crossing mountains and forests to connect the 500kV Lao Cai - Vinh Yen transmission line

Nhóm PV |

During the holidays, thousands of workers are still working hard to erect poles and pull ropes to soon open the entire 500kV Lao Cai - Vinh Yen route.

While many people are resting on the occasion of National Day 2.9, on the rugged mountain slopes and harsh terrain, the construction unit of the 500kV Lao Cai - Vinh Yen transmission line project is still working busily

The most difficult and complicated construction locations in the mountainous province of Lao Cai are VT04 pillars, workers and engineers are assembling the final steel bars to complete the pillar body and preparing specialized equipment and means to be ready for cable stretching and pulling.

Cong nhan dinh vi day moi.
Workers position the hook ropes. Photo: Van Duc

The service road from the foot of the hill to the construction site is deeply repeated with the chain reaction of excavators and cranes. Previously, workers had to use 2 excavators to "pull" the 120-ton crane down the slope to the construction site.

They crossed forests and mountains to transport steel parts and electric poles to each foundation location, and erected poles in the middle of the high mountains. The trucks were slowly "pulling up the slope" to bring materials to the right construction site.

Cong nhan lap rap thi cong cot thep ong. Anh: Van Duc
Workers assemble the construction of steel pipes. Photo: Van Duc

At the locations of poles from 100 to 113, in recent days, machinery has been mobilized to support workers in pulling the ropes.

Each coil of electric wire is more than 2km long, weighing nearly 5 tons, if the wire is not spread well, leaving it crossed together will cost the whole day to remove. To stretch ropes and hang ropes to the top of a pole, it requires experienced people and the use of a winch.

Spreading 500kV wires and pulling them across rivers and mountains is a difficult period for the electricity industry, this job requires workers to be both healthy and resilient and have experience to do it, said Mr. Vu Quang Chien (Lam Dong power transmission team, Power transmission Company 3).

Don vi thi cong su dung may toi de rai day, treo day len dinh cot. Anh: Van Duc
The construction unit used a winch to spread the rope and hung the rope to the top of the pole. Photo: Van Duc

Mr. Nguyen Duy Hung - Director of Hung Phu Thinh Power Construction Company said that contractors are currently mobilizing maximum forces, focusing on completing the installation of poles while the power transmission unit is transporting wires and cables to the locations.

As soon as the pole erection is completed, the construction unit will coordinate with the army to run ropes connecting the poles, expected to be completed in the next 10 days.

"On holidays, we also miss home very much, but because we know that work is urgent, everyone encourages each other to try. I just hope to complete the power on schedule, that is also my joy," said Mr. Hung.

Cong nhan miet mai, hang say lao dong de hoan thanh cac cot mong cuoi cung duong day 500kV Lao Cai - Vinh Yen. Anh: Van Duc
Cong nhan miet mai, hang say lao dong de hoan thanh cac cot mong cuoi cung duong day 500kV Lao Cai - Vinh Yen. Anh: Van Duc
Workers are working hard and enthusiastically to complete the final foundations of the 500kV Lao Cai - Vinh Yen line. Photo: Van Duc

Speaking to Lao Dong Newspaper, Mr. Do Quang Khai, Deputy Director of the Power 1 Project Management Board and Director of the Lao Cai - Vinh Yen 500kV Line Project Management Board, said that during the September 2 National Day holiday, construction units will still increase maximum machinery and human resources to complete the final items.

"The entire route is working in a spirit of water retreat. Every day, construction teams and units try to overcome difficulties to complete the project as soon as possible" - Mr. Do Quang Khai emphasized.

The 500kV Lao Cai - Vinh Yen transmission line project is invested by Vietnam Electricity Group (EVN) with a total investment of more than VND 7,410 billion, a length of 230km

This is a national key energy project, of great significance in ensuring the country's energy security. When completed, the project will contribute to bringing electricity from major energy centers in the Northwest region into the national transmission system, strengthening regional connectivity, and ensuring energy security for the entire North.

Nhóm PV
RELATED NEWS

Encouraging workers to construct the 500Kv Lao Cai - Vinh Yen line

|

The working delegation of the EVN Party Committee and the Vietnam Electricity Trade Union came to encourage workers constructing the 500Kv Lao Cai - Vinh Yen transmission line.

Forests, mountains, and mountains will be built towers for the 500kV Lao Cai - Vinh Yen power line

|

To transport steel, cables, and electric poles to the foundation and erect poles for the 500kV Lao Cai - Vinh Yen line, trucks had to move each section over the slope.

Urgently constructing the 500 kV Lao Cai - Vinh Yen transmission line project before the rainy season

|

Lao Cai - Faced with the pressure of the upcoming storm season, contractors are speeding up the installation of steel poles for the 500kV Lao Cai - Vinh Yen transmission line to ensure the set progress.

Uncle Ho's bodyguards were moved when witnessing the historic parade in Ba Dinh

|

Hanoi - Witnessing the historic parade at Ba Dinh Square on the morning of September 2, Mr. Le Binh (98 years old) could not help but be moved.

Countries send telegrams and letters congratulating Vietnam National Day

|

On the occasion of the 80th anniversary of Vietnam's National Day, Leaders of the countries sent telegrams and congratulatory letters to the leaders of the Party and State of Vietnam.

crossing mountains and forests to connect the 500kV Lao Cai - Vinh Yen transmission line

|

During the holidays, thousands of workers are still working hard to erect poles and pull ropes to soon open the entire 500kV Lao Cai - Vinh Yen route.

A80 parade: Happiness filled the air as seen from hospital windows

|

Hundreds of patients and their families from all departments of Xanh Pon General Hospital are looking at the windows to witness the A80 parade groups.

The female Major said that she felt the biggest pressure when she was the one who explained the opening ceremony of the A80 parade

|

As one of 13 people participating in the explanation team at the A80 mission, Major Ngoc Vu shared with Lao Dong reporter about the pressures, pride and emotions.

Encouraging workers to construct the 500Kv Lao Cai - Vinh Yen line

Đắc Cường |

The working delegation of the EVN Party Committee and the Vietnam Electricity Trade Union came to encourage workers constructing the 500Kv Lao Cai - Vinh Yen transmission line.

Forests, mountains, and mountains will be built towers for the 500kV Lao Cai - Vinh Yen power line

Nhóm PV |

To transport steel, cables, and electric poles to the foundation and erect poles for the 500kV Lao Cai - Vinh Yen line, trucks had to move each section over the slope.

Urgently constructing the 500 kV Lao Cai - Vinh Yen transmission line project before the rainy season

Đinh Đại |

Lao Cai - Faced with the pressure of the upcoming storm season, contractors are speeding up the installation of steel poles for the 500kV Lao Cai - Vinh Yen transmission line to ensure the set progress.