh 2 bridge construction site, workers and machinery are carrying out bored and founded drilling. The items in the project are mainly deployed on the riverbank.

Nhieu ho dan chua di doi tai du an cau Quang Vinh 2. Anh: Viet Bac
Many households have not relocated at the Quang Vinh 2 bridge project. Photo: Viet Bac

At the connection point with the Ben Tuong bridge axis, site clearance is still in disarray. Residential houses have not yet been cleared. For this reason, there is no access road to the construction site, so we have to go around the river bank.

Ms. Nguyen Thi Ban (Linh Son ward) said that her family is subject to relocation to serve the Quang Vinh 2 bridge project. It is expected to be compensated more than 1 billion VND. However, the family has not yet relocated because they have not been resettled.

"There are about 20 households around here. Some have received compensation and resettlement land. My family has not been able to move yet because we do not have a new place to live. Only when I receive the money and have a new place to live with a full red book will I move," said Ms. Ban.

Speaking to Lao Dong Newspaper, Mr. Nguyen Van The - Deputy Head of the Quang Vinh 2 Bridge Construction Team (Licogi Company 18) said that at the starting point of the project adjacent to Ben Tuong Bridge, the construction unit has almost not yet handed over the site. Therefore, it is necessary to construct items on the riverbank.

"The road leading to the bridge still has no site clearance. The road to the construction site must be rented as a roundabout around the people's land.

The progress of the project is affected, and at many times the flood water rises, construction cannot be carried out. At the meetings, the unit also proposed to hand over the clean site soon," said Mr. The.

Duong dan vao cong truong du an cau Quang Vinh 2. Anh: Viet Bac
Road leading to the construction site of Quang Vinh 2 bridge project. Photo: Viet Bac

At the Quang Vinh 1 bridge project, the construction progress has only reached about 31%, the connecting road has not been implemented yet. Meanwhile, the number of households needing to be relocated is large, and the resettlement rate is still very low.

Regarding this issue, Chairman of Thai Nguyen Provincial People's Committee Vuong Quoc Tuan has requested Quan Trieu ward to divide into 2 peak periods for site clearance for resettlement areas from now until Lunar New Year and in the first quarter of 2026.

At the same time, temporary housing policies will be flexibly applied. Strive to have resettlement land to allocate land to people by August 30, 2026, creating conditions to speed up the project's progress.

Land clearance problems also occurred at the Ring Road I Project. The project is 14.1km long, starting at Bo Dau ( Vo Tranh commune), ending at Linh Nham bridge (Dong Hy). The total investment of the project is over 1,152 billion VND.

According to PV at the Son Cam bridge construction area, many households within the construction area have not been relocated. People's houses are still blocking the construction site.

Nhieu ho dan van chua di doi tai Du an duong Vanh dai I. Anh: Viet Bac
Many households have not yet relocated at the Ring Road I Project. Photo: Viet Bac

The section passing through Dong Hy commune still has 26 households that need to be resettled. Meanwhile, the section through Vo Tranh commune and Quan Trieu ward, where the new Son Cam bridge is being built, has reached 42,2% of the construction volume, 6 months behind schedule.

Chairman of Thai Nguyen Provincial People's Committee Vuong Quoc Tuan has requested Dong Hy commune to urgently complete the approval of the plan for all households subject to resettlement before December 30. Deploy temporary housing support, no later than January 10, 2026, hand over 100% of the site.

In the Son Cam bridge construction area, localities must complete site clearance for resettlement before Tet, no later than the first quarter of 2026.

Việt Bắc
RELATED NEWS

In 2025, the Ministry of Construction has set many records for the project

|

Speaking at the summary conference of the Ministry of Construction on December 21, Deputy Prime Minister Tran Hong Ha emphasized that in 2025, the Ministry has set many records for the project.

Gia Lai reviews and handles projects at risk of loss and waste

|

Gia Lai - Energy projects, urban areas... have been pointed out by the Inspectorate for many violations and problems leading to the risk of waste.

Removing obstacles for Kosy's notorious urban area project in Bac Ninh

|

Bac Ninh - Vice Chairman of the Provincial People's Committee Pham Van Thinh has just organized a working session to resolve difficulties and problems in the Kosy new urban area project.

Him Lam, Vinaconex are on the list of inspectors in 2026

|

Some investors and projects are included in the 2026 inspection plan of the Government Inspectorate.

Hanoi reclaims land, clears land to build Tran Hung Dao bridge

|

Hanoi - It is expected that there will be about 640 households subject to land acquisition and site clearance to build Tran Hung Dao bridge, with a total capital of VND 16,226 billion.

The Central Executive Committee of the Vietnam Young Physicians Association, course V, has 89 members

|

Ms. Bui Thi Minh Hoai - Politburo member, Secretary of the Party Central Committee, Chairwoman of the Central Committee of the Vietnam Fatherland Front attended the 5th National Congress of the Vietnam Young Physicians Association, term 2025 - 2030.

Ending the 886 billion VND flood control project after 16 years of unfinished

|

Ha Tinh - The Provincial People's Committee has just decided to terminate the project of the canal system for water separation, flood division, and flood prevention for communes in the south of Ky Anh after 16 years of unfinished work.

Securities waiting for cash flow's spread signal

|

The stock market returns to check the psychological resistance zone of 1,700 points according to the scenario of cash flow circulation between industry groups.

In 2025, the Ministry of Construction has set many records for the project

Xuyên Đông |

Speaking at the summary conference of the Ministry of Construction on December 21, Deputy Prime Minister Tran Hong Ha emphasized that in 2025, the Ministry has set many records for the project.

Gia Lai reviews and handles projects at risk of loss and waste

THANH TUẤN |

Gia Lai - Energy projects, urban areas... have been pointed out by the Inspectorate for many violations and problems leading to the risk of waste.

Removing obstacles for Kosy's notorious urban area project in Bac Ninh

Vân Trường |

Bac Ninh - Vice Chairman of the Provincial People's Committee Pham Van Thinh has just organized a working session to resolve difficulties and problems in the Kosy new urban area project.