Provincial road construction contractor accused of causing pollution and unsafety

LAM HỒNG |

Lam Dong - The construction of Provincial Road DT725 in Loc Ngai commune is spreading dust, uncovered manholes, posing a potential safety risk to students and people.

Causing anxiety

Previously, on DT725 road through Loc Ngai commune, Bao Lam district (from km 98+600 to km 99+400), there were many shortcomings such as narrow roads, frequent flooding and many dangerous turns.

In response to voters' feedback, Lam Dong Provincial People's Committee assigned the Department of Transport (now the Department of Construction) to inspect and propose a renovation plan.

Mot bi cong nam cheo leo tren dong dat co the lan xuong bat cu luc nao, tiem an nguy hiem cho nguoi va phuong tien tham gia giao thong. Anh: Lam Hong
A culvert can be hidden on a pile of soil at any time, posing a potential danger to people and vehicles participating in traffic (photo taken on March 19, 2025). Photo: Lam Hong

After that, the Department of Construction was assigned to be the investor, implementing the project to repair the road surface, asphalt concrete and renovate the drainage system. The project is represented by the Road Maintenance Management Board (under the Department of Construction).

The project started on December 9, 2024, constructed by a joint venture of Nguyen Loi Construction - Trading - Service Company Limited and Dong Luong Group Joint Stock Company, with a winning bid value of VND 8.498 billion.

When the project was implemented, local people were very excited. However, the contractor's construction process was very sluggish, causing people to worry.

Nhieu bi cong de xep chong cheo leo ngay truoc cong truong Tieu hoc Dinh Tien Hoang gay nguy hiem cho hang tram hoc sinh. Anh: Lam Hong
Many culverts are piled up right in front of Dinh Tien Hoang Primary School, endangering hundreds of students (photo taken on March 19, 2025). Photo: Lam Hong

Actual research shows that there are hundreds of households living on both sides of the road in the construction area. In addition, there are also the headquarters of the People's Committee of Loc Ngai commune, Dinh Tien Hoang Primary School and Sao Mai Kindergarten.

However, the construction unit has not ensured labor safety and environmental sanitation. Dozens of sewers are placed in steep locations, at risk of falling at any time.

In particular, right in front of the gate of Dinh Tien Hoang Primary School, more than 10 sewers were piled up, posing a potential safety risk to students and people.

Mot ho ga chua che chan bai ban truoc cong truong hoc mam non. Anh: Lam Hong
A manhole is not properly covered in front of the gate of the kindergarten (photo taken on March 19, 2025). Photo: Lam Hong

Mr. Tran Van Duan - Principal of Dinh Tien Hoang Primary School said that these sewers have existed for nearly two months now.

The school has repeatedly reported to the local authorities and the construction unit, but it has not been handled yet. Therefore, the school had to assign teachers to be on duty in front of the school gate during peak hours to instruct students to stay away from dangerous areas.

"We hope the construction unit will soon relocate the sewers to ensure the safety of the students," Mr. Tran Van Duan added.

Impact on people's lives

Irresponsible construction not only poses a potential risk to traffic safety but also pollutes the environment, greatly affecting the lives of many local people.

Mr. Hung Cu, a resident of Loc Ngai commune, shared: "We support the project, even donate land so that the project can be completed soon. However, the construction unit works irresponsibly, such as not watering water to prevent dust, vehicles carrying soil do not cover with tarpaulins, and manholes do not cover, endangering road users".

 Xe don vi thi cong van chuyen dat da khong che chan gay mat an toan giao thong va phat tan bui bam. Anh: Lam Hong
Vehicles of the construction unit transporting soil and rock without covering cause traffic insecurity and spread dust (photo taken on March 19, 2025). Photo: Lam Hong

Similarly, Mr. Dam Van Dan, another resident, was upset: "We are ready to hand over the land to build a road, but the construction unit lacks cooperation. They dig like a deserted place, ignore people's opinions and even challenge and threaten."

On the side of the local government, Mr. Nguyen Duc Cuong - Chairman of the People's Committee of Loc Ngai commune (Bao Lam district) said that the shortcomings in the construction process of this project are very clear. People's opinions and reflections related to the shortcomings and problems of the construction unit are well-founded.

"The commune will invite the construction unit and the people to work to reach an agreement to avoid affecting people's lives and the progress of the project," affirmed Mr. Nguyen Duc Cuong - Chairman of Loc Ngai Commune People's Committee.

LAM HỒNG
TIN LIÊN QUAN

Stewed ground, 11,000 billion VND expressway still bustling for construction

|

Lang Son - Despite many problems with the site clearance, the Huu Nghi - Chi Lang expressway is being vigorously implemented to reach the finish line on time.

Thang Long Avenue is congested due to construction barriers

|

Hanoi - Due to the construction of underground cables, the area of the Thang Long - Trung Van Boulevard intersection often experiences traffic congestion, especially during rush hours.

Households have cracked houses due to unfavorable compensation levels for highway construction

|

Ha Tinh - After proposing compensation for households with houses and constructions cracked and affected by the construction of the North - South expressway, some households have not yet agreed.

Pork prices in Can Tho stagnate but remain high

|

Can Tho - In the face of increased pork prices, consumers are considering choosing alternative foods to tighten spending.

Enterprises increase wages, 72 workers end work stoppages

|

Nghe An - The collective work stoppage at Zonsen International Packaging Company Limited - Nghe An Branch ended when the enterprise agreed to increase salaries.

Transferring forces when removing the District Military Command

|

The Central Military Commission Standing Committee has just held a conference to review and comment on the draft Project on the local military organization "refined, compact, and strong".

Unprecedented thing before the Call Me by Fire concert

|

On the afternoon of March 22, thousands of audiences wearing traditional costumes attended the Call Me by Fire concert in Ho Chi Minh City.

National Data Association urgently implements 7 tasks

|

The Chairman of the National Data Association affirmed that he would accept the direction of General Secretary To Lam, in which 7 tasks need to be focused on implementation.

Stewed ground, 11,000 billion VND expressway still bustling for construction

Khánh Linh |

Lang Son - Despite many problems with the site clearance, the Huu Nghi - Chi Lang expressway is being vigorously implemented to reach the finish line on time.

Thang Long Avenue is congested due to construction barriers

Minh Hạnh |

Hanoi - Due to the construction of underground cables, the area of the Thang Long - Trung Van Boulevard intersection often experiences traffic congestion, especially during rush hours.

Households have cracked houses due to unfavorable compensation levels for highway construction

TRẦN TUẤN |

Ha Tinh - After proposing compensation for households with houses and constructions cracked and affected by the construction of the North - South expressway, some households have not yet agreed.